IDBLD_0101977 floorsCompleted
7Sanctioned habitable floorsregistration certificate
29 Jun 2022Revised completionpromised 30 Dec 2021

Floors

7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51500006059 · registered 14 Aug 2017
Promised completion
30 Dec 2021
Revised completion
29 Jun 2022
Sanctioned habitable floors
7

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1 RK19.4 m² (209 sq.ft)4not published
FLAT 1 BHK30 m² (323 sq.ft)4not published
FLAT 1 BHK31.4 m² (337 sq.ft)4not published
FLAT 1 BHK31.5 m² (339 sq.ft)4not published
FLAT 1 BHK33.5 m² (361 sq.ft)4not published
FLAT 1 BHK34.5 m² (371 sq.ft)4not published
Total24

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00060
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through10 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology