NeetaShree Residency

Completed

Amravati (M Corp.), Amravati 444606 |Promoter: Rohan Shrikrishna Chimote

4 Aug 2017Registered with MahaRERA
31 Dec 2019Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Land area for this project
300 sq m (3,226 sq ft)
Permissible built-up area
545 sq m (5,861 sq ft)
Sanctioned built-up area
545 sq m (5,861 sq ft)
Address
72PIN 444606
Designated bank account
Canara Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.96430, 77.78650
NeetaShree Residency is at latitude 20.96430, longitude 77.78650.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2019

The latest completion date on record passed 6 years and 10 months ago.

Registered
4 Aug 2017
Promised
31 Dec 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P503000030064 Aug 201731 Dec 2019—Rohan Shrikrishna ChimoteProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
NeetaShree Residency5—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

NeetaShree Residency

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure80%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBoring10%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Septic Tank0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingTree plantation (plants)0%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRain Water Harvesting Tank0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationElectric Meter Room0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

18 documents held by Deedo, 21 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificate

Form b

Form 1s

Form 2s

Form 5s

Registration certificate

Allotment letters

Others

Layout plan

Building plan

Document library

  • Copy of the legal title reporttitle report-min.pdf · uploaded 28 Jul 2017View
  • Details of encumbrancesnon encommembarance certificate.pdf · uploaded 28 Jul 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 28 Jul 2017View
  • Declaration in FORM Bform b.pdf · uploaded 28 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect.pdf · uploaded 28 Jul 2017View
  • Proforma of Allotment letterdeclaration.pdf · uploaded 28 Jul 2017View
  • Building Plan Approval (IOD)SANCTION MAP.pdf · uploaded 28 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentcommencment certificate.pdf · uploaded 28 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate.pdf · uploaded 28 Jul 2017View
  • Certificates of CA (Form 5)declaration2.pdf · uploaded 28 Jul 2017View
  • Certificates of Architect (Form 4)declaration2.pdf · uploaded 28 Jul 2017View
  • Proforma of Allotment letteragr SALE_Rera_APARTMENT_Proforma_Neeta Shree.pdf · uploaded 24 Jan 2018View
  • Proforma of Allotment letterAllotment Letter_Neeta Shree.pdf · uploaded 24 Jan 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate-ilovepdf-compressed.pdf · uploaded 24 Jan 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate1.pdf · uploaded 24 Jan 2018View
  • Certificates of CA (Form 5)CHIMOTE.pdf · uploaded 6 Nov 2018View

Promoter documents

  • Legal Title reporttitle report-min.pdf · uploaded 28 Jul 2017View
  • Declaration Form Bform b.pdf · uploaded 28 Jul 2017View

Technical documents

  • Layout ApprovalLAYOUT.pdfView
  • Building Plan ApprovalSANCTION MAP.pdfView

Proforma allotment letter

  • Proforma allotment letterdeclaration.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

72

As published on MahaRERA's project page

72

Boundaries

North
Service Lane
South
Road Width 12 M
East
Road Width 9 M
West
Plot No 71

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMinal D Sarda—
OtherGirisk K Nagpur—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology