Riverview Classic
Completion date passedKalyandombivali (M Corp.), Thane 421301 |Promoter: Rutu Builders
Project summary
As registered with MahaRERA
- RERA registrations
- 3
- Phases
- 3
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Jun 2019
P51700001351The latest completion date on record passed 7 years and 4 months ago.
- Registered
- 27 Jul 2017
- Promised
- 30 Jun 2019
Completion promised for 30 Dec 2022
P51700017199The latest completion date on record passed 3 years and 10 months ago.
- Registered
- 23 Jul 2018
- Promised
- 30 Dec 2022
Completion promised for 30 Jun 2024
P51700027621The latest completion date on record passed 2 years and 4 months ago.
- Registered
- 25 Dec 2020
- Promised
- 30 Jun 2024
3 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700001351 | 27 Jul 2017 | 30 Jun 2019 | — | Rutu Builders | Project page |
| P51700017199 | 23 Jul 2018 | 30 Dec 2022 | — | Rutu Builders | Project page |
| P51700027621 | 25 Dec 2020 | 30 Jun 2024 | — | Rutu Builders | Project page |
Documents
3 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Kalyandombivali (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.