Skip to content

Riddhi Siddhi Parvati

Certificate Signed

Navi Mumbai (M Corp.), Thane 410206 |Promoter: Riddhi Siddhi Mega Structure Private Limited

10 May 2024Registered with MahaRERA
31 May 2027Promised completion
30 Sep 2027Revised completionPushed back 4 months
1Building
39Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—39 units in all
Address
82, Sector 7 at Pushpak, SECTOR 7, PUSHPAKPIN 410206
Designated bank account
86
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.96765, 73.07602
Riddhi Siddhi Parvati is at latitude 18.96765, longitude 73.07602.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
10 May 2024
Promised
31 May 2027
Revised
30 Sep 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005609110 May 202431 May 202730 Sep 2027Riddhi Siddhi Mega Structure Private LimitedProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Riddhi Siddhi Parvati639

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

39 units registered

— · 39 units
TypeCarpet areaUnits
——39

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 17 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCompany PAN.pdf · uploaded 6 Mar 2024Source

Legal

  • Legal Title reporttitle Report.pdf · uploaded 6 Mar 2024Source
  • Declaration Form BFORM B LAND OWNER.pdf · uploaded 22 Mar 2024Source
  • Declaration Form BFORM B PROMOTER.pdf · uploaded 22 Mar 2024Source

Technical

  • DocumentPlan 1.pdf · uploaded 7 Mar 2024Source
  • DocumentPlan 2.pdf · uploaded 7 Mar 2024Source
  • DocumentPlan 3.pdf · uploaded 7 Mar 2024Source
Show all 18 documentsShow fewer documents

Technical

  • Other – TechnicalANNEXTURE- DECLARATION-CUM-UNDERTAKING.pdf · uploaded 7 Mar 2024Source
  • DocumentPlan 1.pdf · uploaded 8 Mar 2024Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 13 Dec 2024Source
  • DocumentForm 1 - Dec 24 [Signed].pdf · uploaded 20 Jan 2025Source
  • DocumentForm 1 final.pdf · uploaded 3 May 2025Source
  • DocumentForm 1 Q1.pdf · uploaded 23 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 20 Jan 2025Source
  • DocumentForm 2 - Dec 24 [Signed].pdf · uploaded 20 Jan 2025Source
  • DocumentForm 2 final.pdf · uploaded 3 May 2025Source
  • DocumentForm 2 Q1.pdf · uploaded 23 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Navi Mumbai (M Corp.), Thane taluka

Survey, CTS, gat or plot numbers

82Sector 7 at Pushpak

Boundaries

North
Plot No 83
South
Plot No 81
East
Plot No 86
West
15 Meter Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastuyog Architects—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology