Avani Heritage

Lapsed

Amravati (M Corp.), Amravati 444607 |Promoter: Ravi Panjabrao Ghurde

23 Apr 2018Registered with MahaRERA
30 Mar 2024Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Lapsed
Buildings
1
Land area for this project
417 sq m (4,489 sq ft)
Permissible built-up area
904 sq m (9,733 sq ft)
Sanctioned built-up area
704 sq m (7,580 sq ft)
Address
1 SURVEY NO 38/1 MAUJE PETH, Shilangan Road, Shanti Niketan ColonyPIN 444607
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.13679, 72.85791
Avani Heritage is at latitude 19.13679, longitude 72.85791.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Mar 2024

The latest completion date on record passed 2 years and 7 months ago.

Registered
23 Apr 2018
Promised
30 Mar 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030001619523 Apr 201830 Mar 2024—Ravi Panjabrao GhurdeProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Avani Heritage6—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space000036

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Avani Heritage

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
Show all 90 activitiesShow fewer activities
  • Water SupplyBORING100%
  • Water SupplyNot applicable
  • Water SupplyNot applicable
  • Water SupplyNot applicable
  • Water SupplyNot applicable
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Water conservation /Rain water harvestingAS PER PLAN0%
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Electrical meter room, sub-station, receiving stationSEPERATE BRACKET0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingAS REQUIRED0%
  • Open ParkingNot applicable
  • Open ParkingNot applicable
  • Open ParkingNot applicable
  • Open ParkingNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

11 documents held by Deedo, 14 filings listed on MahaRERA's project page

Title report

Encumbrance details

Form B (2)

Commencement certificate

Registration certificate

Other (2)

Show all 25 documentsShow fewer documents

Layout plan

Building plan

Allotment letter

Document library

  • Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 16 Apr 2018View
  • Declaration in FORM BPRMOTOER.pdf · uploaded 16 Apr 2018View
  • Declaration in FORM BCO PROMOTER.pdf · uploaded 16 Apr 2018View
  • Copy of the legal title reportGao Namuna patrak pdf.pdf · uploaded 16 Apr 2018View
  • Details of encumbrancesSEARCH.pdf · uploaded 16 Apr 2018View
  • Proforma of Allotment letteragreement to sale.pdf · uploaded 17 Apr 2018View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCMENT.pdf · uploaded 17 Apr 2018View
  • Building Plan Approval (IOD)SANCTION PLAN.pdf · uploaded 17 Apr 2018View

Promoter documents

  • Declaration Form BPRMOTOER.pdf · uploaded 16 Apr 2018View
  • Declaration Form BCO PROMOTER.pdf · uploaded 16 Apr 2018View
  • Legal Title reportGao Namuna patrak pdf.pdf · uploaded 16 Apr 2018View

Technical documents

  • NA Order for Plotted DevelopmentSANCTION PLAN.pdfView
  • Layout ApprovalLAYOUT PLAN.pdfView

Proforma allotment letter

  • Proforma allotment letteragreement to sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

1 SURVEY NO 38/1 MAUJE PETH

As published on MahaRERA's project page

1 SURVEY NO 38/1 MAUJE PETH

Boundaries

North
PLot No 2
South
Part of Survey No 38
East
Old Badnera Road
West
Service Lane

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRohit Punshi—
EngineerMangesh Bhimrao Gulhane—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology