Residential / Group Housing · 1 building · 126 unitsRERA PR1330002501883

Vaviya Vista

Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record.

Nerul, Thane 400706 · Promoter: Vaviya Developers

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 26 Dec 2025, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1330002501883
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR133000250188326 Dec 202531 Dec 202930 Apr 2030Vaviya DevelopersProject page
Documents30

1 document held by Deedo, 29 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardVAVIYA DEVELOPERS - PAN CARD.pdf · uploaded 26 Nov 2025Source

Legal

  • OthersAnnexure A -Disclosure of Intrest -Firm and Partners.pdf · uploaded 27 Nov 2025Source
  • OthersPARTNERSHIP DEED -VAVIYA DEVELOPERS.pdf · uploaded 28 Nov 2025Source
  • Declaration Form BForm - B -Promoter.pdf · uploaded 28 Nov 2025Source
  • Declaration Form BSHIVSAGAR LEASE DEED_.pdf · uploaded 28 Nov 2025Source
  • Declaration Form BTitle Certificate -Vaviya Vista.pdf · uploaded 29 Nov 2025Source

Migrated

  • Withdrawal Update Form 1Form 1 - Vaviya Vista as on Dec 2025.pdf · uploaded 30 Jan 2026Source
Show all 30 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 2Form 2 - Vaviya Vista as on Dec 2025.pdf · uploaded 30 Jan 2026Source
  • Withdrawal Update Form 3Form 3 - Vaviya Vista as on Dec 2025.pdf · uploaded 30 Jan 2026Source
  • Withdrawal Update Form 1Form 1 - Vaviya Vista as on March 2026.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Form 2 - Vaviya Vista as on March 2026 client.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3Form 3 - Vaviya Vista as on March 2026.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 1Form 1 - Vaviya Vista as on June 2026.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Vaviya Vista as on June 2026.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Vaviya Vista as on June 2026.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Vaviya Vista as on June 2026.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Vaviya Vista as on June 2026.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Vaviya Vista as on June 2026.pdf · uploaded 29 Jul 2026Source
  • Form 5 (FY 2025-2026)Form 5 - Vaviya Vista FY 25-26.pdf · uploaded 30 Sep 2026Source
  • Form 2A (FY 2025-2026)Vaviya_Vista_Form2A_2025-26_01-10-2026_14-57.pdf · uploaded 1 Oct 2026Source

Technical

  • DocumentBuilding Plan Approval -Page 2.pdf · uploaded 27 Nov 2025Source
  • DocumentBuilding Plan Approval -Page 3.pdf · uploaded 27 Nov 2025Source
  • DocumentBuilding Plan Approval -Page 4.pdf · uploaded 27 Nov 2025Source
  • DocumentBuilding Plan Approval -page 5_.pdf · uploaded 27 Nov 2025Source
  • DocumentLayout Plan -Page 1.pdf · uploaded 27 Nov 2025Source
  • DocumentAnnexure A -Order 50.pdf · uploaded 29 Nov 2025Source
  • OthersCC Verification mail -Vaviya Vista.pdf · uploaded 29 Nov 2025Source

Technical (Architect)

  • DocumentForm 1 - Vaviya Vista as on June 2026.pdf · uploaded 18 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 - Vaviya Vista as on June 2026.pdf · uploaded 18 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPlot No -22, Sector -18

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—126 units in all
Address
Sector -18, Nerul, Navi MumbaiPIN 400706
Village
Nerul, Thane taluka
Designated bank account
105
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No -22Sector -18

Boundaries

North
Plot No 13
South
9 Meter Road
East
Plot No 21
West
Plot No 23

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking126 units

126 units registered

— · 126 units
TypeCarpet areaUnits
——126

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerJugal Patel—
EngineerSamarth Agarwal—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology