Al- Maqaam

Certificate Signed

Thane (M Corp.), Thane 400612 |Promoter: Eminent Constructions

27 Jun 2023Registered with MahaRERA
31 Dec 2028Promised completion
30 Apr 2029Revised completionPushed back 4 months
2Buildings
108Units registered28 booked (26%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
1BHK, 2BHK, 3BHK, Shop108 units in all
Address
Survey No 133/5 136/4 and 136/5, Sector No - 09, Sector No - 09, 12 Meter Service Road and 45 Meter DP Road, KausaPIN 400612
Designated bank account
87
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.16219, 73.02454
Al- Maqaam is at latitude 19.16219, longitude 73.02454.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
27 Jun 2023
Promised
31 Dec 2028
Revised
30 Apr 2029

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005159427 Jun 202331 Dec 202830 Apr 2029Eminent ConstructionsProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building A866
Building- B742

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

28 of 108 units booked (26%), as the promoter reported to MahaRERA

1BHK · 42 units2BHK · 42 units3BHK · 14 unitsShop · 10 units
BuildingTypeCarpet areaUnitsBooked
Building A1BHK43.62 sq m · 470 sq ft2615
Building A1BHK44.37 sq m · 478 sq ft20
Building A2BHK55.45 sq m · 597 sq ft64
Building A2BHK55.61 sq m · 599 sq ft11
Building A2BHK58.85 sq m · 633 sq ft71
Building A2BHK58.87 sq m · 634 sq ft71
Building A3BHK76.88 sq m · 828 sq ft70
Building AShop22.5 sq m · 242 sq ft20
Show all 20 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building AShop23 sq m · 248 sq ft20
Building AShop30.53 sq m · 329 sq ft20
Building AShop31.03 sq m · 334 sq ft10
Building AShop37.32 sq m · 402 sq ft10
Building AShop37.56 sq m · 404 sq ft10
Building AShop40.17 sq m · 432 sq ft10
Building- B1BHK40.68 sq m · 438 sq ft72
Building- B1BHK40.73 sq m · 438 sq ft71
Building- B2BHK54.03 sq m · 582 sq ft72
Building- B2BHK57.06 sq m · 614 sq ft70
Building- B2BHK57.53 sq m · 619 sq ft70
Building- B3BHK86.66 sq m · 933 sq ft71

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 73 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPancard- Firm.pdf · uploaded 9 May 2023Source

Legal

  • Declaration Form BForm B- Promoter.pdf · uploaded 12 May 2023Source
  • Legal Title reportFinal Title Report- Eminent Constructions_11zon.pdf · uploaded 6 Jun 2023Source

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 8 May 2023Source
  • 1 PAN CardPancard- Firm.pdf · uploaded 9 May 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 12 May 2023Source
  • 1 Declaration in FORM BForm B- Promoter.pdf · uploaded 12 May 2023Source
Show all 74 documentsShow fewer documents

Migrated

  • 1 CERSAI details1 CERSAI details (1) (1).pdf · uploaded 12 May 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)First Form 3 of Al-Maqaam-Eminent Constructions.pdf · uploaded 18 May 2023Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 18 May 2023Source
  • 1 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance.pdf · uploaded 19 May 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Letter- Legal.pdf · uploaded 19 May 2023Source
  • 1 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance.pdf · uploaded 19 May 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Letter- Legal.pdf · uploaded 19 May 2023Source
  • 1 Copy of Layout Approval (in case of layout)Page 1_11zon.pdf · uploaded 19 May 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPage 1_11zon.pdf · uploaded 19 May 2023Source
  • 2 Building Plan Approval / NA Order for plotted development2 Building Plan Approval _ NA Order for plotted development (1).pdf · uploaded 19 May 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 19 May 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same.pdf · uploaded 19 May 2023Source
  • 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter.pdf · uploaded 19 May 2023Source
  • 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement.pdf · uploaded 19 May 2023Source
  • 1 Proforma of Allotment letterilovepdf_merged (1).pdf · uploaded 2 Jun 2023Source
  • 1 Copy of the legal title reportFinal Title Report- Eminent Constructions_11zon.pdf · uploaded 6 Jun 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Eminent Constructions RERA.PDF · uploaded 27 Dec 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 of Al-Maqaam as on June 2023.pdf · uploaded 3 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 of Al-Maqaam as on Sept 2023.pdf · uploaded 3 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Al-Maqaam as on 30th June 2023.pdf · uploaded 3 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Al-Maqaam as on 30th Sept 23.pdf · uploaded 3 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 of Al-Maqaam as on Dec 2023.pdf · uploaded 17 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Al-Maqaam as on 31-12-2023.pdf · uploaded 17 Jan 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Al Maqaam as on Dec 2023.pdf · uploaded 24 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Al-Maqaam as on March 2024.pdf · uploaded 21 Jun 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Al-Maqaam as on 31-03-2024.pdf · uploaded 21 Jun 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Al-Maqaam as on June 2024.pdf · uploaded 19 Jul 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Al-Maqaam as on 30-06-2024.pdf · uploaded 19 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 of Al-Maqaam for the FY 2023-24.pdf · uploaded 31 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Al-Maqaam as on Sept 2024.PDF · uploaded 15 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Al-Maqaam as on Sept 2024.pdf · uploaded 15 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Al-Maqaam as on Dec 2024.pdf · uploaded 15 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Al-Maqaam as on Sept 2024.pdf · uploaded 15 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Al-Maqaam as on Dec 2024.pdf · uploaded 15 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Al-Maqaam as on 31-03-2025.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Al-Maqaam as on March 2025.pdf · uploaded 19 Apr 2025Source
  • Form 1Form 1 Al Maqaam as on march 2026.PDF · uploaded 19 May 2026Source
  • Form 2Form 2 of Al-Maqaam as on 31-03-2026.pdf · uploaded 19 May 2026Source
  • Form 3Form 3 of Al-Maqaam as on 31-03-2026.pdf · uploaded 19 May 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - AL - Maqaam as on march 2026.pdf · uploaded 19 May 2026Source
  • Form 1Form 1 - Al-Maqaam as on Dec 2025.pdf · uploaded 16 Jun 2026Source
  • Form 2Form 2 - Al-Maqaam as on Dec 2025.pdf · uploaded 16 Jun 2026Source
  • Form 3Form 3 of Al-Maqaam as on 31-12-2025.pdf · uploaded 16 Jun 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Al-Maqaam as on Dec 2025.pdf · uploaded 16 Jun 2026Source
  • Form 1Form 1 Al- Maqaam as on 30-06-2026.PDF · uploaded 20 Jul 2026Source
  • Form 2Al-_Maqaam_Form2_Q1_2026-27_20-07-2026_06-41.pdf · uploaded 20 Jul 2026Source
  • Form 3Al-_Maqaam_Form3_Q1_2026-27_18-07-2026_12-55_doc1.pdf · uploaded 20 Jul 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Al-_Maqaam June 2026.pdf · uploaded 20 Jul 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Al-Maqaam as on June 2025.pdf · uploaded 12 Sep 2026Source
  • Form 1Form 1 - Al-Maqaam as on Dec 2025.pdf · uploaded 12 Sep 2026Source
  • Form 2Form 2 - Al-Maqaam as on June 2025.pdf · uploaded 12 Sep 2026Source
  • Form 3Form 3 of Al-Maqaam as on 30-06-2025.pdf · uploaded 12 Sep 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Al-Maqaam as on Sept 2025.pdf · uploaded 12 Sep 2026Source
  • Form 1Form 1 - Al-Maqaam as on Dec 2025.pdf · uploaded 12 Sep 2026Source
  • Form 2Form 2 - Al-Maqaam as on Sept 2025.pdf · uploaded 12 Sep 2026Source
  • Form 3Form 3 - Al-Maqaam as on Sept 2025.pdf · uploaded 12 Sep 2026Source
  • Form 5 (FY 2025-2026)Form 5 - Al- Maqaam Fy 25-226.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentPage 1_11zon.pdf · uploaded 19 May 2023Source
  • DocumentPage 1_11zon.pdf · uploaded 19 May 2023Source
  • Document2 Building Plan Approval _ NA Order for plotted development (1).pdf · uploaded 19 May 2023Source

Technical (Architect)

  • DocumentForm 1 - Al Maqaam as on Dec 2023.pdf · uploaded 24 Jan 2024Source
  • DocumentForm 1 - Al-Maqaam as on Sept 2024.PDF · uploaded 15 Jan 2025Source

Technical (Engineer)

  • DocumentForm 2 - Al-Maqaam as on June 2024.pdf · uploaded 19 Jul 2024Source
  • DocumentForm 2 - Al-Maqaam as on Sept 2024.pdf · uploaded 15 Jan 2025Source
  • DocumentForm 2 - Al-Maqaam as on Dec 2024.pdf · uploaded 15 Jan 2025Source
  • DocumentForm 2 - Al-Maqaam as on March 2025.pdf · uploaded 19 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Thane (M Corp.), Thane taluka

Survey, CTS, gat or plot numbers

136/5Sector No 09Survey No 133/5 136/4

Boundaries

North
Survey No- 133
South
Mumbra By Pass Road
East
Survey No- 133
West
Mukta Gharonda Complex

Source: registration certificates and MahaRERA's project page, as stated there.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology