My City - Phase I - Part II

Certificate Signed

Dombivli, Thane 400612 |Promoter: Horizon Projects Pvt Ltd

Residential / Group HousingRERAP51700009168
19 Aug 2017Registered with MahaRERA
31 Dec 2018Promised completion
31 Dec 2019Revised completionPushed back 1 year
5Buildings
615Units registered570 booked (93%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
5
Unit types
1 BHK, 1BHK, 2BHK, 2 BHK, 3 BHK, 3BHK615 units in all
Address
SURVEY NO 36PT 77PT, Diva-Manpada Road, BetavadePIN 400612
Designated bank account
85
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.20909, 72.98330
My City - Phase I - Part II is at latitude 19.20909, longitude 72.98330.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 6 years and 10 months ago.

Registered
19 Aug 2017
Promised
31 Dec 2018
Revised
31 Dec 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000916819 Aug 201731 Dec 201831 Dec 2019Horizon Projects Pvt LtdProject page

5 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A131153
A231153
B130103
C131103
C231103

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

570 of 615 units booked (93%), as the promoter reported to MahaRERA

1 BHK · 60 units1BHK · 146 units2BHK · 158 units2 BHK · 197 units3 BHK · 37 units3BHK · 17 units
BuildingTypeCarpet areaUnitsBooked
A11 BHK37.26 sq m · 401 sq ft3535
A11 BHK37.42 sq m · 403 sq ft2525
A11BHK35.02 sq m · 377 sq ft1913
A11BHK35.66 sq m · 384 sq ft2419
A12BHK43.99 sq m · 474 sq ft2212
A12BHK45.63 sq m · 491 sq ft2828
A21BHK35.02 sq m · 377 sq ft1915
A21BHK35.66 sq m · 384 sq ft2114
Show all 26 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A21BHK37.26 sq m · 401 sq ft3535
A21BHK37.42 sq m · 403 sq ft2828
A22BHK43.99 sq m · 474 sq ft127
A22BHK45.63 sq m · 491 sq ft3838
B12 BHK50.3 sq m · 541 sq ft7979
B12BHK47.57 sq m · 512 sq ft2422
C12 BHK48.95 sq m · 527 sq ft4141
C12 BHK50.3 sq m · 541 sq ft1818
C12BHK46.24 sq m · 498 sq ft1311
C12BHK47.25 sq m · 509 sq ft44
C13 BHK65.48 sq m · 705 sq ft1717
C13BHK62.89 sq m · 677 sq ft1010
C22 BHK48.95 sq m · 527 sq ft4040
C22 BHK50.3 sq m · 541 sq ft1919
C22BHK46.24 sq m · 498 sq ft1412
C22BHK47.25 sq m · 509 sq ft32
C23 BHK65.48 sq m · 705 sq ft2020
C23BHK62.89 sq m · 677 sq ft76

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 72 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardCompany PAN Card.pdf · uploaded 29 Jul 2017Source

Legal

  • Declaration Form BForm B.pdf · uploaded 30 Jul 2017Source
  • Legal Title reporttitle certificate8.pdf · uploaded 30 Jul 2017Source
  • Declaration Form BFORM - B My City Part - II.pdf · uploaded 5 Jan 2019Source
  • OtherOC A1A2B1C1C2 14-2-19.pdf · uploaded 25 Feb 2019Source

Migrated

  • 1 PAN CardCompany PAN Card.pdf · uploaded 29 Jul 2017Source
Show all 74 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)20151204_LAYOUT PLAN copy.pdf · uploaded 29 Jul 2017Source
  • 2 Copy of Layout Approval (in case of layout)TOWER A1.pdf · uploaded 29 Jul 2017Source
  • 3 Copy of Layout Approval (in case of layout)TOWER A2.pdf · uploaded 29 Jul 2017Source
  • 4 Copy of Layout Approval (in case of layout)TOWER B1.pdf · uploaded 29 Jul 2017Source
  • 5 Copy of Layout Approval (in case of layout)TOWER C1.pdf · uploaded 29 Jul 2017Source
  • 6 Copy of Layout Approval (in case of layout)TOWER C2.pdf · uploaded 29 Jul 2017Source
  • 1 Building Plan Approval (IOD)PLOT A _ 120706.pdf · uploaded 29 Jul 2017Source
  • 2 Building Plan Approval (IOD)01 LAYOUT PLAN.pdf · uploaded 29 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentAMENDED CC.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)A1_29-07-2017.pdf · uploaded 29 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)A2_29-07-2017.pdf · uploaded 29 Jul 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)C1_29-07-2017.pdf · uploaded 29 Jul 2017Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)C2_29-07-2017.pdf · uploaded 29 Jul 2017Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)B1_29-07-2017.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG CERTIFICATE_29-7-17 My City Plot A Part 2 RERA.pdf · uploaded 29 Jul 2017Source
  • 1 Copy of the legal title reporttitle certificate8.pdf · uploaded 30 Jul 2017Source
  • 1 Details of encumbrancesEncumbrances.pdf · uploaded 30 Jul 2017Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate1.pdf · uploaded 30 Jul 2017Source
  • 1 Proforma of Allotment letterSelf Declaration.pdf · uploaded 30 Jul 2017Source
  • 2 Proforma of Allotment letterMy City Phase I Part II AFS with Allotment.pdf · uploaded 4 Oct 2017Source
  • 3 Proforma of Allotment letterMy City Phase I Part II AFS with Allotment .pdf · uploaded 10 Nov 2017Source
  • 7 Copy of Layout Approval (in case of layout)14092017_ layout.pdf · uploaded 6 Dec 2017Source
  • 2 Commencement Certificates / NA Order for plotted development14092017_CC.pdf · uploaded 6 Dec 2017Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)TOWER- A1.pdf · uploaded 6 Dec 2017Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)TOWER- A2.pdf · uploaded 6 Dec 2017Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)TOWER- B1.pdf · uploaded 6 Dec 2017Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)TOWER- C1.pdf · uploaded 6 Dec 2017Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)TOWER- C2.pdf · uploaded 6 Dec 2017Source
  • 1 Certificates of CA (Form 5)HPPL- Phase I- Part II FORM 5.pdf · uploaded 29 Oct 2018Source
  • 2 Details of encumbrancesSelf Declaration reg encumbrances.pdf · uploaded 5 Jan 2019Source
  • 2 Declaration in FORM BFORM - B My City Part - II.pdf · uploaded 5 Jan 2019Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)310718_MY CITY PHASE I PART II ARCHITECT CERTIFICATE.pdf · uploaded 21 Feb 2019Source
  • 2 Certificates of CA (Form 3)Form 3 My City Cluster dtd 29 sep 18.pdf · uploaded 22 Feb 2019Source
  • 1 OtherOC A1A2B1C1C2 14-2-19.pdf · uploaded 25 Feb 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPATION CERTIFICATE - MY CITY PHASE I PART II.pdf · uploaded 27 Sep 2019Source
  • 3 Certificates of CA (Form 3)Form-3 HPPL - My City Phase 1 Part II.pdf · uploaded 16 Jul 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM-4 - ARCHITECT COMPLETION CERTIFICATE MY CITY PHASE I PART II 2020.pdf · uploaded 10 Aug 2020Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate TA 1.pdf · uploaded 10 Aug 2020Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate TA 2.pdf · uploaded 10 Aug 2020Source
  • 3 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate TB 1.pdf · uploaded 10 Aug 2020Source
  • 4 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate TC 1.pdf · uploaded 10 Aug 2020Source
  • 5 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate TC 2.pdf · uploaded 10 Aug 2020Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Tower A3 30092020.pdf · uploaded 19 Dec 2020Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Tower A4 30092020.pdf · uploaded 19 Dec 2020Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Tower B2 30092020.pdf · uploaded 19 Dec 2020Source
  • 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Tower C3 30092020.pdf · uploaded 19 Dec 2020Source
  • 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Tower C4 30092020.pdf · uploaded 19 Dec 2020Source
  • 2 Certificates of CA (Form 5)Form 5 My City Phase I Part II 08032021.pdf · uploaded 10 Mar 2021Source
  • 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Cluster 5 Tower 7.pdf · uploaded 23 Mar 2022Source
  • 18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Cluster 5 Tower 8.pdf · uploaded 23 Mar 2022Source
  • 19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Cluster 5 Tower 9.pdf · uploaded 23 Mar 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A My City Phase I Part II Year 2020.pdf · uploaded 23 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A My City Phase I Part II Year 2021.pdf · uploaded 23 Jun 2022Source
  • 4 Certificates of CA (Form 3)Form 3 My City Phase I Part II September 2017.pdf · uploaded 20 Aug 2022Source

Technical

  • DocumentPLOT A _ 120706.pdf · uploaded 29 Jul 2017Source
  • Document01 LAYOUT PLAN.pdf · uploaded 29 Jul 2017Source
  • Document20151204_LAYOUT PLAN copy.pdf · uploaded 29 Jul 2017Source
  • DocumentTOWER A1.pdf · uploaded 29 Jul 2017Source
  • DocumentTOWER A2.pdf · uploaded 29 Jul 2017Source
  • DocumentTOWER B1.pdf · uploaded 29 Jul 2017Source
  • DocumentTOWER C1.pdf · uploaded 29 Jul 2017Source
  • DocumentTOWER C2.pdf · uploaded 29 Jul 2017Source
  • Document14092017_ layout.pdf · uploaded 6 Dec 2017Source

Technical (Architect)

  • DocumentForm 1 Cluster 5 Tower 9.pdf · uploaded 23 Mar 2022Source

Technical (Engineer)

  • DocumentENG CERTIFICATE_29-7-17 My City Plot A Part 2 RERA.pdf · uploaded 29 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dombivli, Kalyan taluka

Survey, CTS, gat or plot numbers

SURVEY NO 36PT 77PT

Boundaries

North
Bhopar Village
South
18 Mt Wide Dp Road
East
Sandap Village
West
60 Mt Wide Dedicated Freight Corridor

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectCurrie And Brown—
Registered real estate agent360 Realtors LLP—
Registered real estate agentAsset Housing And Realtors Pvt Ltd—
Registered real estate agentBarcode Realty—
Registered real estate agentBeing Prop Life Style LLP—
Registered real estate agentBnm Business Solutions LLP—
Registered real estate agentCraft Financial Advisors Pvt Ltd—
Registered real estate agentElara Marketing Services Private Limited—
Show all 34 professionalsShow fewer professionals
RoleNameRegistration no.
Registered real estate agentFANM Property Services Pvt Ltd—
Registered real estate agentGargi Quadri—
Registered real estate agentGirish Tathuji Sardar—
Registered real estate agentGlobal Ventures—
Registered real estate agentHarmony Infrasolutions Private Limited—
Registered real estate agentHemanshu Ramesh Mavadia—
Registered real estate agentHitendra Solanki—
Registered real estate agentHorizon Financial &Properties Advisers Private Limited—
Registered real estate agentHousezinn Properties Private Limited—
Registered real estate agentIMCP Realty Pvt Ltd—
Registered real estate agentInvestors Clinic Infratech Private Limited—
Registered real estate agentJairam M Raheja—
Registered real estate agentJM Financial Products Limited—
Registered real estate agentMahavir Prasad Toshniwal—
Registered real estate agentManisha Lifespaces Consulting Pvt. Ltd.—
Registered real estate agentMetro Properties—
Registered real estate agentMithun Shankar Dundale—
Registered real estate agentNeelesh Mishra—
Registered real estate agentNobroker Technologies Solutions Private Limited—
Registered real estate agentPropertyok Realtors LLP—
Registered real estate agentPropertypistol Realty Private Limited—
Registered real estate agentPyramid Homes—
Registered real estate agentRajesh Premji Gori—
Registered real estate agentRehan Bedre—
Registered real estate agentRohan Gautam Gaikwad—
Registered real estate agentSquare Yards Consulting Private Limited—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology