Shivanand Heights

Completed

Amravati (M Corp.), Amravati 444606 |Promoter: Shivanand Infrastructure

Residential / Group HousingRERAP50300005800
14 Aug 2017Registered with MahaRERA
21 Aug 2020Promised completion
20 Feb 2023Revised completionPushed back 2 years and 6 months
1Building
30Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
3BHK, 4BHK, Shop30 units in all
Land area for this project
550 sq m (5,920 sq ft)
Permissible built-up area
2,505 sq m (26,961 sq ft)
Sanctioned built-up area
1,252 sq m (13,481 sq ft)
Address
27PIN 444606
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.52960, 73.87602
Shivanand Heights is at latitude 18.52960, longitude 73.87602.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years and 6 months

The latest completion date on record passed 3 years and 8 months ago.

Registered
14 Aug 2017
Promised
21 Aug 2020
Revised
20 Feb 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030000580014 Aug 201721 Aug 202020 Feb 2023Shivanand InfrastructureProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shivanand Heights830

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

30 units registered

3BHK · 6 units4BHK · 6 unitsShop · 18 units
TypeCarpet areaUnits
3BHK95.29 sq m · 1,026 sq ft6
4BHK106.77 sq m · 1,149 sq ft6
Shop8.89 sq m · 96 sq ft2
Shop9.23 sq m · 99 sq ft2
Shop9.69 sq m · 104 sq ft4
Shop9.73 sq m · 105 sq ft4
Shop9.76 sq m · 105 sq ft2
Shop11.28 sq m · 121 sq ft1
Shop11.29 sq m · 122 sq ft1
Shop18.47 sq m · 199 sq ft2

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shivanand Heights

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMPLETETD100%
  • Storm Water DrainsCOMPLETETD100%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterCOMPLETETD100%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMPLETETD100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsCOMPLETED100%
  • Electrical meter room, sub-station, receiving stationCOMPLETED100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

27 documents held by Deedo, 29 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificates

Form b

Form 1s

Form 2s

Form 5s

Registration certificate

Form 2as

Others

Extension certificate

Completion

Form 4

Layout plan

Building plan

Allotment letter

Document library

  • Copy of the legal title reporttitle report.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesnon encumbrance.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)layout map.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterAGREEMENT TO SELL.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)SANCTION MAP.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BNOTARY.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH CERT.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG CERT.pdf · uploaded 31 Jul 2017View
  • Certificates of CA (Form 5)SHIVA.pdf · uploaded 15 Oct 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 2018-19.pdf · uploaded 17 Feb 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 2019-20.pdf · uploaded 17 Feb 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 2020-21.pdf · uploaded 17 Feb 2022View
  • Declaration about Commencement CertificateCC DECLARATION.pdf · uploaded 17 Feb 2022View
  • CERSAI detailsCERSAI_Search_Report_200230459157_For_Asset_Based_Search_17_02_2022_15_18_19_026.pdf · uploaded 17 Feb 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 2018.pdf · uploaded 17 Feb 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 2019.pdf · uploaded 17 Feb 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 2020.pdf · uploaded 17 Feb 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 2021.pdf · uploaded 17 Feb 2022View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1-compressed (3).pdf · uploaded 17 Feb 2022View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2-compressed (4).pdf · uploaded 17 Feb 2022View
  • Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 17 Feb 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc.pdf · uploaded 27 Feb 2023View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 27 Feb 2023View

Promoter documents

  • Legal Title reporttitle report.pdf · uploaded 31 Jul 2017View
  • Declaration Form BNOTARY.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout Approvallayout map.pdfView
  • Building Plan ApprovalSANCTION MAP.pdfView

Proforma allotment letter

  • Proforma allotment letterAGREEMENT TO SELL.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

27

As published on MahaRERA's project page

27

Boundaries

North
Plot No 26
South
Road
East
Old By Pass Road
West
Plot No 28

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShrikant Hinge—
EngineerMangesh Gulhane—
OtherHariprasad Katare—
OtherIkram Khan—

Source: MahaRERA project page. Contact details are not shown.