Skip to content

Madhu Prem

Certificate Signed

Dombivli, Thane 421201 |Promoter: Shree Developers

Residential / Group HousingRERAP51700011469
31 Aug 2017Registered with MahaRERA
31 Dec 2018Promised completion
30 Nov 2022Revised completionPushed back 3 years and 11 months
1Building
33Units registered20 booked (61%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1 BHK, 2 BHK33 units in all
Address
58, Hissa No 2pPIN 421201
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.21168, 73.09070
Madhu Prem is at latitude 19.21168, longitude 73.09070.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years and 11 months

The latest completion date on record passed 3 years and 11 months ago.

Registered
31 Aug 2017
Promised
31 Dec 2018
Revised
30 Nov 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001146931 Aug 201731 Dec 201830 Nov 2022Shree DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Madhu Prem933

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

20 of 33 units booked (61%), as the promoter reported to MahaRERA

1 BHK · 19 units2 BHK · 14 units
TypeCarpet areaUnitsBooked
1 BHK664.78 sq m · 7,156 sq ft1912
2 BHK719.25 sq m · 7,742 sq ft148

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 27 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN.pdf · uploaded 10 Aug 2017Source

Legal

  • Legal Title reportTitle Certificate.pdf · uploaded 10 Aug 2017Source
  • Declaration Form BForm 'B' - Affidavit.pdf · uploaded 10 Aug 2017Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 10 Aug 2017Source
  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 10 Aug 2017Source
  • 1 Details of encumbrancesShree Developers.pdf · uploaded 10 Aug 2017Source
Show all 29 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Plan (1).pdf · uploaded 10 Aug 2017Source
  • 1 Building Plan Approval (IOD)Sudharit.pdf · uploaded 10 Aug 2017Source
  • 1 Declaration in FORM BForm 'B' - Affidavit.pdf · uploaded 10 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 10 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 10 Aug 2017Source
  • 1 Proforma of Allotment letter0AGREEMENT FOR SALE OF FLAT SHREE DEVELOPERS JULY 2017 1.pdf · uploaded 10 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 11 Aug 2017Source
  • 1 Certificates of CA (Form 5)CA CERTIFICATE.pdf · uploaded 11 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 24 Apr 2018Source
  • 2 Certificates of CA (Form 5)SHREE DEVELOPERS.pdf · uploaded 13 Oct 2018Source
  • 3 Certificates of CA (Form 5)SHREE DEVELOPERS.pdf · uploaded 13 Oct 2018Source
  • 4 Certificates of CA (Form 5)Form 5 Shree Developers.pdf · uploaded 12 Nov 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 Shree Developers.pdf · uploaded 12 Nov 2019Source
  • 1 Disclosure of sold/ booked inventoryPNT RERA FLAT LIST-converted.pdf · uploaded 27 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 29 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5.pdf · uploaded 29 Jul 2021Source
  • 1 Declaration about Commencement CertificateDeclaration 32.pdf · uploaded 31 Jul 2021Source

Technical

  • DocumentPlan (1).pdf · uploaded 10 Aug 2017Source
  • DocumentSudharit.pdf · uploaded 10 Aug 2017Source

Technical (Architect)

  • DocumentArchitect Certificate.pdf · uploaded 10 Aug 2017Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 10 Aug 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dombivli, Kalyan taluka

Survey, CTS, gat or plot numbers

58HISSA NO 2P

Boundaries

North
37 And 58 P
South
33 And 58 P
East
58 And Hissa No 16
West
58 P

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSatish Kanade—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology