Certificate Signed

Navi Mumbai (M Corp.), Thane 400705 |Promoter: Goodwill Constructions

Residential / Group HousingRERAP51700018463
2 Nov 2018Registered with MahaRERA
30 Jun 2022Promised completion
2Buildings
163Units registered50 booked (31%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
1 BHK, 2BHK, Showroom163 units in all
Address
Plot No 12 Sector 08, Sector 08, SanpadaPIN 400705
Designated bank account
76
Developed in phases
Yes

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2022

The latest completion date on record passed 4 years and 4 months ago.

Registered
2 Nov 2018
Promised
30 Jun 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000184632 Nov 201830 Jun 202230 Jun 2022Goodwill ConstructionsProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building No 1 Ews525
Building No 225138

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

50 of 163 units booked (31%), as the promoter reported to MahaRERA

1 BHK · 25 units2BHK · 136 unitsShowroom · 2 units
BuildingTypeCarpet areaUnitsBooked
Building No 1 Ews1 BHK32.63 sq m · 351 sq ft100
Building No 1 Ews1 BHK33.68 sq m · 363 sq ft50
Building No 1 Ews1 BHK33.86 sq m · 364 sq ft50
Building No 1 Ews1 BHK34.58 sq m · 372 sq ft50
Building No 22BHK36.84 sq m · 397 sq ft6828
Building No 22BHK43.91 sq m · 473 sq ft6822
Building No 2Showroom242.94 sq m · 2,615 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 82 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD - GOODWILL CONSTRUCTIONS.pdf · uploaded 17 Oct 2018Source

Legal

  • Declaration Form BFORM B - GOODWILL CONSTRUCTIONS.pdf · uploaded 19 Oct 2018Source
  • Legal Title reportLEGAL TITLE REPORT - GOODWILL CONSTRUCTIONS.pdf · uploaded 29 Oct 2018Source
  • OtherPLINTH COMPLETION CERTIFICATE.pdf · uploaded 13 Mar 2019Source
  • Otherinternal work completion.pdf · uploaded 8 Mar 2021Source
  • Other21st Slabcompletion.pdf · uploaded 8 Mar 2021Source
  • OtherDisclosure of Sold Unsold Inventory-compressed.pdf · uploaded 30 Jun 2021Source
Show all 83 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN CARD - GOODWILL CONSTRUCTIONS.pdf · uploaded 17 Oct 2018Source
  • 1 Building Plan Approval (IOD)COMMENCEMENT CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf · uploaded 17 Oct 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf · uploaded 17 Oct 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE - GOOD WILL CONSTRUCTIONS.pdf · uploaded 17 Oct 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf · uploaded 17 Oct 2018Source
  • 1 Details of encumbrancesLETTER OF ENCUMBRANCES - GOODWILL CONSTRUCTIONS.pdf · uploaded 19 Oct 2018Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN - GOODWILL CONSTRUCTIONS.PDF · uploaded 19 Oct 2018Source
  • 1 Declaration in FORM BFORM B - GOODWILL CONSTRUCTIONS.pdf · uploaded 19 Oct 2018Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf · uploaded 24 Oct 2018Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT - GOODWILL CONSTRUCTIONS.pdf · uploaded 29 Oct 2018Source
  • 1 Proforma of Allotment letterProforma of the allotment letter and agreement for sale - GOODWILL CONSTRUCTIONS.pdf · uploaded 29 Oct 2018Source
  • 1 OtherPLINTH COMPLETION CERTIFICATE.pdf · uploaded 13 Mar 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 24 Apr 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 24 Apr 2019Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 24 Apr 2019Source
  • 2 Proforma of Allotment letterFINAL ALLOTMENT AND SALE AGREEMENT.pdf · uploaded 6 May 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)form 5 RERA.pdf · uploaded 26 Oct 2019Source
  • 2 Details of encumbrancesGC.pdf · uploaded 20 Jun 2020Source
  • 3 Proforma of Allotment letterREVISED AGREEMENT FOR SALE.pdf · uploaded 20 Jun 2020Source
  • 4 Proforma of Allotment letterPROFORMA OF ALLOTMENT LETTER AGRREMENT FOR SALE.pdf · uploaded 3 Nov 2020Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 9 Nov 2020Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 9 Nov 2020Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)F1 UNITY.pdf · uploaded 21 Dec 2020Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Goodwill Unity Form 2.pdf · uploaded 21 Dec 2020Source
  • 2 Certificates of CA (Form 3)Goodwill Unity Form 3.pdf · uploaded 21 Dec 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)20210127180457971 CONST.pdf · uploaded 28 Jan 2021Source
  • 2 Otherinternal work completion.pdf · uploaded 8 Mar 2021Source
  • 3 Other21st Slabcompletion.pdf · uploaded 8 Mar 2021Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Goodwill Unity 31122021.pdf · uploaded 12 Apr 2021Source
  • 3 Certificates of CA (Form 3)Form 3 Goodwill Unity CA certifciate 31122020 (2).pdf · uploaded 12 Apr 2021Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)UNITY 31-12-2020-compressed.pdf · uploaded 30 Jun 2021Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)UNITY 31-03-2021-compressed.pdf · uploaded 30 Jun 2021Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Goodwill Unity-Form 2 - Engineer's Certificate-31032021 (1)-compressed.pdf · uploaded 30 Jun 2021Source
  • 4 Certificates of CA (Form 3)Goodwill Unity-Form 3-CA Certificate-31032021 (2)-compressed.pdf · uploaded 30 Jun 2021Source
  • 4 OtherDisclosure of Sold Unsold Inventory-compressed.pdf · uploaded 30 Jun 2021Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold Inventory-compressed.pdf · uploaded 2 Jul 2021Source
  • 5 Proforma of Allotment letterAgreement For Sale 29072021 ABODE.pdf · uploaded 29 Jul 2021Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate as per rera for UNITY project dtd 30062021.pdf · uploaded 16 Aug 2021Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Goodwill Unity-FORM 2-Associated Consultants -30062021.pdf · uploaded 16 Aug 2021Source
  • 5 Certificates of CA (Form 3)Goodwill Unity-Form 3-CA Certificate-30062021.pdf · uploaded 16 Aug 2021Source
  • 2 Copy of Layout Approval (in case of layout)2.pdf · uploaded 1 Sep 2021Source
  • 3 Copy of Layout Approval (in case of layout)3.pdf · uploaded 1 Sep 2021Source
  • 4 Copy of Layout Approval (in case of layout)4.pdf · uploaded 1 Sep 2021Source
  • 5 Copy of Layout Approval (in case of layout)5.pdf · uploaded 1 Sep 2021Source
  • 6 Copy of Layout Approval (in case of layout)6.pdf · uploaded 1 Sep 2021Source
  • 7 Copy of Layout Approval (in case of layout)7.pdf · uploaded 1 Sep 2021Source
  • 8 Copy of Layout Approval (in case of layout)8.pdf · uploaded 1 Sep 2021Source
  • 9 Copy of Layout Approval (in case of layout)9.pdf · uploaded 1 Sep 2021Source
  • 10 Copy of Layout Approval (in case of layout)10.pdf · uploaded 1 Sep 2021Source
  • 11 Copy of Layout Approval (in case of layout)11.pdf · uploaded 1 Sep 2021Source
  • 12 Copy of Layout Approval (in case of layout)12.pdf · uploaded 1 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)GC_Form5.pdf · uploaded 27 Sep 2021Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)F1 Architect Certificate 30092021.pdf · uploaded 9 Dec 2021Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Goodwill F2 UNITY 30092021.pdf · uploaded 15 Dec 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentEWS OC 01122021.pdf · uploaded 15 Mar 2022Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentGoodwill Unity OC.pdf · uploaded 15 Mar 2022Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)FORM-4 for unity-ews r1.pdf · uploaded 15 Mar 2022Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)FORM-4 for unity sale r1.pdf · uploaded 15 Mar 2022Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Signed Certificate_Form 5_31_03_2021.pdf · uploaded 1 Jun 2022Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-9-2022 ABODE FORM 1_compressed.pdf · uploaded 22 Nov 2022Source

Technical

  • DocumentCOMMENCEMENT CERTIFICATE - GOODWILL CONSTRUCTIONS.pdf · uploaded 17 Oct 2018Source
  • DocumentLAYOUT PLAN - GOODWILL CONSTRUCTIONS.PDF · uploaded 19 Oct 2018Source
  • Document7.pdf · uploaded 1 Sep 2021Source
  • Document2.pdf · uploaded 1 Sep 2021Source
  • Document3.pdf · uploaded 1 Sep 2021Source
  • Document4.pdf · uploaded 1 Sep 2021Source
  • Document5.pdf · uploaded 1 Sep 2021Source
  • Document6.pdf · uploaded 1 Sep 2021Source
  • Document8.pdf · uploaded 1 Sep 2021Source
  • Document9.pdf · uploaded 1 Sep 2021Source
  • Document11.pdf · uploaded 1 Sep 2021Source
  • Document12.pdf · uploaded 1 Sep 2021Source
  • Document10.pdf · uploaded 1 Sep 2021Source

Technical (Architect)

  • Document30-9-2022 ABODE FORM 1_compressed.pdf · uploaded 22 Nov 2022Source

Technical (Engineer)

  • DocumentGoodwill F2 UNITY 30092021.pdf · uploaded 15 Dec 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Navi Mumbai (M Corp.), Thane taluka

Survey, CTS, gat or plot numbers

PLOT NO 12 SECTOR 08

Boundaries

North
Plot No 25
South
Plot No 15 And 14 And 13
East
15 Mts Wide Road
West
Plot No 16 And 17

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHomework Architect—
EngineerAssociated Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology