Rachana Srushti

Lapsed

Amravati (M Corp.), Amravati 444602 |Promoter: Srushti Infra

11 Oct 2021Registered with MahaRERAFirst of 2 registrations
1 Dec 2025Promised completionLatest across registrations
2Buildings2 phases
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
RERA registrations
2
Phases
2
Buildings
2
Land area for this project
2,546 sq m (27,402 sq ft)
Permissible built-up area
11,171 sq m (1,20,239 sq ft)
Sanctioned built-up area
11,171 sq m (1,20,239 sq ft)
Planning authority
AMRAVATI MUNICIPAL CORPORATION
Address
Survey No 103/4 Plot No 24, Amravati University To Dental College Road, Srushti InfraPIN 444602
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.93717, 77.79530
Rachana Srushti is at latitude 20.93717, longitude 77.79530.

Also registered as

Rachana Srushti Phase II

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Sep 2024

P50300031176

The latest completion date on record passed 2 years and 1 month ago.

Registered
11 Oct 2021
Promised
30 Sep 2024

Completion promised for 1 Dec 2025

P50300049603

The latest completion date on record passed 10 months ago.

Registered
15 Feb 2023
Promised
1 Dec 2025

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030003117611 Oct 202130 Sep 2024—Srushti InfraProject page
P5030004960315 Feb 20231 Dec 2025—Srushti InfraProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Rachana Srushti13—
Rachana Srushti Phase II12—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Rachana SrushtiClosed/Covered00002
Rachana SrushtiOpen Space00001
Rachana Srushti Phase IIClosed/Covered00000
Rachana Srushti Phase IIOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Rachana Srushti

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rachana Srushti Phase II

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor70%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises45%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supply0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)as per plan0%
  • Storm Water Drainsas per plan0%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage Waterwork in progress0%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingat the time of completion of work0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsat the time of completion of work0%
  • Electrical meter room, sub-station, receiving stationat the time of completion of work0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parkingat the time of completion of work0%
  • gymgym having carpet area 41.80 sq.mt0%
  • club houseat the time of completion of work0%
  • Internal Roads & FootpathsNot applicable
  • Water SupplyAT THE TIME OF COMPLETION0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN0%
  • Storm Water DrainsAS PER PLAN0%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterAT THE TIME OF COMPLETION0%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAT THE TIME OF COMPLETION0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsAT THE TIME OF COMPLETION0%
  • Electrical meter room, sub-station, receiving stationAT THE TIME OF COMPLETION0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingAT THE TIME OF COMPLETION0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

77 documents held by Deedo, 150 filings listed on MahaRERA's project page

Encumbrances

Commencement certificates

  • Commencement certificateP50300031176 · 21 Sep 2021ViewSource
  • Commencement certificateP50300031176 · 2 Oct 2021ViewSource
  • Commencement certificateP50300049603 · 13 Dec 2022ViewSource
  • Commencement certificateP50300049603 · 13 Dec 2022ViewSource

Form bs

Form 2s

Title

Registration certificates

  • Registration certificateP50300031176 · 11 Oct 2021ViewSource
  • Registration certificateP50300049603 · 15 Sep 2026ViewSource

Form 1s

Form 5s

Completions

Others

Form 2as

Layout plan

Building plans

  • Building planP50300031176 · Date not statedViewSource
  • Building planP50300031176 · Date not statedViewSource
  • Building planP50300031176 · Date not statedViewSource
  • Building planP50300049603 · Date not statedViewSource
  • Building planP50300049603 · Date not statedViewSource
  • Building planP50300049603 · Date not statedViewSource
  • Building planP50300049603 · Date not statedViewSource
  • Building planP50300049603 · Date not statedViewSource
  • Building planP50300049603 · Date not statedViewSource
  • Building planP50300049603 · Date not statedViewSource

Allotment letter

  • Allotment letterP50300031176 · Date not statedViewSource

Document library

  • Details of encumbrancesP50300031176 · ADV_compressed.pdf · uploaded 21 Sep 2021View
  • Copy of Layout Approval (in case of layout)P50300031176 · LAYOUT MAP.pdf · uploaded 21 Sep 2021View
  • Building Plan Approval / NA Order for plotted developmentP50300031176 · building map 1.pdf · uploaded 21 Sep 2021View
  • Building Plan Approval / NA Order for plotted developmentP50300031176 · building map 2.pdf · uploaded 21 Sep 2021View
  • Building Plan Approval / NA Order for plotted developmentP50300031176 · building map 3.pdf · uploaded 21 Sep 2021View
  • Declaration in FORM BP50300031176 · fom-b.pdf · uploaded 21 Sep 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · architect certificate.pdf · uploaded 21 Sep 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · engineer's certificate.pdf · uploaded 21 Sep 2021View
  • Proforma of Allotment letterP50300031176 · agreement to sale.pdf · uploaded 21 Sep 2021View
  • Declaration about Commencement CertificateP50300031176 · srushti infra commencement declaration.pdf · uploaded 21 Sep 2021View
  • Commencement Certificates / NA Order for plotted developmentP50300031176 · Document 2.pdf · uploaded 2 Oct 2021View
  • Copy of the legal title reportP50300031176 · updated title report.pdf · uploaded 6 Oct 2021View
  • Details of encumbrancesP50300031176 · Encumbrance Certificate.pdf · uploaded 28 Sep 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · Architect Certificate.pdf · uploaded 28 Sep 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · Engineer Certificate.pdf · uploaded 28 Sep 2022View
  • Copy of the legal title reportP50300049603 · TITELREPORT.pdf · uploaded 13 Dec 2022Source
  • Commencement Certificates / NA Order for plotted developmentP50300049603 · commencement certificate phase 2.pdf · uploaded 13 Dec 2022View
  • Declaration about Commencement CertificateP50300049603 · declaration about commencement certificate.pdf · uploaded 13 Dec 2022View
  • Declaration in FORM BP50300049603 · affidavit cum declaration new.pdf · uploaded 13 Dec 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300049603 · Architect certificate (1).pdf · uploaded 13 Dec 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300049603 · Engineer certificate phase 2.pdf · uploaded 13 Dec 2022Source
  • CERSAI detailsP50300049603 · CERSAI_Search_Report_200259393985_For_Asset_Based_Search_03_02_2023_12_37_37_089.pdf · uploaded 13 Dec 2022Source
  • Deviation Report with respect to Allotment letterP50300049603 · Deviation Report .pdf · uploaded 13 Dec 2022Source
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 055 (1).pdf · uploaded 13 Dec 2022Source
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 056 (1).pdf · uploaded 13 Dec 2022Source
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 057 (1).pdf · uploaded 13 Dec 2022View
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 058 (1).pdf · uploaded 13 Dec 2022View
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 059 (1).pdf · uploaded 13 Dec 2022View
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 060 (1).pdf · uploaded 13 Dec 2022View
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 061 (1).pdf · uploaded 13 Dec 2022View
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 062 (1).pdf · uploaded 13 Dec 2022View
  • Copy of Layout Approval (in case of layout)P50300049603 · revised map (1).pdf · uploaded 13 Dec 2022Source
  • Building Plan Approval / NA Order for plotted developmentP50300049603 · Mar 2022-- 063 (1).pdf · uploaded 13 Dec 2022View
  • Deviation Report with respect to model copy of AgreementP50300049603 · deviation.pdf · uploaded 13 Dec 2022Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300049603 · declaration about separate bank account for real estate project.pdf · uploaded 13 Dec 2022Source
  • a Details of encumbrances concerned to FinanceP50300049603 · Encumbrance certificate with respect to legal.pdf · uploaded 13 Dec 2022Source
  • b Details of encumbrances concerned to LegalP50300049603 · Encumbrance certificate with respect to legal.pdf · uploaded 13 Dec 2022Source
  • Proforma of Allotment letterP50300049603 · Kaagaz_20221214_172758479714.pdf · uploaded 14 Dec 2022Source
  • Proforma of Agreement for saleP50300049603 · agreementbykhandelwal.pdf · uploaded 14 Dec 2022Source
  • Other – FinanceP50300049603 · Encumbrance certificate with respect to finance.pdf · uploaded 30 Dec 2022Source
  • Disclosure of Interest in Other Real Estate OrganizationsP50300049603 · Partner.pdf · uploaded 5 Jan 2023Source
  • CERSAI detailsP50300049603 · CERSAI_Search_Report_200259395929_For_Asset_Based_Search_03_02_2023_12_47_50_049.pdf · uploaded 26 Jan 2023Source
  • CERSAI detailsP50300049603 · CERSAI_Search_Report_200259396043_For_Asset_Based_Search_03_02_2023_12_48_22_076.pdf · uploaded 26 Jan 2023Source
  • a Details of encumbrances concerned to FinanceP50300049603 · encumbrance certificate.pdf · uploaded 26 Jan 2023Source
  • b Details of encumbrances concerned to LegalP50300049603 · encumbrance certificate.pdf · uploaded 26 Jan 2023Source
  • CERSAI detailsP50300049603 · MAHATMA FULE BANK LETTER.pdf · uploaded 3 Feb 2023Source
  • CERSAI detailsP50300049603 · CERSAI REPLY.pdf · uploaded 7 Feb 2023Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · Form2_30062022.pdf · uploaded 16 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · Form1_30092022.pdf · uploaded 16 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · Form1_30092022.pdf · uploaded 16 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P50300031176 · Form5_Srushti Infra_2122.pdf · uploaded 16 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · Form 1.pdf · uploaded 7 Oct 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · Form 1 New.pdf · uploaded 7 Oct 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · Form 2.pdf · uploaded 7 Oct 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · Form 2 New.pdf · uploaded 7 Oct 2023View
  • Proforma of Agreement for saleP50300049603 · phase 2 FLAT AGREEMENT.pdf · uploaded 12 Oct 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P50300049603 · Audit report 2022-2023_compressed-compressed.pdf · uploaded 12 Oct 2023Source
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P50300031176 · Audit report 2022-2023_compressed-compressed.pdf · uploaded 12 Oct 2023View
  • Deviation Report with respect to Allotment letterP50300049603 · phase 2 FLAT AGREEMENT.pdf · uploaded 12 Oct 2023Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300049603 · ENGINEERSCERTIFICATE.pdf · uploaded 13 Oct 2023Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300049603 · ARCHITECTCERTIFICATE.pdf · uploaded 13 Oct 2023View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300049603 · ESCROWACCOUNTDECLERATION.pdf · uploaded 13 Oct 2023Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300049603 · ESCROWACCOUNTDETAILS.pdf · uploaded 13 Oct 2023Source
  • a Details of encumbrances concerned to FinanceP50300049603 · encumbrance letter.pdf · uploaded 1 Dec 2023Source
  • b Details of encumbrances concerned to LegalP50300049603 · encumbrance letter.pdf · uploaded 1 Dec 2023Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · 31 2 2023 eng certificate.pdf · uploaded 6 Feb 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · 31 2 2023 eng certificate.pdf · uploaded 6 Feb 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · architectcertificate.pdf · uploaded 6 Feb 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · 31 2 2023 eng certificate.pdf · uploaded 6 Feb 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300049603 · arc certificate phase 2.pdf · uploaded 10 Feb 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300049603 · eng certificate phase 2.pdf · uploaded 10 Feb 2024Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300049603 · declarationaboutseparatebankaccount2.pdf · uploaded 31 Mar 2024Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50300049603 · selfdeclarationphase2.pdf · uploaded 31 Mar 2024Source
  • Other – FinanceP50300049603 · declarationcumundertaking2.pdf · uploaded 31 Mar 2024Source
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300049603 · ENGPHASE2.pdf · uploaded 20 Jun 2024Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300049603 · ARCPHASE2.pdf · uploaded 20 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · architecture certificate.pdf · uploaded 20 Jun 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · phase 1 eng.pdf · uploaded 20 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300031176 · architect certificate P-1.pdf · uploaded 4 Feb 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300031176 · engineer certificate P-1.pdf · uploaded 4 Feb 2025View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP50300031176 · scan751_11zon.pdf · uploaded 4 Feb 2025View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP50300031176 · oc1.pdf · uploaded 4 Feb 2025View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP50300031176 · oc2.pdf · uploaded 4 Feb 2025View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP50300031176 · oc3.pdf · uploaded 4 Feb 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)P50300049603 · engcerp2.pdf · uploaded 4 Feb 2025Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)P50300049603 · arccerp2.pdf · uploaded 4 Feb 2025Source
  • Form 1P50300049603 · form 1 310323.pdf · uploaded 11 Jun 2026Source
  • Form 2P50300049603 · 310323 FORM 2.pdf · uploaded 11 Jun 2026Source
  • Disclosure of Sold and Booked InventoryP50300049603 · disc 310323.pdf · uploaded 11 Jun 2026Source
  • Form 1P50300049603 · 300623 form 1.pdf · uploaded 11 Jun 2026Source
  • Form 2P50300049603 · 300623 FORM 2.pdf · uploaded 11 Jun 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · disc 300623.pdf · uploaded 11 Jun 2026View
  • Form 1P50300049603 · 300923 form 1.pdf · uploaded 11 Jun 2026View
  • Form 2P50300049603 · 300923 form 2.pdf · uploaded 11 Jun 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · disc 300923.pdf · uploaded 11 Jun 2026View
  • Form 1P50300049603 · 311223 form 1.pdf · uploaded 11 Jun 2026View
  • Form 2P50300049603 · 3111223 form 2.pdf · uploaded 11 Jun 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · disclosure 311223.pdf · uploaded 11 Jun 2026View
  • Form 1P50300049603 · form 1 310324.pdf · uploaded 11 Jun 2026View
  • Form 2P50300049603 · 310324 form 2.pdf · uploaded 11 Jun 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · DISC310324.pdf · uploaded 11 Jun 2026View
  • Form 1P50300049603 · 300624 form 1.pdf · uploaded 11 Jun 2026View
  • Form 2P50300049603 · 30062A FORM 2.pdf · uploaded 11 Jun 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · DISCLSUE 300624.pdf · uploaded 11 Jun 2026View
  • Form 1P50300049603 · 300924 form 1.pdf · uploaded 11 Jun 2026View
  • Form 2P50300049603 · 300924 form 2.pdf · uploaded 11 Jun 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · dis 300924.pdf · uploaded 11 Jun 2026View
  • Form 1P50300049603 · 311224 form 1.pdf · uploaded 11 Jun 2026View
  • Form 2P50300049603 · 311224 form 2.pdf · uploaded 11 Jun 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · disclosure 311224.pdf · uploaded 11 Jun 2026View
  • Form 1P50300049603 · form 1 310325.pdf · uploaded 4 Aug 2026View
  • Form 2P50300049603 · FORM 2.pdf · uploaded 4 Aug 2026View
  • Disclosure of Sold and Booked InventoryP50300049603 · Sold Booked Inventory Disclosure.pdf · uploaded 4 Aug 2026View
  • Withdrawal Update Form 1P50300049603 · 300625 form 1.pdf · uploaded 4 Aug 2026View
  • Withdrawal Update Form 2P50300049603 · 300625 FORM 2.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 1P50300049603 · 300925 form 1.pdf · uploaded 4 Aug 2026View
  • Withdrawal Update Form 2P50300049603 · 300925 form 2.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 1P50300049603 · FORM 1.pdf · uploaded 4 Aug 2026View
  • Withdrawal Update Form 2P50300049603 · FORM 2 (2) (1).pdf · uploaded 4 Aug 2026Source
  • Form 2A (FY 2024-2025)P50300049603 · Form 2A 2024-25.pdf · uploaded 8 Aug 2026Source
  • Form 2A (FY 2025-2026)P50300049603 · Form 2A 2025-26 (1).pdf · uploaded 8 Aug 2026Source
  • Form 5 (FY 2022-2023)P50300049603 · Form 5 23.pdf · uploaded 9 Aug 2026Source
  • Form 5 (FY 2023-2024)P50300049603 · Form 5 24.pdf · uploaded 9 Aug 2026Source
  • Form 5 (FY 2024-2025)P50300049603 · Form 5 25.pdf · uploaded 9 Aug 2026Source
  • Form 2A (FY 2021-2022)P50300031176 · Form 2A 2021-22.pdf · uploaded 17 Aug 2026View
  • Form 2A (FY 2022-2023)P50300031176 · Form 2A 2022-23.pdf · uploaded 17 Aug 2026View
  • Form 2A (FY 2023-2024)P50300031176 · Form 2A 2023-24.pdf · uploaded 17 Aug 2026View
  • Form 2A (FY 2024-2025)P50300031176 · Form 2A 2024-25.pdf · uploaded 17 Aug 2026View

Promoter documents

  • Declaration Form BP50300031176 · fom-b.pdf · uploaded 21 Sep 2021View
  • Legal Title reportP50300031176 · updated title report.pdf · uploaded 6 Oct 2021View
  • Legal Title reportP50300049603 · TITELREPORT.pdf · uploaded 13 Dec 2022Source
  • Declaration Form BP50300049603 · affidavit cum declaration new.pdf · uploaded 13 Dec 2022View

Technical documents

  • Layout ApprovalP50300031176 · LAYOUT MAP.pdfView
  • Building Plan ApprovalP50300031176 · building map 1.pdfView
  • Building Plan ApprovalP50300031176 · building map 2.pdfView
  • Building Plan ApprovalP50300031176 · building map 3.pdfView
  • Layout ApprovalP50300049603 · revised map (1).pdfSource
  • Building Plan ApprovalP50300049603 · Mar 2022-- 055 (1).pdfSource
  • Building Plan ApprovalP50300049603 · Mar 2022-- 056 (1).pdfSource
  • Building Plan ApprovalP50300049603 · Mar 2022-- 057 (1).pdfView
  • Building Plan ApprovalP50300049603 · Mar 2022-- 058 (1).pdfView
  • Building Plan ApprovalP50300049603 · Mar 2022-- 059 (1).pdfView
  • Building Plan ApprovalP50300049603 · Mar 2022-- 060 (1).pdfView
  • Building Plan ApprovalP50300049603 · Mar 2022-- 061 (1).pdfView
  • Building Plan ApprovalP50300049603 · Mar 2022-- 062 (1).pdfView
  • Building Plan ApprovalP50300049603 · Mar 2022-- 063 (1).pdfView

Financial documents

  • Other – FinanceP50300049603 · Encumbrance certificate with respect to finance.pdf · uploaded 30 Dec 2022Source
  • Other – FinanceP50300049603 · declarationcumundertaking2.pdf · uploaded 31 Mar 2024Source

Proforma allotment letter

  • Proforma allotment letterP50300031176 · agreement to sale.pdfView
  • Proforma allotment letterP50300049603 · Kaagaz_20221214_172758479714.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

103/42425PLOT NO. 25SURVEY NO. 103/4SURVEY NO 103/4 PLOT NO 24

As published on MahaRERA's project page

SURVEY NO 103/4 PLOT NO 24

Boundaries

North
Plot No 25
South
30 Meter Wide Road
East
Plot No 21-A To 23
West
30 Meter Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectShailendra Deshmukh—P50300049603
ArchitectShailendra Deshmukh—P50300031176
Chartered accountantAman Sahu—P50300031176
Chartered accountantAshutosh Rajput—P50300049603
Chartered accountantAshutosh Rajput—P50300031176
Chartered accountantBhushan Lathiya—P50300049603
Chartered accountantKALOTI and LATHIYA—P50300031176
Chartered accountantManish Khushlani—P50300049603
Chartered accountantV S Jakhotiya Chartered Accountants—P50300031176
EngineerSurendra Pohokar—P50300031176
EngineerSurendra Pohokar—P50300049603
EngineerV K Design Consultancy—P50300049603
EngineerVk Design Consultancy—P50300031176
OtherRishabh Khandelwal—P50300049603

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology