Dosti Greater Thane - Phase 1
Certificate SignedKopar, Thane 421302 |Promoter: Adrika Developers Private Limited
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 4
- Unit types
- 1BHK, 1RK, Shop, Studio1,806 units in all
- Address
- 9/4 Pt, 7/8 Pt, 7/1pt, 11/25pt, 11/23pt, 12/19pt, 7/13pt, 11/17pt, 11/12pt, 11/13pt, 11/7pt, 11/1pt, 11/8pt, 11/18pt, 11/19a Pt, 11/19b Pt, 11/15pt, 11/16pt, 11/14pt, 11/11pt, 12/9pt, 11/21pt, 11/3pt, 11/9pt, 11/10pt, Junction Of Kalher Pipeline Road And Bunder Road, Near Umiya Complex And S S HospitalPIN 421302
- Designated bank account
- 109
- Developed in phases
- Yes
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 1 Apr 2026
The latest completion date on record passed 6 months ago.
- Registered
- 12 Mar 2020
- Promised
- 1 Apr 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700024923 | 12 Mar 2020 | 1 Apr 2026 | 1 Apr 2026 | Adrika Developers Private Limited | Project page |
4 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Dosti Bliss | 20 | 488 |
| Dosti Delight | 20 | 665 |
| Dosti Fortune | 17 | 418 |
| Dosti Glory | 20 | 235 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
1,792 of 1,806 units booked (99%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Dosti Bliss | 1BHK | 26.23 sq m · 282 sq ft | 464 | 464 |
| Dosti Bliss | 1RK | 13.96 sq m · 150 sq ft | 6 | 0 |
| Dosti Bliss | Shop | 13.38 sq m · 144 sq ft | 4 | 4 |
| Dosti Bliss | Shop | 18.77 sq m · 202 sq ft | 2 | 2 |
| Dosti Bliss | Shop | 19.79 sq m · 213 sq ft | 12 | 12 |
| Dosti Delight | 1BHK | 26.23 sq m · 282 sq ft | 656 | 655 |
| Dosti Delight | 1RK | 17.8 sq m · 192 sq ft | 6 | 6 |
| Dosti Delight | Studio | 13.96 sq m · 150 sq ft | 3 | 1 |
Show all 15 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Dosti Fortune | 1BHK | 26.23 sq m · 282 sq ft | 396 | 395 |
| Dosti Fortune | Shop | 13.38 sq m · 144 sq ft | 4 | 4 |
| Dosti Fortune | Shop | 18.77 sq m · 202 sq ft | 2 | 2 |
| Dosti Fortune | Shop | 19.79 sq m · 213 sq ft | 12 | 12 |
| Dosti Fortune | Studio | 13.96 sq m · 150 sq ft | 4 | 2 |
| Dosti Glory | 1BHK | 26.23 sq m · 282 sq ft | 232 | 232 |
| Dosti Glory | Studio | 13.96 sq m · 150 sq ft | 3 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 154 filings listed on MahaRERA's project page
Legal
- Legal Title reportHKO-7.pdf · uploaded 3 Mar 2020Source
- Legal Title reportHKO-11.pdf · uploaded 3 Mar 2020Source
- Legal Title reportHKO-15.pdf · uploaded 3 Mar 2020Source
- Legal Title reportHKO-18.pdf · uploaded 3 Mar 2020Source
- Legal Title reportHKO-23.pdf · uploaded 3 Mar 2020Source
- Legal Title reportHKO-28.pdf · uploaded 3 Mar 2020Source
- Legal Title reportHKO-38.pdf · uploaded 3 Mar 2020Source
Show all 155 documentsShow fewer documents
Legal
- Legal Title reportHKO-40.pdf · uploaded 3 Mar 2020Source
- Legal Title reportHKO-63.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-14.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-22.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-37.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-49.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-51.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-62.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-76.pdf · uploaded 3 Mar 2020Source
- Legal Title reportKO-114.pdf · uploaded 3 Mar 2020Source
- OtherAdrika.pdf · uploaded 4 Mar 2020Source
- Legal Title reportHKO-43.pdf · uploaded 4 Mar 2020Source
- Legal Title reportKO-05.pdf · uploaded 4 Mar 2020Source
- Declaration Form BForm B.pdf · uploaded 4 Mar 2020Source
Migrated
- 1 Copy of the legal title reportHKO-7.pdf · uploaded 3 Mar 2020Source
- 2 Copy of the legal title reportHKO-11.pdf · uploaded 3 Mar 2020Source
- 3 Copy of the legal title reportHKO-15.pdf · uploaded 3 Mar 2020Source
- 4 Copy of the legal title reportHKO-18.pdf · uploaded 3 Mar 2020Source
- 5 Copy of the legal title reportHKO-23.pdf · uploaded 3 Mar 2020Source
- 6 Copy of the legal title reportHKO-28.pdf · uploaded 3 Mar 2020Source
- 7 Copy of the legal title reportHKO-38.pdf · uploaded 3 Mar 2020Source
- 8 Copy of the legal title reportHKO-40.pdf · uploaded 3 Mar 2020Source
- 9 Copy of the legal title reportHKO-63.pdf · uploaded 3 Mar 2020Source
- 10 Copy of the legal title reportKO-14.pdf · uploaded 3 Mar 2020Source
- 11 Copy of the legal title reportKO-22.pdf · uploaded 3 Mar 2020Source
- 12 Copy of the legal title reportKO-37.pdf · uploaded 3 Mar 2020Source
- 13 Copy of the legal title reportKO-49.pdf · uploaded 3 Mar 2020Source
- 14 Copy of the legal title reportKO-51.pdf · uploaded 3 Mar 2020Source
- 15 Copy of the legal title reportKO-62.pdf · uploaded 3 Mar 2020Source
- 16 Copy of the legal title reportKO-76.pdf · uploaded 3 Mar 2020Source
- 17 Copy of the legal title reportKO-114.pdf · uploaded 3 Mar 2020Source
- 1 Details of encumbrancesDosti Novo City Phase 1.pdf · uploaded 3 Mar 2020Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT 1.pdf · uploaded 3 Mar 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentCC 3.pdf · uploaded 3 Mar 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCC Low.pdf · uploaded 3 Mar 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Novo City Phase 1.pdf · uploaded 3 Mar 2020Source
- 1 Proforma of Allotment letterAgreement.pdf · uploaded 3 Mar 2020Source
- 18 Copy of the legal title reportHKO-43.pdf · uploaded 4 Mar 2020Source
- 19 Copy of the legal title reportKO-05.pdf · uploaded 4 Mar 2020Source
- 1 Declaration in FORM BForm B.pdf · uploaded 4 Mar 2020Source
- 1 OtherAdrika.pdf · uploaded 4 Mar 2020Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 16 Oct 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 16 Oct 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentAmended Commencement Certificate.pdf · uploaded 16 Oct 2020Source
- 3 Commencement Certificates / NA Order for plotted developmentcorrigendum to cc.pdf · uploaded 29 Oct 2020Source
- 4 Commencement Certificates / NA Order for plotted developmentCC letter.pdf · uploaded 8 Dec 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Adrika RERA Certificate - Form 5.pdf · uploaded 29 Apr 2021Source
- 1 Disclosure of sold/ booked inventoryRERA REPORT- DELIGHT (3).pdf · uploaded 22 Jun 2021Source
- 2 Disclosure of sold/ booked inventoryRERA REPORT- FORTUNE (1).pdf · uploaded 22 Jun 2021Source
- 3 Disclosure of sold/ booked inventoryRERA REPORT-BLISS (1).pdf · uploaded 22 Jun 2021Source
- 4 Disclosure of sold/ booked inventoryRERA REPORT-GLORY (1).pdf · uploaded 22 Jun 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form No 2A Quality Certificate DGT PH1 june 2021_compressed.pdf · uploaded 29 Jul 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE DGT.pdf · uploaded 5 Oct 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)dgt phase 1.pdf · uploaded 5 Oct 2021Source
- 5 Disclosure of sold/ booked inventoryFORTUNE AND BLISS COMPILED.pdf · uploaded 8 Oct 2021Source
- 6 Disclosure of sold/ booked inventoryDELIGHT AND GLORY COMPRESSED.pdf · uploaded 8 Oct 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DGT PH 1.pdf · uploaded 12 Oct 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form No 3 CA Certificate Sept 2021 DGT Ph 1_compressed.pdf · uploaded 20 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Dosti Greater Thane Phase 1Form 5.pdf · uploaded 7 Jan 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Certificate DGT Ph1.pdf · uploaded 2 Mar 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate DGT Ph1.pdf · uploaded 2 Mar 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate DGT Ph 1.pdf · uploaded 2 Mar 2022Source
- 2 Details of encumbrancesIndex II - DGT Phase 1 - Details of Encumbrances_compressed.pdf · uploaded 4 Apr 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate DGT PHASE 1.pdf · uploaded 18 Jul 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate DGT PHASE 1.pdf · uploaded 18 Jul 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate DGT PHASE 1.pdf · uploaded 18 Jul 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dosti Greater Thane-Sept 2022.pdf · uploaded 7 Nov 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate-DGT PH1.pdf · uploaded 23 Nov 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate-DGT PH1.pdf · uploaded 23 Nov 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate-DGT PH1.pdf · uploaded 23 Nov 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate DGT Phase 1.pdf · uploaded 12 Dec 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate DGT.pdf · uploaded 12 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM 5-DGT-PH1.pdf · uploaded 12 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5-DGT-PARADISE.pdf · uploaded 12 Dec 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate-DGT-Phase 1.pdf · uploaded 21 Jan 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate DGT Phase 1.pdf · uploaded 25 Jan 2023Source
- 7 Disclosure of sold/ booked inventoryDGT - Sold and Unsold Inventory.pdf · uploaded 31 Jan 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)arch certificate Dosti Greater Thane PH1 dated March 2020 Signed.pdf · uploaded 6 Feb 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DGT PH1 March 2021.pdf · uploaded 6 Feb 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Certificate DGT Ph1.pdf · uploaded 6 Feb 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Dosti Greater Thane Ph 1 March 2020.pdf · uploaded 6 Feb 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form No 2 DGT PH 1 March 2021.pdf · uploaded 6 Feb 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate Dosti Greater thane Phase 1 Dec 2022.pdf · uploaded 6 Feb 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Dosti Greater Thane PH 1 March 2020.pdf · uploaded 6 Feb 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 DGT PH1 signed march 2021.pdf · uploaded 6 Feb 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dosti greater Thane Phase 1_compressed.pdf · uploaded 11 Apr 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dosti greater thane Phase 1_compressed.pdf · uploaded 11 Apr 2023Source
- 8 Disclosure of sold/ booked inventoryDosti Greater Thane - Phase 1 - Bliss-Fortune Shops - Sold-Unsold Data.pdf · uploaded 14 Apr 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 DGT Ph1 March 2023.pdf · uploaded 19 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assurance Certificate DGT Phase 1.pdf · uploaded 20 Apr 2023Source
- 9 Disclosure of sold/ booked inventoryDGT - Phase 1.pdf · uploaded 11 Jul 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate Dosti greater Thane Phase 1.pdf · uploaded 18 Jul 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dosti greater thane Ph1.pdf · uploaded 5 Aug 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dosti greater thane Ph1.pdf · uploaded 5 Aug 2023Source
- 10 Disclosure of sold/ booked inventoryDGT Phase 1 Bliss Delight Fortune Glory.pdf · uploaded 20 Oct 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate DGT Phase 1 Glory Delight Bliss Fortune.pdf · uploaded 23 Oct 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg-Form-2-DGT-PH-I.pdf · uploaded 13 Dec 2023Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA-Form-3-DGT-PH-I- Paradise.pdf · uploaded 13 Dec 2023Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate DGT Phase 1.pdf · uploaded 15 Dec 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Rera Form 5 - Adrika -DGT PH -1 March 31, 2022.pdf · uploaded 18 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form-5-DGT-PH-I.pdf · uploaded 28 Dec 2023Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Dosti Greater Thane Phase 1.pdf · uploaded 16 Jan 2024Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate DGT Phase 1.pdf · uploaded 17 Jan 2024Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch certifi-DGT-Ph-I-Dec23.pdf · uploaded 20 Jan 2024Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch certifi-DGT-Ph-I-Dec23.pdf · uploaded 29 Jan 2024Source
- 11 Disclosure of sold/ booked inventoryDosti Bliss Delight fortune Glory.pdf · uploaded 5 Feb 2024Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate DGT Phase 1.pdf · uploaded 23 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)DGT Novocity Phase 1 Bliss Delight fortune Glory.pdf · uploaded 24 Apr 2024Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate DGT Novocity Phase 1.pdf · uploaded 26 Apr 2024Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate DGT Novocity Phase 1.pdf · uploaded 26 Apr 2024Source
- 12 Disclosure of sold/ booked inventoryDosti Novocity Phase-1.pdf · uploaded 10 May 2024Source
- 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)DGT Phase-1- Form1 Arch Cert June 2024.pdf · uploaded 22 Jul 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)DGT Phase-1- Form2 CA Cert June 2024.pdf · uploaded 22 Jul 2024Source
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)DGT Phase-1- Form3 CA Cert June 2024.pdf · uploaded 22 Jul 2024Source
- 13 Disclosure of sold/ booked inventory5-0 DGT Novocity Phase-1- Bliss Fortune Delight.pdf · uploaded 9 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)DGT Phase-1.pdf · uploaded 7 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)DGT Phase-1 Form1 Sep24.pdf · uploaded 15 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)DGT Phase-1 Form3 Sep24.pdf · uploaded 15 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)DGT Phase-1 Form2 Sep24.pdf · uploaded 15 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryDGT Phase-1.pdf · uploaded 18 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate DGT Phase 1.pdf · uploaded 13 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate DGT Phase 1.pdf · uploaded 13 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate DGT Phase 1.pdf · uploaded 13 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDGT PH 1_compressed.pdf · uploaded 13 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryADPL DGT PH 1 Bliss Delight Fortune Glory_compressed (2).pdf · uploaded 12 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)DGT PHASE-1 ARCH Certificate.pdf · uploaded 14 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)DGT Phase-1 CA Certificate.pdf · uploaded 14 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)DGT PHASE-1 Engg Certificate.pdf · uploaded 14 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)DGT PHASE-1 Quality Certificate.pdf · uploaded 14 Apr 2025Source
- Form 1DGT Novocity PHASE1 ARCH Certificate June2025.pdf · uploaded 28 Jul 2025Source
- Form 2DGT Novocity Phase1 Engg Certificate June2025.pdf · uploaded 28 Jul 2025Source
- Form 3DGT Novocity Phase1 CA Certificate June2025.pdf · uploaded 28 Jul 2025Source
- Disclosure of Sold and Booked InventoryDGT PH1-Bliss_merged_compressed.pdf · uploaded 28 Jul 2025Source
- Form 5 (FY 2024-2025)Adrika DGT Novocity PH1.pdf · uploaded 12 Nov 2025Source
- Form 5 (FY 2025-2026)Adrika DGT Novocity PH1 2025-26.pdf · uploaded 5 Oct 2026Source
Technical
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Kopar, Bhiwandi taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey No 11 H 5 S 11 H 6 S 12 H 3 S 12 H 6
- South
- Survey No 9 H 7 S 7 H 20
- East
- Survey No 7 H 9 S 7 H 15
- West
- Survey No 11 H 1 Pt
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Jay Vora | — |
| Chartered accountant | Manish Bardia | — |
| Engineer | Swapnil Ramesh Londhe | — |
Source: MahaRERA project page. Contact details are not shown.