Suvidhi Darshan
Certificate SignedDombivli, Thane 421201 |Promoter: Subh Associates
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Address
- 11077 To 11084, G. B. Patharli, Dombivli EastPIN 421201
- Designated bank account
- 119
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2025
The latest completion date on record passed 10 months ago.
- Registered
- 21 Nov 2023
- Promised
- 31 Dec 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700053651 | 21 Nov 2023 | 31 Dec 2025 | 31 Dec 2025 | Subh Associates | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Main building | 8 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
1 document held by Deedo, 83 filings listed on MahaRERA's project page
Finance
- PAN CardSUBH ASS PAN CARD.pdf · uploaded 9 Sep 2023Source
Legal
Show all 84 documentsShow fewer documents
Migrated
- 2 Copy of the legal title reportSEARCH REPORT.pdf · uploaded 9 Sep 2023Source
- 1 a Details of encumbrances concerned to FinanceDETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf · uploaded 9 Sep 2023Source
- 1 b Details of encumbrances concerned to LegalDETAILS OF ENCUMBRANCES CONCERNED TO LEGAL.pdf · uploaded 9 Sep 2023Source
- 1 Copy of Layout Approval (in case of layout)APPROVAL PLAN.pdf · uploaded 9 Sep 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentAPPROVAL PLAN.pdf · uploaded 9 Sep 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 9 Sep 2023Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 9 Sep 2023Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 9 Sep 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTFICATE.pdf · uploaded 9 Sep 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 9 Sep 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200279212172_For_Asset_Based_Search_02_09_2023_11_14_16_241.pdf · uploaded 9 Sep 2023Source
- 2 CERSAI detailsCERSAI PAYMENT RECEIPT.pdf · uploaded 9 Sep 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORG.pdf · uploaded 9 Sep 2023Source
- 1 Proforma of Allotment letterMODEL FORM OF ALLOTMENT LETTER.pdf · uploaded 9 Sep 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf · uploaded 9 Sep 2023Source
- 1 Deviation Report with respect to Allotment letterDEVIATION REPORT WITH RESPECT TO ALLOTMENT LETTER.pdf · uploaded 9 Sep 2023Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT WITH RESPECT TO MODEL OF AGREEMENT.pdf · uploaded 9 Sep 2023Source
- 2 a Details of encumbrances concerned to FinanceDETAILS OF ENCUMBRANCES CONCERNED TO FINANCE.pdf · uploaded 18 Sep 2023Source
- 2 b Details of encumbrances concerned to LegalDETAILS OF ENCUMBRANCES CONCERNED TO FINANCE.pdf · uploaded 18 Sep 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentPLINTH CERTIFICATE.pdf · uploaded 20 Sep 2023Source
- 1 Proforma of Agreement for saleAgreement for Sale Flat.pdf · uploaded 25 Sep 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 23 Oct 2023Source
- 1 Other – LegalTO WHOMSOEVER IT MAY CONCERN.pdf · uploaded 23 Oct 2023Source
- 1 Other – TechnicalTO WHOMSOEVER IT MAY CONCERN.pdf · uploaded 30 Oct 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentAPPROVAL PLAN 1.pdf · uploaded 8 Nov 2023Source
- 2 Other – TechnicalAPPROVAL PLAN 1.pdf · uploaded 8 Nov 2023Source
- 3 Other – TechnicalPlan Letter.pdf · uploaded 8 Nov 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30-09-2024.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31-03-2024.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30-06-2024.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30-09-2024.pdf · uploaded 14 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31-12-2023.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31-12-2023.pdf · uploaded 14 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31-03-2024.pdf · uploaded 14 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30-06-2024.pdf · uploaded 14 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31-12-2023.pdf · uploaded 14 Oct 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31-03-2024.pdf · uploaded 14 Oct 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30-06-2024.pdf · uploaded 14 Oct 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30-09-2024.pdf · uploaded 14 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31-12-2023.pdf · uploaded 14 Oct 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31-03-2024.pdf · uploaded 14 Oct 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30-06-2024.pdf · uploaded 14 Oct 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30-09-2024.pdf · uploaded 14 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)SUBH ASSOCIATES FORM 5 2023-24.pdf · uploaded 3 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 SUBH 31ST DEC 2024.pdf · uploaded 24 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 SUBH 31ST DEC 2024.pdf · uploaded 24 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 31 03 2025 SUBH ASSOCIATES.pdf · uploaded 8 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 31 03 2025 SUBH ASSOCIATES.pdf · uploaded 8 May 2025Source
Technical
- DocumentAPPROVAL PLAN.pdf · uploaded 9 Sep 2023Source
- DocumentAPPROVAL PLAN.pdf · uploaded 9 Sep 2023Source
- Other – TechnicalTO WHOMSOEVER IT MAY CONCERN.pdf · uploaded 30 Oct 2023Source
- DocumentAPPROVAL PLAN 1.pdf · uploaded 8 Nov 2023Source
- Other – TechnicalAPPROVAL PLAN 1.pdf · uploaded 8 Nov 2023Source
- Other – TechnicalPlan Letter.pdf · uploaded 8 Nov 2023Source
Technical (Architect)
- DocumentARCHITECT CERTFICATE.pdf · uploaded 9 Sep 2023Source
- DocumentFORM 1 30-09-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 1 31-12-2023.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 1 31-03-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 1 30-06-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 1 31-12-2023.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 1 31-03-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 1 30-06-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 1 30-09-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM-1 SUBH 31ST DEC 2024.pdf · uploaded 24 Feb 2025Source
- Documentform 1 31 03 2025 SUBH ASSOCIATES.pdf · uploaded 8 May 2025Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE.pdf · uploaded 9 Sep 2023Source
- DocumentFORM 2 31-03-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 2 30-06-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 2 30-09-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 2 31-12-2023.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 2 31-12-2023.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 2 31-03-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 2 30-06-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM 2 30-09-2024.pdf · uploaded 14 Oct 2024Source
- DocumentFORM-2 SUBH 31ST DEC 2024.pdf · uploaded 24 Feb 2025Source
- Documentform 2 31 03 2025 SUBH ASSOCIATES.pdf · uploaded 8 May 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Dombivli, Kalyan taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Gyan Prasad Chs
- South
- Rukmani Chs
- East
- 21 Meter Wide Dp Road
- West
- Gurudaiwat Chs And Ramdarshan Chs
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sandeep S Paranjpe | — |
| Chartered accountant | P C Parvadiya And Associates | — |
| Engineer | Aarna Structural Consultants | — |
Source: MahaRERA project page. Contact details are not shown.