Uday Nagar -Layout B

Completed

Amravati (M Corp.), Amravati 444601 |Promoter: Poonam Devendra Chandak

20 Nov 2017Registered with MahaRERA
31 Oct 2019Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Completed
Land area for this project
6,100 sq m (65,660 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
610 sq m (6,566 sq ft)
Address
131PIN 444601
Designated bank account
Bank Of Maharashtra
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.94164, 77.75093
Uday Nagar -Layout B is at latitude 20.94164, longitude 77.75093.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Oct 2019

The latest completion date on record passed 7 years ago.

Registered
20 Nov 2017
Promised
31 Oct 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030001428920 Nov 201731 Oct 2019—Poonam Devendra ChandakProject page

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsAS PER PLAN0%
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER PLAN0%
  • Street LightingAS PER PLAN0%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER PLAN0%
  • Aggregate area of recreational Open SpaceAS PER PLAN0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

10 documents held by Deedo, 14 filings listed on MahaRERA's project page

Title

Encumbrance

Form b

Registration certificate

Form 5

Form 4

Other

Layout plan

Commencement certificate

Allotment letter

Document library

  • Details of encumbrancesPoonam_EC.pdf · uploaded 15 Nov 2017View
  • Copy of Layout Approval (in case of layout)Poonam_Map.pdf · uploaded 15 Nov 2017View
  • Building Plan Approval (IOD)Poonam_Technical.pdf · uploaded 15 Nov 2017View
  • Declaration in FORM BPoonam_B.pdf · uploaded 15 Nov 2017View
  • Proforma of Allotment letterPoonam_ATS.pdf · uploaded 15 Nov 2017View
  • Copy of the legal title reportPoonam_Legal Report.pdf · uploaded 15 Nov 2017View
  • Commencement Certificates / NA Order for plotted developmentPoonam_Technical.pdf · uploaded 27 Mar 2018View
  • Certificates of CA (Form 5)POONAM CHANDAK.pdf · uploaded 29 Sep 2018View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4-P D CHANDAK.pdf · uploaded 1 Feb 2020View

Promoter documents

  • Declaration Form BPoonam_B.pdf · uploaded 15 Nov 2017View
  • Legal Title reportPoonam_Legal Report.pdf · uploaded 15 Nov 2017View

Technical documents

  • Layout ApprovalPoonam_Map.pdfView
  • NA Order for Plotted DevelopmentPoonam_Technical.pdfView

Proforma allotment letter

  • Proforma allotment letterPoonam_ATS.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

131

As published on MahaRERA's project page

131

Boundaries

North
Land S No 129
South
Land S No 131
East
Land S No 131
West
Land S No 131

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArun Bijwe—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology