Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK, 3BHK192 units in all
- Address
- Survey No 93/3, 93/4, 93/5, Kanchangaon, KanchangaonPIN 421201
- Designated bank account
- 220
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2026
- Registered
- 18 Mar 2020
- Promised
- 30 Dec 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700025125 | 18 Mar 2020 | 30 Dec 2026 | 30 Dec 2026 | M/S Om Swayambhu Siddhivinayak Builders And Developers | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Balaji Annex | 26 | 192 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
192 of 192 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 43.08 sq m · 464 sq ft | 24 | 24 |
| 1BHK | 43.16 sq m · 465 sq ft | 12 | 12 |
| 1BHK | 43.25 sq m · 466 sq ft | 12 | 12 |
| 1BHK | 43.27 sq m · 466 sq ft | 24 | 24 |
| 1BHK | 43.58 sq m · 469 sq ft | 12 | 12 |
| 1BHK | 43.66 sq m · 470 sq ft | 12 | 12 |
| 2BHK | 37.57 sq m · 404 sq ft | 9 | 9 |
| 2BHK | 41.75 sq m · 449 sq ft | 9 | 9 |
Show all 20 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 46.1 sq m · 496 sq ft | 8 | 8 |
| 2BHK | 46.97 sq m · 506 sq ft | 8 | 8 |
| 2BHK | 55.99 sq m · 603 sq ft | 3 | 3 |
| 2BHK | 56.51 sq m · 608 sq ft | 13 | 13 |
| 2BHK | 56.61 sq m · 609 sq ft | 12 | 12 |
| 2BHK | 56.62 sq m · 609 sq ft | 3 | 3 |
| 2BHK | 56.93 sq m · 613 sq ft | 3 | 3 |
| 2BHK | 57.14 sq m · 615 sq ft | 4 | 4 |
| 3BHK | 41.56 sq m · 447 sq ft | 9 | 9 |
| 3BHK | 47.96 sq m · 516 sq ft | 8 | 8 |
| 3BHK | 69.03 sq m · 743 sq ft | 3 | 3 |
| 3BHK | 70.06 sq m · 754 sq ft | 4 | 4 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 154 filings listed on MahaRERA's project page
Finance
- PAN CardCompany PAN Card.pdf · uploaded 12 Feb 2020Source
Legal
Show all 155 documentsShow fewer documents
Migrated
- 2 Copy of the legal title report93-4 Title Certificate.pdf · uploaded 12 Feb 2020Source
- 3 Copy of the legal title report93-5 title Certificate.pdf · uploaded 12 Feb 2020Source
- 1 Details of encumbrancesNo Encumbrance declaration letter.pdf · uploaded 12 Feb 2020Source
- 1 Copy of Layout Approval (in case of layout)HPSCANNER0144.pdf · uploaded 12 Feb 2020Source
- 2 Copy of Layout Approval (in case of layout)HPSCANNER0145.pdf · uploaded 12 Feb 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentHPSCANNER0144.pdf · uploaded 12 Feb 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentHPSCANNER0145.pdf · uploaded 12 Feb 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentBALAJI ANNEX -CC.pdf · uploaded 12 Feb 2020Source
- 1 Declaration in FORM BFom B Sanjay Singh.pdf · uploaded 12 Feb 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 12 Feb 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex Form 2.pdf · uploaded 19 Feb 2020Source
- 1 Proforma of Allotment letterLETTER OF ALLOTMENT-.pdf · uploaded 9 Mar 2020Source
- 2 Proforma of Allotment letterBALAJI ANNEX AGREEMENT DRAFT.pdf · uploaded 9 Mar 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Balaji Annex.pdf · uploaded 11 Mar 2020Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Mar 20.pdf · uploaded 15 Apr 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Jun 20.pdf · uploaded 15 Apr 2021Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sep 20.pdf · uploaded 15 Apr 2021Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 20.pdf · uploaded 15 Apr 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mar 20.pdf · uploaded 15 Apr 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jun 20.pdf · uploaded 15 Apr 2021Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep 20.pdf · uploaded 15 Apr 2021Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec 20.pdf · uploaded 15 Apr 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Mar 20.pdf · uploaded 15 Apr 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jun 20.pdf · uploaded 15 Apr 2021Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 20.pdf · uploaded 15 Apr 2021Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 20.pdf · uploaded 15 Apr 2021Source
- 3 Copy of Layout Approval (in case of layout)HPSCANNER0833.pdf · uploaded 14 Jun 2021Source
- 4 Copy of Layout Approval (in case of layout)HPSCANNER0834.pdf · uploaded 14 Jun 2021Source
- 5 Copy of Layout Approval (in case of layout)HPSCANNER0835.pdf · uploaded 14 Jun 2021Source
- 6 Copy of Layout Approval (in case of layout)HPSCANNER0836.pdf · uploaded 14 Jun 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentBalaji annex 24 floor.pdf · uploaded 14 Jun 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)march 2020.pdf · uploaded 23 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)June 2020.pdf · uploaded 23 Aug 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sept 2020.pdf · uploaded 23 Aug 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Dec 2020.pdf · uploaded 23 Aug 2021Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)march 2021.pdf · uploaded 23 Aug 2021Source
- 1 Declaration about Commencement CertificateBalaji annex.pdf · uploaded 8 Sep 2021Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Aug 2022Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Aug 2022Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Aug 2022Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Aug 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Aug 2022Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Aug 2022Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Aug 2022Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Aug 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_1-compressed.pdf · uploaded 2 Aug 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_2_compressed.pdf · uploaded 2 Aug 2022Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 _1.pdf · uploaded 2 Aug 2022Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_2.pdf · uploaded 2 Aug 2022Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_1.pdf · uploaded 2 Aug 2022Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-2.pdf · uploaded 2 Aug 2022Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-1.pdf · uploaded 2 Aug 2022Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-2.pdf · uploaded 2 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 2020 2021 OSSBD_compressed.pdf · uploaded 12 Jun 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)OSSBD NX FORM 5 310321.pdf · uploaded 12 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)OSSBD NX FORM 5 DT 31032022.pdf · uploaded 12 Jun 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex - Form 1 - 01042022.pdf · uploaded 22 Sep 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji annex - form 1 - 01-07-22.pdf · uploaded 22 Sep 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji annex - form 1 - 01-10-22.pdf · uploaded 22 Sep 2023Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex - Form 1 - 01012023.pdf · uploaded 22 Sep 2023Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex - Form - 1 - Dt - 01042023.pdf · uploaded 22 Sep 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex- Form -2- 01042022_compressed.pdf · uploaded 22 Sep 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex- Form -2- 01072022_compressed.pdf · uploaded 22 Sep 2023Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex- Form -2- 01102022_compressed.pdf · uploaded 22 Sep 2023Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex- Form -2- 01012023_compressed.pdf · uploaded 22 Sep 2023Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex- Form -2- 01042023_compressed.pdf · uploaded 22 Sep 2023Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)Annex Form 3 March 2022-1-6.pdf · uploaded 22 Sep 2023Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)Annex Form 3 March 2022-7-12.pdf · uploaded 22 Sep 2023Source
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)Annex Form 3 June 2022-1-6.pdf · uploaded 22 Sep 2023Source
- 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)Annex Form 3 June 2022-7-12.pdf · uploaded 22 Sep 2023Source
- 18 CA Certificate on Project Cost & Fund withdrawal (Form 3)Annex Form 3 Sept 2022-1-6.pdf · uploaded 22 Sep 2023Source
- 19 CA Certificate on Project Cost & Fund withdrawal (Form 3)Annex Form 3 Sept 2022-7-12.pdf · uploaded 22 Sep 2023Source
- 20 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Annex Form 3 - 31122022-1-6_compressed.pdf · uploaded 22 Sep 2023Source
- 21 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Annex Form 3 - 31122022-7-12_compressed.pdf · uploaded 22 Sep 2023Source
- 22 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Annex Form 3 - 31032023-1-6_compressed.pdf · uploaded 22 Sep 2023Source
- 23 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Annex Form 3 - 31032023-7-12_compressed.pdf · uploaded 22 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)OSSBD NX FORM 2A MAR 22.pdf · uploaded 3 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)OSSBD NX FORM 2A MAR 23.pdf · uploaded 3 Oct 2023Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex - Form - 1 - Dt - 01072023.pdf · uploaded 13 Oct 2023Source
- 24 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Annex - Form 3 - 30062023-1-6_compressed.pdf · uploaded 23 Oct 2023Source
- 25 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Annex - Form 3 - 30062023-7-12_compressed.pdf · uploaded 23 Oct 2023Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Balaji Annex June 2023_compressed.pdf · uploaded 3 Nov 2023Source
- 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex - Form 1 - 01102023.pdf · uploaded 10 Nov 2023Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Balaji Annex sept 2023.pdf · uploaded 22 Dec 2023Source
- 26 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Balaji Annex.pdf · uploaded 22 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Annex 2022 23.pdf · uploaded 28 Dec 2023Source
- 27 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 OSSBD Annex_compressed.pdf · uploaded 22 Jan 2024Source
- 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Balaji annex Dec 23.pdf · uploaded 30 Jan 2024Source
- 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex Form -1 Dt 01012024.pdf · uploaded 19 Feb 2024Source
- 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form - 1 - Balaji Annex - Dt 01-04-2024.pdf · uploaded 22 May 2024Source
- 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex - Form 2 - Dt 31-05-2024.pdf · uploaded 6 Jun 2024Source
- 1 Disclosure of sold/ booked inventoryOSSBD ANNEX SOLD UNSOLD SHEET_compressed.pdf · uploaded 6 Jun 2024Source
- 2 Disclosure of sold/ booked inventoryInventory disclosure march 2024.pdf · uploaded 6 Jun 2024Source
- 28 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 New.pdf · uploaded 6 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)March 2024.pdf · uploaded 18 Jun 2024Source
- 19 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex - Form 1 - Dt 01-07-2024.pdf · uploaded 30 Jul 2024Source
- 19 Engineer’s Certificate on Cost Incurred on Project (Form 2)Balaji Annex Form 2 - Dt 23-07-2024.pdf · uploaded 30 Jul 2024Source
- 3 Disclosure of sold/ booked inventoryInventory Balaji Annex Jun 24_compressed.pdf · uploaded 30 Jul 2024Source
- 29 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Annex - Form 3 - Dt - 30-06-2024_compressed.pdf · uploaded 30 Jul 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Annex Sept 24.pdf · uploaded 20 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Balaji Annex sept 2024.pdf · uploaded 20 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryInventory disclosure Balaji Annex Sept 24.pdf · uploaded 20 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Balaji Annex sept 2024.pdf · uploaded 20 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Annex Sept 24.pdf · uploaded 20 Nov 2024Source
- 2 Disclosure of sold/ booked inventoryInventory disclosure Balaji Annex Sept 24.pdf · uploaded 20 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Annex sept 24.pdf · uploaded 17 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 of Annex 2023 24.pdf · uploaded 21 Dec 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3 of Balaji Annex Dec 2024_compressed.pdf · uploaded 5 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Balaji Annex Dt 01-01-2025- .pdf · uploaded 5 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryInventory of Balaji Annex Dec 2024_compressed.pdf · uploaded 5 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Balaji Annex - Form 1 - Dt -01-01-2025.pdf · uploaded 12 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Balaji Annex - Date 01-04-2025.pdf · uploaded 30 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3 Annex March 2025_compressed.pdf · uploaded 30 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Balaji Annex - Date 01-04-2025.pdf · uploaded 30 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryInventory disclosure Annex March 2025_compressed.pdf · uploaded 30 Apr 2025Source
- Form 1Form 1 - Balaji Annex - Date 01-04-2025.pdf · uploaded 27 Jun 2025Source
- Form 2Form 2 - Balaji Annex - Date 01-04-2025.pdf · uploaded 27 Jun 2025Source
- Form 3Signed Form 3 Annex March 2025_compressed.pdf · uploaded 27 Jun 2025Source
- Disclosure of Sold and Booked InventoryInventory disclosure Annex March 2025.pdf · uploaded 27 Jun 2025Source
- Withdrawal Update Form 1Balaji Annex - Form 1 - Dt 01-07-2025.pdf · uploaded 18 Aug 2025Source
- Withdrawal Update Form 2Form 2 Annex June 25.pdf · uploaded 18 Aug 2025Source
- Withdrawal Update Form 3Form 3 Balaji Annex June 2025_compressed.pdf · uploaded 18 Aug 2025Source
- Withdrawal Update Form 1Balaji Annex - Form 1 - Dt 01-07-2025.pdf · uploaded 24 Oct 2025Source
- Withdrawal Update Form 2Form 2 Annex June 25.pdf · uploaded 24 Oct 2025Source
- Withdrawal Update Form 3Form 3 Balaji Annex June 2025_compressed.pdf · uploaded 24 Oct 2025Source
- Withdrawal Update Form 1Balaji Annex - Form 1 - Sept 25.pdf · uploaded 19 Nov 2025Source
- Withdrawal Update Form 2Balaji Annex - Form 2 - Sept 25.pdf · uploaded 19 Nov 2025Source
- Withdrawal Update Form 3Balaji Annex - Form 3 - Sept 25_compressed.pdf · uploaded 19 Nov 2025Source
- Form 5 (FY 2024-2025)OSS - Form 5 - Annex Dt 1-04-2024 To 31-03-2025.pdf · uploaded 5 Jan 2026Source
- Form 2A (FY 2024-2025)Form 2A - March 25.pdf · uploaded 4 Apr 2026Source
Technical
- DocumentHPSCANNER0144.pdf · uploaded 12 Feb 2020Source
- DocumentHPSCANNER0145.pdf · uploaded 12 Feb 2020Source
- DocumentHPSCANNER0144.pdf · uploaded 12 Feb 2020Source
- DocumentHPSCANNER0145.pdf · uploaded 12 Feb 2020Source
- DocumentHPSCANNER0833.pdf · uploaded 14 Jun 2021Source
- DocumentHPSCANNER0834.pdf · uploaded 14 Jun 2021Source
- DocumentHPSCANNER0835.pdf · uploaded 14 Jun 2021Source
- DocumentHPSCANNER0836.pdf · uploaded 14 Jun 2021Source
Technical (Architect)
Technical (Engineer)
- DocumentForm 2 Annex Sept 24.pdf · uploaded 20 Nov 2024Source
- DocumentForm 2 Annex Sept 24.pdf · uploaded 20 Nov 2024Source
- DocumentForm 2 - Balaji Annex Dt 01-01-2025- .pdf · uploaded 5 Feb 2025Source
- DocumentForm 2 - Balaji Annex - Date 01-04-2025.pdf · uploaded 30 Apr 2025Source
- DocumentBalaji Annex - Form 2 - Sept 25.pdf · uploaded 19 Nov 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Dombivli, Kalyan taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- 18 Meters Dp Road
- South
- Balaji Residency Project
- East
- Survey No 93 Hissa No 6
- West
- Nala
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Nitesh Gupta | — |