Skip to content
Deedo home
Menu

Rich County Apartment

Completed

Amravati (M Corp.), Amravati 444602 |Promoter: Nirmiti Construction

22 Mar 2018Registered with MahaRERA
30 Sep 2020Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Land area for this project
892 sq m (9,600 sq ft)
Permissible built-up area
979 sq m (10,537 sq ft)
Sanctioned built-up area
979 sq m (10,537 sq ft)
Recreational open space
892 sq m (9,600 sq ft)
Address
2081, Gadge nagar road, Near Gadge Maharaj MandirPIN 444602
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.03339, 78.95428
Rich County Apartment is at latitude 21.03339, longitude 78.95428.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Sep 2020

The latest completion date on record passed 6 years and 1 month ago.

Registered
22 Mar 2018
Promised
30 Sep 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030001574022 Mar 201830 Sep 2020—Nirmiti ConstructionProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Rich County Apartment5—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Rich County Apartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supply0100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)0100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And Disposal010%
  • Water conservation /Rain water harvesting0100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirements010%
  • Electrical meter room, sub-station, receiving station0100%
  • Aggregate area of recreational Open Space020%
  • Open Parking010%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 16 filings listed on MahaRERA's project page

Encumbrance

Commencement certificate

Title

Form b

Registration certificate

Form 1

Completions

Form 4

Others

Layout plan

Building plan

Allotment letter

Document library

  • Details of encumbrancesform b.pdf · uploaded 28 Feb 2018View
  • Proforma of Allotment letteragreemt to sale.pdf · uploaded 28 Feb 2018View
  • Building Plan Approval (IOD)LAYOUT MAP.pdf · uploaded 28 Feb 2018View
  • Copy of Layout Approval (in case of layout)MOZNI.pdf · uploaded 28 Feb 2018View
  • Commencement Certificates / NA Order for plotted developmentSACTION LETTER.pdf · uploaded 28 Feb 2018View
  • Copy of the legal title reporttitle report.pdf · uploaded 15 Mar 2018View
  • Declaration in FORM Brera fb.pdf · uploaded 15 Mar 2018View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 6 Feb 2023View
  • Architect’s Certificate on Completion of Project (Form 4)FORM4C.pdf · uploaded 23 Jun 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC23.pdf · uploaded 23 Jun 2023View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCCNIEMITI.pdf · uploaded 9 May 2024View

Promoter documents

  • Legal Title reporttitle report.pdf · uploaded 15 Mar 2018View
  • Declaration Form Brera fb.pdf · uploaded 15 Mar 2018View

Technical documents

  • Building Plan ApprovalLAYOUT MAP.pdfView
  • Layout ApprovalMOZNI.pdfView

Proforma allotment letter

  • Proforma allotment letteragreemt to sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

2081

As published on MahaRERA's project page

2081

Boundaries

North
Pasari House
South
Shoping complex
East
Service line
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectmehul vasavt shah—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology