Suncity Orion

Completed

Bhiwandi (M Corp.), Thane 421305 |Promoter: Nestor Sai Developers Pvt Ltd

Residential / Group HousingRERAP51700008247
18 Aug 2017Registered with MahaRERA
31 Dec 2018Promised completion
31 Dec 2019Revised completionPushed back 1 year
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Land area for this project
4,077 sq m (43,884 sq ft)
Permissible built-up area
4,077 sq m (43,884 sq ft)
Sanctioned built-up area
4,077 sq m (43,884 sq ft)
Recreational open space
1,148 sq m (12,361 sq ft)
Address
142/1 Part And 142/2/2, Bhiwandi, BhiwandiPIN 421305
Designated bank account
Bank Of Baroda
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.27926, 73.05006
Suncity Orion is at latitude 19.27926, longitude 73.05006.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 6 years and 10 months ago.

Registered
18 Aug 2017
Promised
31 Dec 2018
Revised
31 Dec 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000824718 Aug 201731 Dec 201831 Dec 2019Nestor Sai Developers Pvt LtdProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Orion Awing And B Wing11—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Orion Awing And B Wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsPAVER BLOCK100%
  • Water SupplyBOREWELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK100%
  • Storm Water DrainsGUTTERS ON PERIPHERI100%
  • Landscaping & Tree PlantingGARDEN LANDSCAPING100%
  • Street LightingSOLAR LIGHTING100%
  • Community BuildingsCOMMUNITY HALL100%
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingBORE WELL TYPE RWH100%
  • Energy managemcntSOLAR WATER HEATER100%
  • Fire protection and fire safety requirementsAS PER MFS NOC100%
  • Electrical meter room, sub-station, receiving stationMETER ROOM100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

39 documents held by Deedo, 48 filings listed on MahaRERA's project page

Titles

Encumbrance

Form bs

Form 1s

Form 2s

Allotment letters

Registration certificate

Form 5s

Extension certificate

Completion

Form 2a

Form 4

Others

Layout plans

Building plans

Document library

  • Declaration in FORM BFORM B 001.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BFORM B 002.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BFORM B 003.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesNON ENCUMBRANCE.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 001.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 002.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 003.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 004.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 005.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 001.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 002.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 003.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 004.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 005.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 006.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 007.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 008.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportSEARCH REPORT 001.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportSEARCH REPORT.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)BUILDING APPROVAL PLAN 001.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT PG 01.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT 002.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)BUILDING APPROVAL PALN 002.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterAllotment letter 1.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letteralootment letter 2.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterAGREEMENT_FORMAT_RERA.pdf · uploaded 31 Jul 2017View
  • Certificates of CA (Form 5)form 5 2018.pdf · uploaded 6 May 2019View
  • Certificates of CA (Form 5)form 5 2019.pdf · uploaded 6 May 2019View
  • Certificates of CA (Form 5)form 5 2019.pdf · uploaded 6 May 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentorion oc copy_11zon.pdf · uploaded 15 Sep 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 (19-20).pdf · uploaded 16 Sep 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 (19-20)_11zon.pdf · uploaded 16 Sep 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A YEAR CHANGE.pdf · uploaded 16 Sep 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)2 Certificates of CA (Form 5).pdf · uploaded 16 Sep 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 16 Sep 2023View
  • Architect’s Certificate on Completion of Project (Form 4)FORM_4.pdf · uploaded 16 Sep 2023View

Promoter documents

  • Declaration Form BFORM B 001.pdf · uploaded 31 Jul 2017View
  • Declaration Form BFORM B 002.pdf · uploaded 31 Jul 2017View
  • Declaration Form BFORM B 003.pdf · uploaded 31 Jul 2017View
  • Legal Title reportSEARCH REPORT 001.pdf · uploaded 31 Jul 2017View
  • Legal Title reportSEARCH REPORT.pdf · uploaded 31 Jul 2017View
  • Legal Title reportTITLE CERTIFICATE.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout ApprovalLAYOUT 002.pdfView
  • Building Plan ApprovalBUILDING APPROVAL PLAN 001.pdfView
  • Building Plan ApprovalBUILDING APPROVAL PALN 002.pdfView
  • Layout ApprovalLAYOUT PG 01.pdfView

Proforma allotment letter

  • Proforma allotment letteralootment letter 2.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bhiwandi (M Corp.), Bhiwandi taluka

Survey, CTS, gat or plot numbers

142/1 PART142/2/2

As published on MahaRERA's project page

142/1 PART AND 142/2/2

Boundaries

North
Land S No 142 -2-1 Paiki
South
Land S No 136 And D P Road
East
Proposed 60 Ft D P Road
West
Proposed 60 Ft D P Road And S No 136

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectWasiq Nisar Ahmed Nakhuda—
Chartered accountantMukesh Soni & Associates—
EngineerPradeep L Lakhotia—
OtherSalim Chand Khatri—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology