Shalini Residency
LapsedAmravati (M Corp.), Amravati 444606 |Promoter: Vijayshali Enterprises Privatye Limited
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Lapsed
- Buildings
- 1
- Land area for this project
- 368 sq m (3,966 sq ft)
- Permissible built-up area
- 1,076 sq m (11,579 sq ft)
- Sanctioned built-up area
- 1,076 sq m (11,579 sq ft)
- Planning authority
- AMRAVATI MUNCIPAL CORPORATION
- Address
- Plot No 18 Part (18b) & 19survey No 2 Mauje Benoda (19a+19b), 0, BenodaPIN 444606
- Designated bank account
- State Bank Of India
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2026
The latest completion date on record passed 7 months ago.
- Registered
- 24 Feb 2023
- Promised
- 31 Mar 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50300049786 | 24 Feb 2023 | 31 Mar 2026 | — | Vijayshali Enterprises Privatye Limited | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| A-1 | 6 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 23 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
A-1
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
35 documents held by Deedo, 72 filings listed on MahaRERA's project page
Commencement certificates
Others
- Other14 Jan 2023ViewSource
- Other18 Feb 2023ViewSource
- Other7 Aug 2025ViewSource
- Other7 Aug 2025ViewSource
- Other7 Aug 2025ViewSource
- Other7 Aug 2025ViewSource
- Other20 Aug 2025ViewSource
- Other20 Aug 2025ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Form 1s
Form 2s
Document library
- a Details of encumbrances concerned to FinanceVijayshali_Encumberance.pdf · uploaded 27 Dec 2022View
- b Details of encumbrances concerned to LegalVijayshali_Encumberance.pdf · uploaded 27 Dec 2022View
- Copy of Layout Approval (in case of layout)Vijayshali_NA Order_compressed.pdf · uploaded 27 Dec 2022View
- Commencement Certificates / NA Order for plotted developmentVijayshali_Commencement_compressed.pdf · uploaded 27 Dec 2022View
- Declaration about Commencement CertificateVijayshali_Format D Commencment.pdf · uploaded 27 Dec 2022View
- Declaration in FORM BVijayshali_Form B.pdf · uploaded 27 Dec 2022View
- Proforma of Allotment letterVijayshali_Allotment Letter_compressed.pdf · uploaded 27 Dec 2022View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameVijayshali_Format A Bank.pdf · uploaded 27 Dec 2022Source
- Deviation Report with respect to Allotment letterVijayshali_Deviation Allotment Letter.pdf · uploaded 27 Dec 2022Source
- Deviation Report with respect to model copy of AgreementVijayshali_Deviation AGreement for Sale.pdf · uploaded 27 Dec 2022Source
- Disclosure of Interest in Other Real Estate OrganizationsAnnex A-Anupreet.pdf · uploaded 14 Jan 2023Source
- Disclosure of Interest in Other Real Estate OrganizationsAnnex A-Shalini.pdf · uploaded 14 Jan 2023Source
- Disclosure of Interest in Other Real Estate OrganizationsAnnex A-Shriya.pdf · uploaded 14 Jan 2023Source
- Building Plan Approval / NA Order for plotted developmentVijayshali_Sanction Map.pdf · uploaded 14 Jan 2023View
- CERSAI detailsVijayshali_Cersai.pdf · uploaded 14 Jan 2023View
- Copy of the legal title reportVIJAYSHALI SEARCH REPORT.pdf · uploaded 1 Feb 2023View
- Proforma of Agreement for saleTulip ATS RERA Updated.pdf · uploaded 18 Feb 2023View
- Commencement Certificates / NA Order for plotted developmentExtention letter.pdf · uploaded 18 Feb 2023View
- Other – TechnicalExtention letter.pdf · uploaded 18 Feb 2023View
- Building Plan Approval / NA Order for plotted developmentVijayshali_MAP.pdf · uploaded 18 Feb 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Shailini 31032023.pdf · uploaded 20 Oct 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Shailini 31032023.pdf · uploaded 20 Oct 2023View
- Disclosure of sold/ booked inventorySold Unsold_Shailini 31032023.pdf · uploaded 20 Oct 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_300623.pdf · uploaded 17 Jan 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_300623.pdf · uploaded 17 Jan 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_300923.pdf · uploaded 17 Jan 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_300923.pdf · uploaded 17 Jan 2024View
- Disclosure of sold/ booked inventorySold_300623.pdf · uploaded 17 Jan 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_311223.pdf · uploaded 17 Jan 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_311223.pdf · uploaded 17 Jan 2024View
- Disclosure of sold/ booked inventorySold_300923.pdf · uploaded 17 Jan 2024View
- Disclosure of sold/ booked inventorySold_311223.pdf · uploaded 17 Jan 2024View
- Form 1Form 1_Shailini 31032023.pdf · uploaded 7 Aug 2025View
- Form 2Form 2_Shailini 31032023.pdf · uploaded 7 Aug 2025View
- Disclosure of Sold and Booked InventorySold Unsold_Shailini 31032023.pdf · uploaded 7 Aug 2025View
- OthersForm 5_Shailini.pdf · uploaded 7 Aug 2025Source
- Form 1Form 1_300623.pdf · uploaded 7 Aug 2025View
- Form 2Form 2_300623.pdf · uploaded 7 Aug 2025View
- Disclosure of Sold and Booked InventorySold_300623.pdf · uploaded 7 Aug 2025View
- Form 1Form 1_300923.pdf · uploaded 7 Aug 2025View
- Form 2Form 2_300923.pdf · uploaded 7 Aug 2025View
- Disclosure of Sold and Booked InventorySold_300923.pdf · uploaded 7 Aug 2025View
- Form 1Form 1_311223.pdf · uploaded 7 Aug 2025View
- Form 2Form 2_311223.pdf · uploaded 7 Aug 2025View
- Disclosure of Sold and Booked InventorySold_311223.pdf · uploaded 7 Aug 2025View
- Form 1FORM-1 (31-03-24).pdf · uploaded 20 Aug 2025Source
- Form 2FORM-2 (31-03-24).pdf · uploaded 20 Aug 2025Source
- Disclosure of Sold and Booked InventoryVijayshali Sold Unsold_310324.pdf · uploaded 20 Aug 2025Source
- Form 1FORM-1 (30-06-24).pdf · uploaded 20 Aug 2025Source
- Form 2FORM-2 (30-06-24).pdf · uploaded 20 Aug 2025Source
- Disclosure of Sold and Booked InventoryVijayshali Sold Unsold_300624.pdf · uploaded 20 Aug 2025Source
- Form 1FORM-1 (30-09-24).pdf · uploaded 20 Aug 2025Source
- Form 2FORM-2 (30-09-24).pdf · uploaded 20 Aug 2025Source
- Disclosure of Sold and Booked InventoryVijayshali Sold Unsold_300924.pdf · uploaded 20 Aug 2025Source
- Form 1FORM-1 (31-12-24).pdf · uploaded 20 Aug 2025View
- Form 2FORM-2 (31-12-24).pdf · uploaded 20 Aug 2025View
- Disclosure of Sold and Booked InventoryVijayshali Sold Unsold_311224.pdf · uploaded 20 Aug 2025View
- Form 1FORM-1 (31-03-25).pdf · uploaded 20 Aug 2025View
- Form 2FORM-2 (31-03-25).pdf · uploaded 20 Aug 2025View
- Disclosure of Sold and Booked InventoryVijayshali Sold Unsold_310325.pdf · uploaded 20 Aug 2025View
- Withdrawal Update Form 1Form 1.pdf · uploaded 31 Mar 2026View
- Withdrawal Update Form 2Form 2.pdf · uploaded 31 Mar 2026View
- Withdrawal Update Form 1Form 1.pdf · uploaded 31 Mar 2026View
- Withdrawal Update Form 2Form 2.pdf · uploaded 31 Mar 2026View
- Withdrawal Update Form 1Form 1.pdf · uploaded 31 Mar 2026View
- Withdrawal Update Form 2Form 2.pdf · uploaded 31 Mar 2026View
Promoter documents
Technical documents
Proforma allotment letter
- Proforma allotment letterVijayshali_Allotment Letter_compressed.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Amravati (M Corp.), Amravati taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
PLOT NO 18 PART (18B) & 19SURVEY NO 2 MAUJE BENODA (19A+19B)
Boundaries
- North
- Road
- South
- Plot No 20
- East
- 18
- West
- 19
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Girish Krushnarao Nagpure | — |
| Chartered accountant | Ca Deepak Zambani G A D & Associates | — |
| Chartered accountant | Manish Nareshkumar Khushlani | — |
| Engineer | Amit Vishwasrao Mehare | — |
Source: MahaRERA project page. Contact details are not shown.