Skip to content
Deedo home
Menu

Jaee Residency

Completed

Amravati (M Corp.), Amravati 444604 |Promoter: Manisha Anantkumar Lingot

Residential / Group HousingRERAP50300028493
8 Mar 2021Registered with MahaRERA
15 Feb 2024Promised completion
1Building
17Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK17 units in all
Land area for this project
508 sq m (5,467 sq ft)
Permissible built-up area
1,300 sq m (13,993 sq ft)
Sanctioned built-up area
1,300 sq m (13,993 sq ft)
Address
45/5/B/2/3, Maharshi Colony, Tower Line Road Kathora RoadPIN 444604
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 15 Feb 2024

The latest completion date on record passed 2 years and 8 months ago.

Registered
8 Mar 2021
Promised
15 Feb 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P503000284938 Mar 202115 Feb 2024—Manisha Anantkumar LingotProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Jaee Residency517

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

17 units registered

2BHK · 17 units
TypeCarpet areaUnits
2BHK35.48 sq m · 382 sq ft1
2BHK47.25 sq m · 509 sq ft4
2BHK47.45 sq m · 511 sq ft4
2BHK55.7 sq m · 600 sq ft4
2BHK58.92 sq m · 634 sq ft4

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Jaee Residency

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBOARWELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingTREE PALNTING100%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationELECT METER ROOM100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

30 documents held by Deedo, 58 filings listed on MahaRERA's project page

Title

Encumbrance

Form b

Allotment letters

Others

Commencement certificate

Form 2as

Form 2s

Form 5s

Completion

Registration certificate

Layout plan

Building plan

Document library

  • Building Plan Approval / NA Order for plotted developmentjrplan_compressed (1).pdf · uploaded 19 Feb 2021View
  • Commencement Certificates / NA Order for plotted developmentpermit-compressed.pdf · uploaded 19 Feb 2021View
  • Declaration in FORM Bjaeenotary-compressed.pdf · uploaded 19 Feb 2021View
  • Proforma of Allotment letterjaeealotment.pdf · uploaded 19 Feb 2021View
  • Proforma of Allotment letterAGREEMENT TO SALE.pdf · uploaded 19 Feb 2021View
  • Details of encumbrancesencumbrances.pdf · uploaded 19 Feb 2021View
  • Copy of Layout Approval (in case of layout)jaee layout plan.pdf · uploaded 19 Feb 2021View
  • Copy of the legal title reportlegal title report jaee_compressed.pdf · uploaded 19 Feb 2021View
  • Status of Formation of Legal Entity (Society/Co Op etc.)dod.pdf · uploaded 17 Jun 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)jaee.pdf · uploaded 25 Jul 2021View
  • Declaration about Commencement Certificatepermit-compressed.pdf · uploaded 12 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)jaee residency.pdf · uploaded 12 Aug 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)engi cer jaeeresidency.pdf · uploaded 12 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)jaee residency.pdf · uploaded 12 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)nil (1).pdf · uploaded 13 Aug 2021View
  • Disclosure of sold/ booked inventoryjaeesoldunsoldinve.pdf · uploaded 13 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)nil (1).pdf · uploaded 13 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)nil (1).pdf · uploaded 13 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)nil (1).pdf · uploaded 13 Aug 2021View
  • Status of Conveyancejaeesoldunsoldinve.pdf · uploaded 13 Aug 2021View
  • Details of Restarting of Construction work post lockdownnil (1).pdf · uploaded 13 Aug 2021View
  • Othernil (1).pdf · uploaded 13 Aug 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)jaee residency.pdf · uploaded 14 Aug 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)jaee (CA 5).pdf · uploaded 14 Aug 2021View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc jaee.pdf · uploaded 14 Aug 2021View
  • Architect’s Certificate on Completion of Project (Form 4)jaee.pdf · uploaded 14 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)jaee.pdf · uploaded 14 Aug 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)jaee residency.pdf · uploaded 14 Aug 2021View
  • Status of ConveyanceJR.pdf · uploaded 24 Nov 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)jaee engi.pdf · uploaded 24 Nov 2021View
  • Disclosure of sold/ booked inventoryJR.pdf · uploaded 24 Nov 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)jaee form 2.pdf · uploaded 24 Nov 2021View
  • Disclosure of sold/ booked inventorysold jaee.pdf · uploaded 26 Jan 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Jaee engi.pdf · uploaded 28 Jan 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)3 jaee residency quality assurance.pdf · uploaded 4 May 2022View
  • Disclosure of sold/ booked inventoryjaee r 1 sold unsold.pdf · uploaded 4 May 2022View
  • Disclosure of sold/ booked inventoryjaee resi sold.pdf · uploaded 22 Sep 2022View
  • a Details of encumbrances concerned to FinanceNA MBD.pdf · uploaded 13 Jan 2023View
  • b Details of encumbrances concerned to LegalNA MBD.pdf · uploaded 13 Jan 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)NA MBD.pdf · uploaded 13 Jan 2023View
  • CERSAI detailsNA MBD.pdf · uploaded 13 Jan 2023View
  • Disclosure of Interest in Other Real Estate OrganizationsNA MBD.pdf · uploaded 13 Jan 2023View
  • Proforma of Agreement for saleNA MBD.pdf · uploaded 13 Jan 2023View
  • Other – FinanceNA MBD.pdf · uploaded 13 Jan 2023View
  • Foreclosure of the ProjectNA MBD.pdf · uploaded 13 Jan 2023View
  • Other – TechnicalNA MBD.pdf · uploaded 13 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)NA MBD.pdf · uploaded 13 Jan 2023View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameNA MBD.pdf · uploaded 13 Jan 2023View
  • Deviation Report with respect to Allotment letterNA MBD.pdf · uploaded 13 Jan 2023View
  • Deviation Report with respect to model copy of AgreementNA MBD.pdf · uploaded 13 Jan 2023View
  • Disclosure of sold/ booked inventorysold unsold jaee residency.pdf · uploaded 12 Apr 2023View

Promoter documents

  • Declaration Form Bjaeenotary-compressed.pdf · uploaded 19 Feb 2021View
  • Legal Title reportlegal title report jaee_compressed.pdf · uploaded 19 Feb 2021View

Technical documents

  • Building Plan Approvaljrplan_compressed (1).pdfView
  • Layout Approvaljaee layout plan.pdfView

Other legal documents

  • Othernil (1).pdfView

Financial documents

  • Other – FinanceNA MBD.pdf · uploaded 13 Jan 2023View

Proforma allotment letter

  • Proforma allotment letterjaeealotment.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

45/5/B/2/3

As published on MahaRERA's project page

45/5/B/2/3

Boundaries

North
Plot No 1
South
Part Of Plot No 3
East
Road
West
Service Lane

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShraddha Sagane—
Chartered accountantTapesh Mundada—
EngineerPratiksha Gurjar—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology