Suncity Orion
CompletedBhiwandi (M Corp.), Thane 421305 |Promoter: Nestor Sai Developers Pvt Ltd
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Buildings
- 1
- Land area for this project
- 4,077 sq m (43,884 sq ft)
- Permissible built-up area
- 4,077 sq m (43,884 sq ft)
- Sanctioned built-up area
- 4,077 sq m (43,884 sq ft)
- Recreational open space
- 1,148 sq m (12,361 sq ft)
- Address
- 142/1 Part And 142/2/2, Bhiwandi, BhiwandiPIN 421305
- Designated bank account
- Bank Of Baroda
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
The latest completion date on record passed 6 years and 10 months ago.
- Registered
- 18 Aug 2017
- Promised
- 31 Dec 2018
- Revised
- 31 Dec 2019
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700008247 | 18 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Nestor Sai Developers Pvt Ltd | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Orion Awing And B Wing | 11 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 1 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Orion Awing And B Wing
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
39 documents held by Deedo, 48 filings listed on MahaRERA's project page
Form 1s
Form 2s
Allotment letters
Document library
- Declaration in FORM BFORM B 001.pdf · uploaded 31 Jul 2017View
- Declaration in FORM BFORM B 002.pdf · uploaded 31 Jul 2017View
- Declaration in FORM BFORM B 003.pdf · uploaded 31 Jul 2017View
- Details of encumbrancesNON ENCUMBRANCE.pdf · uploaded 31 Jul 2017View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 001.pdf · uploaded 31 Jul 2017View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 002.pdf · uploaded 31 Jul 2017View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 003.pdf · uploaded 31 Jul 2017View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 004.pdf · uploaded 31 Jul 2017View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 005.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 001.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 002.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 003.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 004.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 005.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 006.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 007.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 008.pdf · uploaded 31 Jul 2017View
- Copy of the legal title reportSEARCH REPORT 001.pdf · uploaded 31 Jul 2017View
- Copy of the legal title reportSEARCH REPORT.pdf · uploaded 31 Jul 2017View
- Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 31 Jul 2017View
- Building Plan Approval (IOD)BUILDING APPROVAL PLAN 001.pdf · uploaded 31 Jul 2017View
- Copy of Layout Approval (in case of layout)LAYOUT PG 01.pdf · uploaded 31 Jul 2017View
- Copy of Layout Approval (in case of layout)LAYOUT 002.pdf · uploaded 31 Jul 2017View
- Building Plan Approval (IOD)BUILDING APPROVAL PALN 002.pdf · uploaded 31 Jul 2017View
- Proforma of Allotment letterAllotment letter 1.pdf · uploaded 31 Jul 2017View
- Proforma of Allotment letteralootment letter 2.pdf · uploaded 31 Jul 2017View
- Proforma of Allotment letterAGREEMENT_FORMAT_RERA.pdf · uploaded 31 Jul 2017View
- Certificates of CA (Form 5)form 5 2018.pdf · uploaded 6 May 2019View
- Certificates of CA (Form 5)form 5 2019.pdf · uploaded 6 May 2019View
- Certificates of CA (Form 5)form 5 2019.pdf · uploaded 6 May 2019View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentorion oc copy_11zon.pdf · uploaded 15 Sep 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 (19-20).pdf · uploaded 16 Sep 2023View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 (19-20)_11zon.pdf · uploaded 16 Sep 2023View
- Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A YEAR CHANGE.pdf · uploaded 16 Sep 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)2 Certificates of CA (Form 5).pdf · uploaded 16 Sep 2023View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 16 Sep 2023View
- Architect’s Certificate on Completion of Project (Form 4)FORM_4.pdf · uploaded 16 Sep 2023View
Promoter documents
- Declaration Form BFORM B 001.pdf · uploaded 31 Jul 2017View
- Declaration Form BFORM B 002.pdf · uploaded 31 Jul 2017View
- Declaration Form BFORM B 003.pdf · uploaded 31 Jul 2017View
- Legal Title reportSEARCH REPORT 001.pdf · uploaded 31 Jul 2017View
- Legal Title reportSEARCH REPORT.pdf · uploaded 31 Jul 2017View
- Legal Title reportTITLE CERTIFICATE.pdf · uploaded 31 Jul 2017View
Technical documents
Proforma allotment letter
- Proforma allotment letteralootment letter 2.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bhiwandi (M Corp.), Bhiwandi taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
142/1 PART AND 142/2/2
Boundaries
- North
- Land S No 142 -2-1 Paiki
- South
- Land S No 136 And D P Road
- East
- Proposed 60 Ft D P Road
- West
- Proposed 60 Ft D P Road And S No 136
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Wasiq Nisar Ahmed Nakhuda | — |
| Chartered accountant | Mukesh Soni & Associates | — |
| Engineer | Pradeep L Lakhotia | — |
| Other | Salim Chand Khatri | — |
Source: MahaRERA project page. Contact details are not shown.