RERA projects in Chandur
3 projects under 5 MahaRERA registrations, registered 2017–2020. 20% have a completion date extended beyond the one promised.
Locality
3RERA projects
5Registrationssome projects hold several
1Completion still due4 past their completion date, 2 marked completed
43 monthsMedian extension beyond promised date20% of registrations extended
0Regulatory casesnone on MahaRERA's lists
22Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 1 |
| 2019 | 2 |
| 2020 | 1 |
Projects in Chandur
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Nisarg GardenDilip Devichand Chaudhari, Dilip Devichand Chaudhari | P50100019355, P50100021651, P50100027492 | 23 Jan 2019 | 30 May 2023 | 31 Dec 2026 | Completed | 0 |
| Anand VatikaPurushottam Lunkaran Malani | P50100018690 | 27 Nov 2018 | 30 Mar 2023 | — | Promised date passed | 0 |
| Nisarg GardenDilip Devichand Chaudhari | P50100000101 | 3 Jul 2017 | 31 Jul 2018 | — | Completed | 0 |
Other localities in Akola
Most active promoters
By projects registered here, as named on MahaRERA.
- Dilip Devichand Chaudhari2 projects
- Purushottam Lunkaran Malani1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology