Completed

Amravati (M Corp.), Amravati 444603 |Promoter: Nitin Sahebrao Umap

9 Oct 2017Registered with MahaRERA
30 Jun 2019Promised completion
29 Dec 2020Revised completionPushed back 1 year and 6 months
1Building
17Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
1BHK, 2BHK, Office17 units in all
Land area for this project
531 sq m (5,713 sq ft)
Permissible built-up area
793 sq m (8,536 sq ft)
Sanctioned built-up area
743 sq m (7,998 sq ft)
Address
25b, 26a And 26bPIN 444603
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.52928, 73.94571
Shree Gurudev Residency is at latitude 18.52928, longitude 73.94571.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 5 years and 10 months ago.

Registered
9 Oct 2017
Promised
30 Jun 2019
Revised
29 Dec 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P503000135489 Oct 201730 Jun 201929 Dec 2020Nitin Sahebrao UmapProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shree Gurudev Residency517

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

17 units registered

1BHK · 3 units2BHK · 12 unitsOffice · 2 units
TypeCarpet areaUnits
1BHK32.05 sq m · 345 sq ft3
2BHK38.84 sq m · 418 sq ft2
2BHK38.88 sq m · 419 sq ft2
2BHK39.8 sq m · 428 sq ft4
2BHK44.25 sq m · 476 sq ft4
Office10.63 sq m · 114 sq ft1
Office10.66 sq m · 115 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shree Gurudev Residency

  • Excavation100%
  • Basement (if any)70%
  • Podiums (if any)0%
  • Plinth70%
  • Stilt Floor50%
  • Slabs of Super Structure40%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAS PER MAP0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER MAP0%
  • Storm Water DrainsAS PER MAP0%
  • Landscaping & Tree PlantingAS PER MAP0%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER MAP0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER MAP0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

18 documents held by Deedo, 20 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificate

Form b

Allotment letters

Form 1s

Form 2s

Registration certificate

Form 5

Extension certificate

Form 4

Others

Layout plan

Document library

  • Copy of the legal title reportSEARCH REPOET.pdf · uploaded 15 Sep 2017View
  • Details of encumbrancesIN.pdf · uploaded 16 Sep 2017View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 16 Sep 2017View
  • Declaration in FORM BFORM B.pdf · uploaded 16 Sep 2017View
  • Proforma of Allotment letterUNDERTAKING.pdf · uploaded 16 Sep 2017View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 16 Sep 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)art.pdf · uploaded 23 Sep 2017View
  • Building Plan Approval (IOD)LAYOUT.pdf · uploaded 23 Sep 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 23 Sep 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 26 Sep 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)111.pdf · uploaded 14 Apr 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)NITIN FORM 2.pdf · uploaded 14 Apr 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)4-5.pdf · uploaded 20 Apr 2018View
  • Certificates of CA (Form 5)NITIN .pdf · uploaded 6 Nov 2018View
  • Architect’s Certificate on Completion of Project (Form 4)UMAPFORM4.pdf · uploaded 18 Jan 2021View

Promoter documents

  • Legal Title reportSEARCH REPOET.pdf · uploaded 15 Sep 2017View
  • Declaration Form BFORM B.pdf · uploaded 16 Sep 2017View

Technical documents

  • Building Plan ApprovalLAYOUT.pdfView
  • Layout ApprovalLAYOUT.pdfView

Proforma allotment letter

  • Proforma allotment letterUNDERTAKING.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

25B26A26B

As published on MahaRERA's project page

25B,26A AND 26B

Boundaries

North
Another Layout
South
9 Mtr Road
East
Plot No 27-A
West
Plot No 25-A

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmol Sabale—
EngineerPankaj Deshmukh—
EngineerSanjay Chetule—
OtherAnant Maldhure—
OtherVilas Sahare—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology