Skip to content

Globe Estate - Next

Certificate Signed

Dombivli, Thane 421203 |Promoter: Vijay Paper Product

30 Aug 2022Registered with MahaRERA
31 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Address
A 12, B 17, Dombivli Industrial Area, Phase - 1PIN 421203
Designated bank account
109
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.20426, 73.09798
Globe Estate - Next is at latitude 19.20426, longitude 73.09798.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
30 Aug 2022
Promised
31 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004669630 Aug 202231 Dec 202630 Apr 2027Vijay Paper ProductProject page

Documents

1 document held by Deedo, 87 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardVIJAY PAPER PRODUCTS PAN CARD.pdf · uploaded 2 Aug 2022Source

Legal

  • Legal Title reportLegal title report_compressed.pdf · uploaded 2 Aug 2022Source
  • Declaration Form BFORM B_compressed dated.pdf · uploaded 2 Aug 2022Source

Migrated

  • 1 PAN CardVIJAY PAPER PRODUCTS PAN CARD.pdf · uploaded 2 Aug 2022Source
  • 1 Copy of the legal title reportLegal title report_compressed.pdf · uploaded 2 Aug 2022Source
  • 1 b Details of encumbrances concerned to LegalNon encumbrance of Legal Final.pdf · uploaded 2 Aug 2022Source
  • 1 Copy of Layout Approval (in case of layout)VIJAY PAPER PRODUCT PLAN APPOVED (1)-1.pdf · uploaded 2 Aug 2022Source
Show all 88 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)VIJAY PAPER PRODUCT PLAN APPOVED (1)-2-3_compressed.pdf · uploaded 2 Aug 2022Source
  • 3 Copy of Layout Approval (in case of layout)VIJAY PAPER PRODUCT PLAN APPOVED (1)-4.pdf · uploaded 2 Aug 2022Source
  • 4 Copy of Layout Approval (in case of layout)VIJAY PAPER PRODUCT PLAN APPOVED (1)-5 BW_compressed.pdf · uploaded 2 Aug 2022Source
  • 5 Copy of Layout Approval (in case of layout)ilovepdf_merged 6-8.pdf · uploaded 2 Aug 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentMIDC DOCUMENTS Commencement Certificate - VIJAY PAPER PRODUCTS_compressed-1-4.pdf · uploaded 2 Aug 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentMIDC DOCUMENTS Commencement Certificate - VIJAY PAPER PRODUCTS_compressed-5-8.pdf · uploaded 2 Aug 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentMIDC DOCUMENTS Commencement Certificate - VIJAY PAPER PRODUCTS_compressed-9-10.pdf · uploaded 2 Aug 2022Source
  • 1 Declaration about Commencement CertificateVIJAY PAPER PRODUCTS FORM D Declaration of CC.pdf · uploaded 2 Aug 2022Source
  • 1 Declaration in FORM BFORM B_compressed dated.pdf · uploaded 2 Aug 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT - ENGINEERS CERTIFICATE FOR RERA_compressed.pdf · uploaded 2 Aug 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE FOR RERA_compressed.pdf · uploaded 2 Aug 2022Source
  • 1 Proforma of Allotment letterALLOTTMENT LETTER.pdf · uploaded 2 Aug 2022Source
  • 2 Proforma of Allotment letterVijay Paper Product Agreement to Assignment (1).pdf · uploaded 2 Aug 2022Source
  • 1 a Details of encumbrances concerned to FinanceDetails of non Encumbrance Finance.pdf · uploaded 3 Aug 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval_compressed-1-4.pdf · uploaded 3 Aug 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval_compressed-5.pdf · uploaded 3 Aug 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval_compressed-6-10.pdf · uploaded 3 Aug 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200244018576_For_Asset_Based_Search_04_08_2022_19_06_21_534.pdf · uploaded 3 Aug 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 new merged_final signed_compressed.pdf · uploaded 3 Aug 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about separate Bank Account.pdf · uploaded 3 Aug 2022Source
  • 1 Deviation Report with respect to Allotment letterDeclaration regarding No deviation with respect to allotment letter.pdf · uploaded 3 Aug 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeclaration regarding No deviation with respect to Model copy of agreement.pdf · uploaded 3 Aug 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 DATED 31DEC 2022.pdf · uploaded 4 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 CERTIFICATE 31DEC2022.pdf · uploaded 4 Apr 2023Source
  • 1 Disclosure of sold/ booked inventoryVpp discloser of Units 31DEC22.pdf · uploaded 12 Apr 2023Source
  • 2 Disclosure of sold/ booked inventoryVPP INVENTORY SOLD AS ON 31ST MARCH23.pdf · uploaded 28 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Vijay Paper Product 30-09-2024.pdf · uploaded 6 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate Vijay Paper Product 30-09-2024.pdf · uploaded 6 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VPP 30 JUNE24.pdf · uploaded 19 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VPP 31 DEC 24.pdf · uploaded 19 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VPP 30 SEP 2023.pdf · uploaded 19 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)VPP FORM 1 31mARCH 2024.pdf · uploaded 19 Feb 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)VPP FORM 1 31 DEC 23.pdf · uploaded 19 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2024.pdf · uploaded 19 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)VPP FORM 3 Final SEPT 24.pdf · uploaded 19 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VPP 31 DEC 24.pdf · uploaded 19 Feb 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)vpp fORM 2 31MARCH 24.pdf · uploaded 19 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)VPP FORM 2 DEC 2023.pdf · uploaded 19 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)VPP FORM 2 30 SEPT 2023.pdf · uploaded 19 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 vPP 30 JUNE24.pdf · uploaded 19 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryVPP SOLD INVENTORY 30JUNE24.pdf · uploaded 19 Feb 2025Source
  • 2 Disclosure of sold/ booked inventoryVijay Paper Product inventory 30 SEPT 2024.pdf · uploaded 19 Feb 2025Source
  • 3 Disclosure of sold/ booked inventoryVPP INVENTORY SOLD CERTIFICATE 31 DEC24.pdf · uploaded 19 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Vijay Paper Product - Form 2A - 31 MARCH 23.pdf · uploaded 19 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Vijay Paper Product - Form 2A - 31 MARCH 24.pdf · uploaded 19 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vijay Paper Product Form 3 FOR 31 MARCH 2023.pdf · uploaded 20 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)vp form 5 FY 2022-23.pdf · uploaded 20 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)vpp form 5 FY 2023 -24.pdf · uploaded 20 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)31-03-2025 vijay paper product architect certificate.pdf · uploaded 23 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-03-2025 vijay paper product engineers certificate.pdf · uploaded 23 Apr 2025Source
  • Form 5 (FY 2024-2025)Form 5 - Vijay Paper Product _Signed.pdf · uploaded 5 Jan 2026Source
  • Form 1Form1 30-09-2024.pdf · uploaded 12 Feb 2026Source
  • Form 2Form2 30-09-2024.pdf · uploaded 12 Feb 2026Source
  • Form 3Form3 30-09-2024.pdf · uploaded 12 Feb 2026Source
  • Disclosure of Sold and Booked Inventory30-09-24 sold Booked.pdf · uploaded 12 Feb 2026Source
  • Form 5 (FY 2022-2023)vpp form 5 FY 2023 -24.pdf · uploaded 13 Feb 2026Source
  • Form 131 March 2023 Architect Certificate.pdf · uploaded 27 Mar 2026Source
  • Form 231 March 2023 Engineer Certificate.pdf · uploaded 27 Mar 2026Source
  • Form 3VPP Form 3 FOR 31 MARCH 2023 signed.pdf · uploaded 27 Mar 2026Source
  • Disclosure of Sold and Booked Inventory31 March 23 sold.pdf · uploaded 27 Mar 2026Source
  • Form 1Architect Certificate VPP 31 dec 2024.pdf · uploaded 27 Mar 2026Source
  • Form 2Engineer Certificate VPP 31 Dec 2024.pdf · uploaded 27 Mar 2026Source
  • Form 3vpp Form 3 December 2024.pdf · uploaded 27 Mar 2026Source
  • Disclosure of Sold and Booked InventoryVijay Paper Product Sold list 31 Dec 2024.pdf · uploaded 27 Mar 2026Source

Technical (Architect)

  • DocumentForm 1 DATED 31DEC 2022.pdf · uploaded 4 Apr 2023Source
  • DocumentForm 1 Architect Certificate Vijay Paper Product 30-09-2024.pdf · uploaded 6 Feb 2025Source
  • DocumentFORM 1 VPP 30 JUNE24.pdf · uploaded 19 Feb 2025Source
  • DocumentFORM 1 VPP 31 DEC 24.pdf · uploaded 19 Feb 2025Source
  • DocumentFORM 1 VPP 30 SEP 2023.pdf · uploaded 19 Feb 2025Source
  • DocumentVPP FORM 1 31mARCH 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentVPP FORM 1 31 DEC 23.pdf · uploaded 19 Feb 2025Source
  • Document31-03-2025 vijay paper product architect certificate.pdf · uploaded 23 Apr 2025Source

Technical (Engineer)

  • DocumentFORM 2 CERTIFICATE 31DEC2022.pdf · uploaded 4 Apr 2023Source
  • DocumentForm 2 Engineers Certificate Vijay Paper Product 30-09-2024.pdf · uploaded 6 Feb 2025Source
  • DocumentFORM 2 vPP 30 JUNE24.pdf · uploaded 19 Feb 2025Source
  • DocumentFORM 2 VPP 31 DEC 24.pdf · uploaded 19 Feb 2025Source
  • DocumentVPP FORM 2 30 SEPT 2023.pdf · uploaded 19 Feb 2025Source
  • DocumentVPP FORM 2 DEC 2023.pdf · uploaded 19 Feb 2025Source
  • Documentvpp fORM 2 31MARCH 24.pdf · uploaded 19 Feb 2025Source
  • Document31-03-2025 vijay paper product engineers certificate.pdf · uploaded 23 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dombivli, Kalyan taluka

Survey, CTS, gat or plot numbers

A 12B 17

Boundaries

North
Dombivli - Kalyan Road
South
Plot no C - 9A
East
Plot no A 13
West
MIDC Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRajesh Thakare—
Chartered accountantAnkur Sangoi—
Chartered accountantNikita Vishal Lapasia—
EngineerRajesh Thakare—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology