Building No 2 · Vishwajeet Precious Phase III
Varap · RERA P51700031318
IDBLD_0601278 floorsPromised date passed
8Sanctioned habitable floorsregistration certificate
2 Mar 2024Revised completionpromised 2 Mar 2024
22 of 28Units bookedMahaRERA project page
Floors
8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P51700031318 · registered 15 Oct 2021
- Promised completion
- 2 Mar 2024
- Revised completion
- 2 Mar 2024
- Sanctioned habitable floors
- 8
- ProjectId
- 34,872
- ProjectName
- VISHWAJEET PRECIOUS PHASE III
- TotalUnitCount
- 0
- ProjectBuildingId
- 30,000
- BuildingNameNumber
- BUILDING NO 2
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P51700031318
- ProjectBuildingWingsId
- 30,000
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- BUILDING NO 2
- NoOfBuildingWingFloorProposed
- 8
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 8
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 43.9 m² (472 sq.ft) | 28 | 22 |
| Total | 28 | 22 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology