Building A · Al- Maqaam
Thane (M Corp.) · RERA P51700051594
IDBLD_0672668 floorsExtended 4 mo
8Sanctioned habitable floorsregistration certificate
30 Apr 2029Revised completionpromised 31 Dec 2028
22 of 66Units bookedMahaRERA project page
Floors
8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P51700051594 · registered 27 Jun 2023
- Promised completion
- 31 Dec 2028
- Revised completion
- 30 Apr 2029
- Sanctioned habitable floors
- 8
- ProjectId
- 44,704
- ProjectName
- Al- Maqaam
- TotalUnitCount
- 65
- ProjectBuildingId
- 1,27,753
- BuildingNameNumber
- Building A
- FsiWithSanctionSqmts
- 8 (Ground + 7 Upper Floors)
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 55
- ProjectRegistartionNo
- P51700051594
- ProjectBuildingWingsId
- 1,31,170
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 10
- AdvertisedBuildingNameNumber
- Building A
- NoOfBuildingWingFloorProposed
- 8
- NoOfBuildingWingFloorHabitable
- 8
- NoOfBuildingWingFloorSanctioned
- 8
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 43.6 m² (470 sq.ft) | 26 | 15 |
| 1BHK | 44.4 m² (478 sq.ft) | 2 | 0 |
| 2BHK | 55.5 m² (597 sq.ft) | 6 | 4 |
| 2BHK | 55.6 m² (599 sq.ft) | 1 | 1 |
| 2BHK | 58.9 m² (633 sq.ft) | 7 | 1 |
| 2BHK | 58.9 m² (634 sq.ft) | 7 | 1 |
| 3BHK | 76.9 m² (828 sq.ft) | 7 | 0 |
| Shop | 22.5 m² (242 sq.ft) | 2 | 0 |
| Shop | 23 m² (248 sq.ft) | 2 | 0 |
| Shop | 30.5 m² (329 sq.ft) | 2 | 0 |
Show all 14 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 31 m² (334 sq.ft) | 1 | 0 |
| Shop | 37.3 m² (402 sq.ft) | 1 | 0 |
| Shop | 37.6 m² (404 sq.ft) | 1 | 0 |
| Shop | 40.2 m² (432 sq.ft) | 1 | 0 |
| Total | 66 | 22 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology