Dharmavihar
Completion due Mar 2027Bhiwandi (M Corp.), Thane 421302 |Promoter: MKY Infrastructure
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 9 months
P51700010249The latest completion date on record passed 7 years and 6 months ago.
- Registered
- 24 Aug 2017
- Promised
- 31 Jul 2018
- Revised
- 30 Apr 2019
Completion promised for 31 Mar 2027
P51700019748- Registered
- 5 Mar 2019
- Promised
- 31 Mar 2027
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700010249 | 24 Aug 2017 | 31 Jul 2018 | 30 Apr 2019 | MKY Infrastructure | Project page |
| P51700019748 | 5 Mar 2019 | 31 Mar 2027 | — | MKY Infrastructure | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bhiwandi (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.