Skip to content
Deedo home
Menu

Ayur Mall

Completion date passed

Amravati (M Corp.), Amravati 444601 |Promoter: K. K. Infrastructure

12 Apr 2018Registered with MahaRERA
15 Jan 2022Promised completion
15 Jul 2022Revised completionPushed back 6 months
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

Project type
Commercial
Buildings
1
Address
59/3PIN 444601

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.58175, 73.98171
Ayur Mall is at latitude 18.58175, longitude 73.98171.
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 6 months

The latest completion date on record passed 4 years and 3 months ago.

Registered
12 Apr 2018
Promised
15 Jan 2022
Revised
15 Jul 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030001604012 Apr 201815 Jan 202215 Jul 2022K. K. InfrastructureProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Ayur Mall4—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

2 documents held by Deedo

Registration certificate

Extension certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.)

Survey, CTS, gat or plot numbers

59/3

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology