Skip to content

Arihant City

Certificate Signed

Bhiwandi (M Corp.), Thane 421302 |Promoter: Arihant Enterprises

10 Jan 2021Registered with MahaRERAFirst of 3 registrations
31 Dec 2028Promised completionLatest across registrations
3Buildings3 phases
423Units registered127 booked (30%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
RERA registrations
3
Phases
3
Buildings
3
Unit types
1 BHK, 1BHK423 units in all
Address
49/1p, 49/2, 49/3p, 50/1p, 52/1p, 52/1p, 53/1p, 53/1p, 53/1p, 53/2p, 55p, 55p, 55p, 56p, 56p, 56p, 57/3 And Others, Kalyan Bhiwandi Road, BhadwadPIN 421302
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.21833, 72.97809
Arihant City is at latitude 19.21833, longitude 72.97809.

Also registered as

Arihant City Phase-II - M BuildingArihant City Phase-II - N BuildingArihant City Phase-II - L Building

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2028

P51700027862
Registered
10 Jan 2021
Promised
31 Dec 2028

Completion promised for 31 Dec 2028

P51700028430
Registered
2 Mar 2021
Promised
31 Dec 2028

Completion promised for 30 Jun 2026

P51700028441

The latest completion date on record passed 4 months ago.

Registered
2 Mar 2021
Promised
30 Jun 2026

3 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002786210 Jan 202131 Dec 202831 Dec 2028Arihant EnterprisesProject page
P517000284302 Mar 202131 Dec 202831 Dec 2028Arihant EnterprisesProject page
P517000284412 Mar 202130 Jun 202630 Jun 2026Arihant EnterprisesProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
L Building20141
M Building20141
N Building20141

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

127 of 423 units booked (30%), as the promoter reported to MahaRERA

1 BHK · 282 units1BHK · 141 units
RERABuildingTypeCarpet areaUnitsBooked
P51700028441L Building1 BHK44.47 sq m · 479 sq ft14139
P51700028430M Building1 BHK44.47 sq m · 479 sq ft14131
P51700027862N Building1BHK44.47 sq m · 479 sq ft14157

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

3 documents held by Deedo, 587 filings listed on MahaRERA's project page

Registration certificate (3)

  • Registration certificateP51700028441 · 8 Sep 2021ViewSource
  • Registration certificateP51700028430 · 19 Aug 2026ViewSource
  • Registration certificateP51700027862 · 20 Aug 2026ViewSource

Finance

  • PAN CardP51700027862 · Arihant Pancard.pdf · uploaded 9 Dec 2020Source
  • PAN CardP51700028441 · Arihant Pancard.pdf · uploaded 16 Feb 2021Source
  • PAN CardP51700028430 · Arihant Pancard.pdf · uploaded 16 Feb 2021Source

Legal

  • Legal Title reportP51700027862 · PHASE-II PROJECT TITLE REPORT.pdf · uploaded 9 Dec 2020Source
  • Declaration Form BP51700027862 · FORM B PHASE-II.pdf · uploaded 9 Dec 2020Source
Show all 590 documentsShow fewer documents

Legal

  • Declaration Form BP51700027862 · FORM-B ARIHANT N BUILDING_compressed.pdf · uploaded 4 Jan 2021Source
  • Legal Title reportP51700028441 · PHASE-II PROJECT TITLE REPORT.pdf · uploaded 16 Feb 2021Source
  • Declaration Form BP51700028441 · FORM-B ARIHANT L BUILDING_compressed.pdf · uploaded 16 Feb 2021Source
  • Legal Title reportP51700028430 · PHASE-II PROJECT TITLE REPORT.pdf · uploaded 16 Feb 2021Source
  • Declaration Form BP51700028430 · FORM-B ARIHANT M BUILDING_compressed.pdf · uploaded 16 Feb 2021Source

Migrated

  • 1 PAN CardP51700027862 · Arihant Pancard.pdf · uploaded 9 Dec 2020Source
  • 1 Copy of the legal title reportP51700027862 · PHASE-II PROJECT TITLE REPORT.pdf · uploaded 9 Dec 2020Source
  • 1 Details of encumbrancesP51700027862 · N BLDG ENCUMBRANCES.pdf · uploaded 9 Dec 2020Source
  • 1 Copy of Layout Approval (in case of layout)P51700027862 · PHASE-II NEW SANCTION PLAN.pdf · uploaded 9 Dec 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700027862 · N BLDG BUILDING SANCTIONED PLAN (1).pdf · uploaded 9 Dec 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700027862 · Commencement Certificate.pdf · uploaded 9 Dec 2020Source
  • 1 Declaration in FORM BP51700027862 · FORM B PHASE-II.pdf · uploaded 9 Dec 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · ARCHITECT CERTICIATE N BUILDING.pdf · uploaded 9 Dec 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · ENGINEER CERTIFICATE N BUILDING.pdf · uploaded 9 Dec 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · CA CERTIFICATE N BUILDING.pdf · uploaded 9 Dec 2020Source
  • 1 Proforma of Allotment letterP51700027862 · Draft Agreement Letter - PHASE-II.pdf · uploaded 9 Dec 2020Source
  • 2 Proforma of Allotment letterP51700027862 · Draft Allotment Letter - PHASE-II.pdf · uploaded 9 Dec 2020Source
  • 2 Declaration in FORM BP51700027862 · FORM-B ARIHANT N BUILDING_compressed.pdf · uploaded 4 Jan 2021Source
  • 1 PAN CardP51700028441 · Arihant Pancard.pdf · uploaded 16 Feb 2021Source
  • 1 Copy of the legal title reportP51700028441 · PHASE-II PROJECT TITLE REPORT.pdf · uploaded 16 Feb 2021Source
  • 1 Details of encumbrancesP51700028441 · L BLDG ENCUMBRANCE.pdf · uploaded 16 Feb 2021Source
  • 1 Copy of Layout Approval (in case of layout)P51700028441 · PHASE-II NEW SANCTION PLAN.pdf · uploaded 16 Feb 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700028441 · L BLDG SANCTIONED PLAN.pdf · uploaded 16 Feb 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700028441 · Commencement Certificate.pdf · uploaded 16 Feb 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentP51700028441 · IOD 20-05-2019 - PHASE-II.pdf · uploaded 16 Feb 2021Source
  • 1 Declaration in FORM BP51700028441 · FORM-B ARIHANT L BUILDING_compressed.pdf · uploaded 16 Feb 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · ARCHITECT CERTIFICATE L BUILDING.pdf · uploaded 16 Feb 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · ENGINEER CERTIFICATE L BUILDING.pdf · uploaded 16 Feb 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · CA CERTIFICATE L BUILDING.pdf · uploaded 16 Feb 2021Source
  • 1 Proforma of Allotment letterP51700028441 · Draft Allotment Letter - PHASE-II.pdf · uploaded 16 Feb 2021Source
  • 2 Proforma of Allotment letterP51700028441 · L BLDG Draft Agreement.pdf · uploaded 16 Feb 2021Source
  • 1 PAN CardP51700028430 · Arihant Pancard.pdf · uploaded 16 Feb 2021Source
  • 1 Copy of the legal title reportP51700028430 · PHASE-II PROJECT TITLE REPORT.pdf · uploaded 16 Feb 2021Source
  • 1 Details of encumbrancesP51700028430 · M BLDG ENCUMBRANCE.pdf · uploaded 16 Feb 2021Source
  • 1 Copy of Layout Approval (in case of layout)P51700028430 · PHASE-II NEW SANCTION PLAN.pdf · uploaded 16 Feb 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700028430 · M BLDG SANCTIONED PLAN.pdf · uploaded 16 Feb 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700028430 · Commencement Certificate.pdf · uploaded 16 Feb 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentP51700028430 · IOD 20-05-2019 - PHASE-II.pdf · uploaded 16 Feb 2021Source
  • 1 Declaration in FORM BP51700028430 · FORM-B ARIHANT M BUILDING_compressed.pdf · uploaded 16 Feb 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · ARCHITECT CERTICIATE M BUILDING.pdf · uploaded 16 Feb 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · ENGINEER CERTIFICATE M BUILDING.pdf · uploaded 16 Feb 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · CA CERTIFICATE M BUILDING.pdf · uploaded 16 Feb 2021Source
  • 1 Proforma of Allotment letterP51700028430 · Draft Allotment Letter - PHASE-II.pdf · uploaded 16 Feb 2021Source
  • 2 Proforma of Allotment letterP51700028430 · M BLDG Draft Agreement.pdf · uploaded 16 Feb 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · MAR-21 ARCH-CERT - N.pdf · uploaded 12 Jul 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · MAR-21 ENGG-CERT - N.pdf · uploaded 12 Jul 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · MAR-21 ARCH-CERT - L.pdf · uploaded 12 Jul 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · MAR-21 ENGG-CERT - L.pdf · uploaded 12 Jul 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · MAR-21 ARCH-CERT - M.pdf · uploaded 12 Jul 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · MAR-21 ENGG-CERT - M.pdf · uploaded 12 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P51700027862 · Engineer Certificate March 2021 N Building.pdf · uploaded 13 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P51700028441 · Engineer Certificate March 2021 L Building.pdf · uploaded 13 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P51700028430 · Engineer Certificate March 2021 M Building.pdf · uploaded 13 Jul 2021Source
  • 1 Disclosure of sold/ booked inventoryP51700027862 · MAR-21 RERA DISCLOSURE - N.pdf · uploaded 28 Sep 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · MAR-21 CA-CERT - N.pdf · uploaded 28 Sep 2021Source
  • 1 Disclosure of sold/ booked inventoryP51700028441 · MAR-21 RERA DISCLOSURE - L.pdf · uploaded 28 Sep 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · MAR-21 CA-CERT - L.pdf · uploaded 28 Sep 2021Source
  • 1 Disclosure of sold/ booked inventoryP51700028430 · MAR-21 RERA DISCLOSURE - M.pdf · uploaded 28 Sep 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · MAR-21 CA-CERT - M.pdf · uploaded 28 Sep 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · JUN-21 ARCH-CERT - N.pdf · uploaded 21 Oct 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · SEP-21 ARCH-CERT - N.pdf · uploaded 21 Oct 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · JUN-21 ENGG-CERT - N.pdf · uploaded 21 Oct 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · SEP-21 ENGG-CERT - N.pdf · uploaded 21 Oct 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · JUN-21 ARCH-CERT - L.pdf · uploaded 21 Oct 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · SEP-21 ARCH-CERT - L.pdf · uploaded 21 Oct 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · JUN-21 ENGG-CERT - L.pdf · uploaded 21 Oct 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · SEP-21 ENGG-CERT - L.pdf · uploaded 21 Oct 2021Source
  • 2 Disclosure of sold/ booked inventoryP51700028441 · JUN-21 RERA DISCLOSURE - L.pdf · uploaded 21 Oct 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · JUN-21 ARCH-CERT - M.pdf · uploaded 21 Oct 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · SEP-21 ARCH-CERT - M.pdf · uploaded 21 Oct 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · JUN-21 ENGG-CERT - M.pdf · uploaded 21 Oct 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · SEP-21 ENGG-CERT - M.pdf · uploaded 21 Oct 2021Source
  • 2 Disclosure of sold/ booked inventoryP51700028430 · JUN-21 RERA DISCLOSURE - M.pdf · uploaded 21 Oct 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · JUN-21 CA-CERT - L.pdf · uploaded 2 Dec 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · JUN-21 CA-CERT - M.pdf · uploaded 2 Dec 2021Source
  • 1 Declaration about Commencement CertificateP51700027862 · FORMAT D PHASE-II.pdf · uploaded 15 Dec 2021Source
  • 1 Declaration about Commencement CertificateP51700028441 · FORMAT D PHASE-II.pdf · uploaded 15 Dec 2021Source
  • 3 Disclosure of sold/ booked inventoryP51700028441 · SEP-21 RERA DISCLOSURE - L.pdf · uploaded 15 Dec 2021Source
  • 1 Declaration about Commencement CertificateP51700028430 · FORMAT D PHASE-II.pdf · uploaded 15 Dec 2021Source
  • 3 Disclosure of sold/ booked inventoryP51700028430 · SEP-21 RERA DISCLOSURE - M.pdf · uploaded 15 Dec 2021Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · SEP-21 CA-CERT - L.pdf · uploaded 8 Jan 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · SEP-21 CA-CERT - M.pdf · uploaded 8 Jan 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P51700028441 · MAR-21 CA-FORM_5 - L.pdf · uploaded 8 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P51700027862 · MAR-21 CA-FORM_5 - N.pdf · uploaded 9 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P51700028430 · MAR-21 CA-FORM_5 - M.pdf · uploaded 9 Apr 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · JUN-21 CA-CERT - N.pdf · uploaded 25 Apr 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · SEP-21 CA-CERT - N.pdf · uploaded 25 Apr 2022Source
  • 2 Disclosure of sold/ booked inventoryP51700027862 · JUN-21 RERA DISCLOSURE - N.pdf · uploaded 28 Apr 2022Source
  • 3 Disclosure of sold/ booked inventoryP51700027862 · SEP-21 RERA DISCLOSURE -N.pdf · uploaded 28 Apr 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · DEC-21 ARCH-CERT - N.pdf · uploaded 20 May 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · DEC-21 ENGG-CERT - N.pdf · uploaded 20 May 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · DEC-21 ARCH-CERT - L.pdf · uploaded 20 May 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · DEC-21 ENGG-CERT - L.pdf · uploaded 20 May 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · DEC-21 ARCH-CERT - M.pdf · uploaded 20 May 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · DEC-21 ENGG-CERT - M.pdf · uploaded 20 May 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · MAR-22 ARCH-CERT - N.pdf · uploaded 24 May 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P51700027862 · Form Engineer Cetificate Phase II N Bldg March 2022.pdf · uploaded 24 May 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · MAR-22 ARCH-CERT - L.pdf · uploaded 24 May 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P51700028441 · Form Engineer Certificate Phase II L Bldg March 2022.pdf · uploaded 24 May 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · MAR-22 ARCH-CERT - M.pdf · uploaded 24 May 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P51700028430 · Form Engineer Certificate Phase II M Bldg March 2022.pdf · uploaded 24 May 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · DEC-21 CA-CERT - N.pdf · uploaded 25 May 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · DEC-21 CA-CERT - L.pdf · uploaded 25 May 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · DEC-21 CA-CERT - M.pdf · uploaded 25 May 2022Source
  • 2 Details of encumbrancesP51700027862 · Encumbrance Building N.pdf · uploaded 4 Jun 2022Source
  • 2 Details of encumbrancesP51700028441 · Encumbrance Building L.pdf · uploaded 4 Jun 2022Source
  • 2 Details of encumbrancesP51700028430 · Encumbrance Building M.pdf · uploaded 4 Jun 2022Source
  • 4 Disclosure of sold/ booked inventoryP51700027862 · DEC-21 RERA DISCLOSURE - N.pdf · uploaded 25 Jun 2022Source
  • 5 Disclosure of sold/ booked inventoryP51700027862 · MAR-22 RERA DISCLOSURE - N.pdf · uploaded 25 Jun 2022Source
  • 4 Disclosure of sold/ booked inventoryP51700028441 · DEC-21 RERA DISCLOSURE - L.pdf · uploaded 25 Jun 2022Source
  • 5 Disclosure of sold/ booked inventoryP51700028441 · MAR-22 RERA DISCLOSURE - L.pdf · uploaded 25 Jun 2022Source
  • 4 Disclosure of sold/ booked inventoryP51700028430 · DEC-21 RERA DISCLOSURE - M.pdf · uploaded 25 Jun 2022Source
  • 5 Disclosure of sold/ booked inventoryP51700028430 · MAR-22 RERA DISCLOSURE - M.pdf · uploaded 25 Jun 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · MAR-22 ENGG-CERT- N.pdf · uploaded 5 Jul 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · MAR-22 ENGG-CERT- L.pdf · uploaded 5 Jul 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · MAR-22 ENGG-CERT- M.pdf · uploaded 5 Jul 2022Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · MAR-22 CA-CERT - N.pdf · uploaded 2 Aug 2022Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · MAR-22 CA-CERT - L.pdf · uploaded 2 Aug 2022Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · MAR-22 CA-CERT - M.pdf · uploaded 2 Aug 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · JUN-22 ARCH-CERT - N.pdf · uploaded 22 Aug 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · JUN-22 ENGG-CERT - N.pdf · uploaded 22 Aug 2022Source
  • 6 Disclosure of sold/ booked inventoryP51700027862 · JUN-22 RERA DISCLOSURE - N.pdf · uploaded 22 Aug 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700027862 · Format A Building -N.pdf · uploaded 22 Aug 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · JUN-22 ARCH-CERT - L.pdf · uploaded 22 Aug 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · JUN-22 ENGG CERT - L.pdf · uploaded 22 Aug 2022Source
  • 6 Disclosure of sold/ booked inventoryP51700028441 · JUN-22 RERA DISCLOSURE - L.pdf · uploaded 22 Aug 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700028441 · Format A Building -L.pdf · uploaded 22 Aug 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · JUN-22 ARCH-CERT - M.pdf · uploaded 22 Aug 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · JUN-22 ARCH-CERT - M.pdf · uploaded 22 Aug 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · JUN-22 ENGG-CERT - M.pdf · uploaded 22 Aug 2022Source
  • 6 Disclosure of sold/ booked inventoryP51700028430 · JUN-22 RERA DISCLOSURE - M.pdf · uploaded 22 Aug 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700028430 · Format A Building -M.pdf · uploaded 22 Aug 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · SEP-22 ARCH-CERT - N.pdf · uploaded 13 Oct 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · SEP-22 ARCH-CERT - L.pdf · uploaded 13 Oct 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · SEP-22 ARCH-CERT - M.pdf · uploaded 13 Oct 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · SEP-22 ENGG-CERT - N.pdf · uploaded 28 Jan 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · SEP-22 ENGG-CERT - L.pdf · uploaded 28 Jan 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · SEP-22 ARCH-CERT - L.pdf · uploaded 28 Jan 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · SEP-22 ARCH-CERT - M.pdf · uploaded 28 Jan 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · SEP-22 ENGG-CERT - M.pdf · uploaded 28 Jan 2023Source
  • 7 Disclosure of sold/ booked inventoryP51700027862 · Maha Disclosure Sept 22 N- Building.pdf · uploaded 30 Jan 2023Source
  • 7 Disclosure of sold/ booked inventoryP51700028441 · Maha Disclosure Sept 22 L Building.pdf · uploaded 30 Jan 2023Source
  • 7 Disclosure of sold/ booked inventoryP51700028430 · Maha Disclosure Sept 22 M- Building.pdf · uploaded 30 Jan 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · DEC-22 ARCH-CERT - N.pdf · uploaded 7 Feb 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · DEC-22 ARCH-CERT - L.pdf · uploaded 7 Feb 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · DEC-22 ARCH-CERT - M.pdf · uploaded 7 Feb 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · Form 2 Building - N Dec 22.pdf · uploaded 10 Feb 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · Form 2 Building- L Dec 22.pdf · uploaded 10 Feb 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · Form 2 Building- M Dec 22.pdf · uploaded 10 Feb 2023Source
  • 8 Disclosure of sold/ booked inventoryP51700027862 · MahaReRa Discolcure Letter Dec 22 N Building (1).pdf · uploaded 18 Feb 2023Source
  • 8 Disclosure of sold/ booked inventoryP51700028441 · MahaReRa Discolcure Letter Dec 22 L Building (1).pdf · uploaded 18 Feb 2023Source
  • 8 Disclosure of sold/ booked inventoryP51700028430 · MahaReRa Discolcure Letter Dec 22 M Building (1).pdf · uploaded 18 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700027862 · Phase II- N Building (1).pdf · uploaded 22 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700028441 · Phase II- L Building (1).pdf · uploaded 22 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700028430 · Phase II- M Building (1).pdf · uploaded 22 Feb 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · Form 1 March 23 N Building.pdf · uploaded 22 Apr 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · Form 1 March 23 L Building.pdf · uploaded 22 Apr 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · Form 1 March 23 M Building.pdf · uploaded 22 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P51700027862 · ENGINEER'S CERTIFICATE (N BUILDING) MARCH,2023 (1).pdf · uploaded 12 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P51700028441 · ENGINEER 'S CERTIFICATE (L BUILDING) MARCH ,2023 (1).pdf · uploaded 12 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P51700028430 · ENGINEER'S CERTIFICATE (M BUILDING) (MARCH, 2023) (1).pdf · uploaded 12 May 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · Form 3 Building N June 22.pdf · uploaded 22 May 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · Form 3 Building L June 22.pdf · uploaded 22 May 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · Form 3 Building M June 22 (1).pdf · uploaded 22 May 2023Source
  • 9 Disclosure of sold/ booked inventoryP51700027862 · MahaRera Discloser N Building March 23 (1).pdf · uploaded 24 May 2023Source
  • 9 Disclosure of sold/ booked inventoryP51700028441 · MahaRera Discloser L Building March 23 (1).pdf · uploaded 24 May 2023Source
  • 9 Disclosure of sold/ booked inventoryP51700028430 · MahaRera Discloser M Building March 23 (1).pdf · uploaded 24 May 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · SEP-22 CA-CERT - N.pdf · uploaded 16 Jun 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · SEP-22 CA-CERT - L.pdf · uploaded 16 Jun 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · SEP-22 CA-CERT - M.pdf · uploaded 16 Jun 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · JUN-23 ARCH-CERT - N.pdf · uploaded 20 Jul 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · JUN-23 ARCH-CERT - L.pdf · uploaded 20 Jul 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · JUN-23 ARCH-CERT - M.pdf · uploaded 20 Jul 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · Form 2 March 23 Building N.pdf · uploaded 7 Aug 2023Source
  • 10 Disclosure of sold/ booked inventoryP51700027862 · MahaRera Disclosure June 23 Building N.pdf · uploaded 7 Aug 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · Form2 March 23 Building L.pdf · uploaded 7 Aug 2023Source
  • 10 Disclosure of sold/ booked inventoryP51700028441 · MahaRera Disclosure June 23 Building L.pdf · uploaded 7 Aug 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · Form2 March 23 Building M.pdf · uploaded 7 Aug 2023Source
  • 10 Disclosure of sold/ booked inventoryP51700028430 · MahaRera Disclosure June 23 Building M.pdf · uploaded 7 Aug 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · DEC-22 CA-CERT - N.pdf · uploaded 26 Sep 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · MAR-23 CA-CERT - N.pdf · uploaded 26 Sep 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · DEC-22 CA-CERT - L.pdf · uploaded 26 Sep 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · MAR-23 CA-CERT - L.pdf · uploaded 26 Sep 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · DEC-22 CA-CERT - M.pdf · uploaded 26 Sep 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · MAR-23 CA-CERT - M.pdf · uploaded 26 Sep 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · SEP-23 ARCH-CERT - N.pdf · uploaded 2 Nov 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · SEP-23 ARCH-CERT - L.pdf · uploaded 2 Nov 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · SEP-23 ARCH-CERT - M.pdf · uploaded 2 Nov 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · DEC-23 ARCH-CERT - N.pdf · uploaded 31 Jan 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · DEC-23 ARCH-CERT - L.pdf · uploaded 31 Jan 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · DEC-23 ARCH-CERT - M.pdf · uploaded 31 Jan 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · MAR-24 ARCH-CERT - N.pdf · uploaded 4 May 2024Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · MAR-24 ARCH-CERT - L.pdf · uploaded 4 May 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · MAR-24 ARCH-CERT - M.pdf · uploaded 4 May 2024Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · JUN-24 ARCH-CERT - N.pdf · uploaded 12 Jul 2024Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · JUN-24 ARCH-CERT - L.pdf · uploaded 12 Jul 2024Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · JUN-24 ARCH-CERT - M.pdf · uploaded 12 Jul 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · SEP-24 ARCH-CERT - N.pdf · uploaded 18 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · SEP-24 ARCH-CERT - L.pdf · uploaded 18 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · SEP-24 ARCH-CERT - M.pdf · uploaded 18 Oct 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · June 23 - N Bldg.pdf · uploaded 27 Dec 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · Sept 23 - N Bldg.pdf · uploaded 27 Dec 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · Dec 23 - N Bldg_241227_153647.pdf · uploaded 27 Dec 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · June 23 - L Bldg.pdf · uploaded 27 Dec 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · Sept 23 - L Bldg.pdf · uploaded 27 Dec 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · Dec 23 - L Bldg.pdf · uploaded 27 Dec 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · June 23 - M Bldg.pdf · uploaded 27 Dec 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · Sept 23 - M Bldg.pdf · uploaded 27 Dec 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · Dec 23 - M Bldg.pdf · uploaded 27 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · DEC-24 ARCH-CERT - N.pdf · uploaded 14 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · MAR-24 ENGG-CERT - N.pdf · uploaded 14 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · JUN-24 ENGG-CERT- N.pdf · uploaded 14 Jan 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · SEP-24 ENGG-CERT- N.pdf · uploaded 14 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · DEC-24 ARCH-CERT - L.pdf · uploaded 14 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · MAR-24 ENGG-CERT - L.pdf · uploaded 14 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · JUN-24 ENGG-CERT- L.pdf · uploaded 14 Jan 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · SEP-24 ENGG-CERT- L.pdf · uploaded 14 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · DEC-24 ARCH-CERT - M.pdf · uploaded 14 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · MAR-24 ENGG-CERT - M.pdf · uploaded 14 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · JUN-24 ENGG-CERT- M.pdf · uploaded 14 Jan 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · SEP-24 ENGG-CERT- M.pdf · uploaded 14 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700027862 · Form -2A Engineer Certificate N Building March -2024.pdf · uploaded 21 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700028441 · Form -2A Engineer Certificate L Building March 2024.pdf · uploaded 21 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700028430 · Form -2A Engineer Certificate M Building March-2024.pdf · uploaded 21 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700027862 · CA Rera Certificate N Building June -2023.pdf · uploaded 23 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · CA Rera Certificate N Building June -2023.pdf · uploaded 23 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · C A Rera Certificate N Building Sep-2023.pdf · uploaded 23 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · CA Rera Certificate N Building Dec-2023.pdf · uploaded 23 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028441 · CA Rera Certificate L Building June -2023.pdf · uploaded 23 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · CA Rera Certificate L Building June -2023.pdf · uploaded 23 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · CA Rera Certificate L Building Sep-2023.pdf · uploaded 23 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · CA Rera Certificate L Building Dec-2023.pdf · uploaded 23 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700028430 · CA Rera Certificate M Building June -2023.pdf · uploaded 23 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · CA Rera Certificate M Building June -2023.pdf · uploaded 23 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · CA Rera Certificate M Building Sep-2023.pdf · uploaded 23 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · CA Rera Certificate M Building Dec-2023.pdf · uploaded 23 Jan 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700027862 · Form 2 Engineer Certificate N Building Dec -24.pdf · uploaded 30 Jan 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028441 · Form -2Engineer Certificate L Building Dec-24.pdf · uploaded 30 Jan 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700028430 · Form 2- Engineer Certificate M Building Dec-24.pdf · uploaded 30 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700027862 · FORM 2 BUILDING- N- PHASE -II.pdf · uploaded 11 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700028441 · form 2 building- L -PHASE -II.pdf · uploaded 11 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700028430 · FORM 2 BUILDING M-PHASE -II.pdf · uploaded 11 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · MAR-24 CA-CERT - M.pdf · uploaded 15 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · MAR-24 CA-CERT - N.pdf · uploaded 15 Apr 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · JUN-24 CA-CERT - N.pdf · uploaded 15 Apr 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · SE-24 CA-CERT - N.pdf · uploaded 15 Apr 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700027862 · DEC-24 CA-CERT - N.pdf · uploaded 15 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP51700027862 · N-Bldg September 2023.pdf · uploaded 15 Apr 2025Source
  • 2 Disclosure of sold/ booked inventoryP51700027862 · N-Bldg December 2023.pdf · uploaded 15 Apr 2025Source
  • 3 Disclosure of sold/ booked inventoryP51700027862 · N-Bldg March 2024.pdf · uploaded 15 Apr 2025Source
  • 4 Disclosure of sold/ booked inventoryP51700027862 · N-Bldg June 2024.pdf · uploaded 15 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · MAR-24 CA-CERT - L.pdf · uploaded 15 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · JUN-24 CA-CERT - L.pdf · uploaded 15 Apr 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · SEP-24 CA-CERT - L.pdf · uploaded 15 Apr 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028441 · DEC-24 CA-CERT - L.pdf · uploaded 15 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP51700028441 · L-Bldg September 2023.pdf · uploaded 15 Apr 2025Source
  • 2 Disclosure of sold/ booked inventoryP51700028441 · L-Bldg December 2023.pdf · uploaded 15 Apr 2025Source
  • 3 Disclosure of sold/ booked inventoryP51700028441 · L-Bldg March 2024.pdf · uploaded 15 Apr 2025Source
  • 4 Disclosure of sold/ booked inventoryP51700028441 · L-Bldg June 2024.pdf · uploaded 15 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · MAR-24 CA-CERT - M.pdf · uploaded 15 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · JUN-24 CA-CERT - M.pdf · uploaded 15 Apr 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · SEP-24 CA-CERT - M.pdf · uploaded 15 Apr 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700028430 · DEC-24 CA-CERT - M.pdf · uploaded 15 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP51700028430 · M-Bldg September 2023.pdf · uploaded 15 Apr 2025Source
  • 2 Disclosure of sold/ booked inventoryP51700028430 · N-Bldg December 2023.pdf · uploaded 15 Apr 2025Source
  • 3 Disclosure of sold/ booked inventoryP51700028430 · M-Bldg March 2024.pdf · uploaded 15 Apr 2025Source
  • 4 Disclosure of sold/ booked inventoryP51700028430 · M-Bldg June 2024.pdf · uploaded 15 Apr 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Form 5 (FY 2022-2023)P51700027862 · Form 5 Building N 22-23.pdf · uploaded 15 May 2025Source
  • Form 5 (FY 2023-2024)P51700027862 · Form 5 Building N 23-24.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · L BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · L BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · L BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Form 5 (FY 2022-2023)P51700028441 · Form 5 Building L 22-23.pdf · uploaded 15 May 2025Source
  • Form 5 (FY 2023-2024)P51700028441 · Form 5 Building L 23-24.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M BLDG 30_09_2024.pdf · uploaded 15 May 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M BLDG 31_03_2025.pdf · uploaded 15 May 2025Source
  • Form 5 (FY 2022-2023)P51700028430 · Form 5 Building M 22-23.pdf · uploaded 15 May 2025Source
  • Form 5 (FY 2023-2024)P51700028430 · Form 5 Building M 23-24.pdf · uploaded 15 May 2025Source
  • Withdrawal Update Form 1P51700027862 · JUN-25 ARCH-CERT - N.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 2P51700027862 · JUN-25 ENGG-CERT - N.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 3P51700027862 · DEC-24 CA-CERT - N.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 1P51700028441 · JUN-25 ARCH-CERT - L.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 2P51700028441 · JUN-25 ENGG-CERT - L.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 3P51700028441 · DEC-24 CA-CERT - L.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 1P51700028430 · JUN-25 ARCH-CERT - M.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 2P51700028430 · JUN-25 ENGG-CERT - M.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 3P51700028430 · DEC-24 CA-CERT - M.pdf · uploaded 17 Sep 2025Source
  • Form 5 (FY 2024-2025)P51700027862 · FORM-5 FY 2024-25 - N.pdf · uploaded 4 Oct 2025Source
  • Form 5 (FY 2024-2025)P51700028441 · FORM-5 FY 2024-25 - L.pdf · uploaded 4 Oct 2025Source
  • Form 5 (FY 2024-2025)P51700028430 · FORM-5 FY 2024-25 - M.pdf · uploaded 4 Oct 2025Source
  • Withdrawal Update Form 1P51700027862 · JUN-25 ARCH-CERT - N.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 2P51700027862 · JUN-25 ENGG-CERT - N.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 3P51700027862 · JUN-25 CA-CERT - N.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 1P51700028441 · JUN-25 ARCH-CERT - L.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 2P51700028441 · JUN-25 ENGG-CERT - L.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 3P51700028441 · JUN-25 CA-CERT - L.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 1P51700028430 · JUN-25 ARCH-CERT - M.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 2P51700028430 · JUN-25 ENGG-CERT - M.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 3P51700028430 · JUN-25 CA-CERT - M.pdf · uploaded 27 Oct 2025Source
  • Form 1P51700027862 · MAR-21 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · MAR-21 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · MAR-21 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · MAR-21 RERA DISCLOSURE - N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · JUN-21 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · JUN-21 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · JUN-21 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · JUN-21 RERA DISCLOSURE - N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · SEP-21 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · SEP-21 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · SEP-21 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · SEP-21 RERA DISCLOSURE -N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · DEC-21 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · DEC-21 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · DEC-21 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · DEC-21 RERA DISCLOSURE - N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · MAR-22 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · MAR-22 ENGG-CERT- N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · MAR-22 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · MAR-22 RERA DISCLOSURE - N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · JUN-22 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · JUN-22 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · JUN-22 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · JUN-22 RERA DISCLOSURE - N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · SEP-22 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · SEP-22 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · SEP-22 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · SEP-22 RERA DISCLOSURE -N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · DEC-22 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · DEC-22 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · DEC-22 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · DEC-22 RERA DISCLOSURE - N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · MAR-23 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · MAR-23 ENGG-CERT- N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · MAR-23 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · MAR-23 RERA DISCLOSURE - N.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · JUN-23 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · JUN-23 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · JUN-23 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N-Bldg June 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · SEP-23 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · SEP-23 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · SEP-23 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N-Bldg September 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · DEC-23 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · DEC-23 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · DEC-23 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N-Bldg December 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · MAR-24 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · MAR-24 ENGG-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · MAR-24 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N-Bldg March 2024.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700027862 · JUN-24 ARCH-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700027862 · JUN-24 ENGG-CERT- N.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700027862 · JUN-24 CA-CERT - N.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700027862 · N-Bldg June 2024.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · MAR-21 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · MAR-21 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · MAR-21 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · MAR-21 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · JUN-21 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · JUN-21 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · JUN-21 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · JUN-21 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · SEP-21 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · SEP-21 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · SEP-21 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · SEP-21 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · DEC-21 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · DEC-21 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · DEC-21 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · DEC-21 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · MAR-22 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · MAR-22 ENGG-CERT- L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · MAR-22 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · MAR-22 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · JUN-22 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · JUN-22 ENGG CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · JUN-22 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · JUN-22 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · SEP-22 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · SEP-22 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · SEP-22 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · SEP-22 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · DEC-22 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · DEC-22 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · DEC-22 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · DEC-22 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · MAR-23 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · MAR-23 ENGG-CERT- L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · MAR-23 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · MAR-23 RERA DISCLOSURE - L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · JUN-23 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · JUN-23 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · JUN-23 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · MahaRera Disclosure June 23 Building L.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · SEP-23 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · SEP-23 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · SEP-23 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · L-Bldg September 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · DEC-23 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · DEC-23 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · DEC-23 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · L-Bldg December 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · MAR-24 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · MAR-24 ENGG-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · MAR-24 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · L-Bldg March 2024.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028441 · JUN-24 ARCH-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028441 · JUN-24 ENGG-CERT- L.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028441 · JUN-24 CA-CERT - L.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028441 · L-Bldg June 2024.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · MAR-21 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · MAR-21 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · MAR-21 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · MAR-21 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · JUN-21 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · JUN-21 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · JUN-21 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · JUN-21 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · SEP-21 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · SEP-21 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · SEP-21 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · SEP-21 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · DEC-21 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · DEC-21 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · DEC-21 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · DEC-21 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · MAR-22 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · MAR-22 ENGG-CERT- M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · MAR-22 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · MAR-22 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · JUN-22 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · JUN-22 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · JUN-22 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · JUN-22 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · SEP-22 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · SEP-22 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · SEP-22 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · SEP-22 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · DEC-22 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · DEC-22 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · DEC-22 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · DEC-22 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · MAR-23 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · MAR-23 ENGG-CERT- M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · MAR-23 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · MAR-23 RERA DISCLOSURE - M.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · JUN-23 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · JUN-23 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · JUN-23 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M-Bldg June 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · SEP-23 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · SEP-23 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · SEP-23 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M-Bldg September 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · DEC-23 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · DEC-23 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · DEC-23 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M-Bldg December 2023.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · MAR-24 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · MAR-24 ENGG-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · MAR-24 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M-Bldg March 2024.pdf · uploaded 11 Nov 2025Source
  • Form 1P51700028430 · JUN-24 ARCH-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Form 2P51700028430 · JUN-24 ENGG-CERT- M.pdf · uploaded 11 Nov 2025Source
  • Form 3P51700028430 · JUN-24 CA-CERT - M.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP51700028430 · M-Bldg June 2024.pdf · uploaded 11 Nov 2025Source
  • Form 5 (FY 2020-2021)P51700027862 · MAR-21 CA-FORM_5 - N.pdf · uploaded 12 Nov 2025Source
  • Form 5 (FY 2021-2022)P51700027862 · MAR-22 CA-FORM_5 - N.pdf · uploaded 12 Nov 2025Source
  • Form 5 (FY 2020-2021)P51700028441 · MAR-21 CA-FORM_5 - L.pdf · uploaded 12 Nov 2025Source
  • Form 5 (FY 2021-2022)P51700028441 · MAR-22 CA-FORM_5 - L.pdf · uploaded 12 Nov 2025Source
  • Form 5 (FY 2020-2021)P51700028430 · MAR-21 CA-FORM_5 - M.pdf · uploaded 12 Nov 2025Source
  • Form 5 (FY 2021-2022)P51700028430 · MAR-22 CA-FORM_5 - M.pdf · uploaded 12 Nov 2025Source
  • Form 2A (FY 2020-2021)P51700027862 · Engineer Certificate March 2021 N Building.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2021-2022)P51700027862 · Form Engineer Cetificate Phase II N Bldg March 2022.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2022-2023)P51700027862 · ENGINEER'S CERTIFICATE (N BUILDING) MARCH,2023 (1).pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2023-2024)P51700027862 · Form -2A Engineer Certificate N Building March -2024.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2024-2025)P51700027862 · FORM 2 BUILDING- N- PHASE -II MAR 2025.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2020-2021)P51700028441 · Engineer Certificate March 2021 L Building.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2021-2022)P51700028441 · Form Engineer Certificate Phase II L Bldg March 2022.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2022-2023)P51700028441 · ENGINEER 'S CERTIFICATE (L BUILDING) MARCH ,2023 (1).pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2023-2024)P51700028441 · Form -2A Engineer Certificate L Building March 2024.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2024-2025)P51700028441 · form 2 building- L -PHASE -II MAR 2025.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2020-2021)P51700028430 · Engineer Certificate March 2021 M Building.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2021-2022)P51700028430 · Form Engineer Certificate Phase II M Bldg March 2022.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2022-2023)P51700028430 · ENGINEER'S CERTIFICATE (M BUILDING) (MARCH, 2023) (1).pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2023-2024)P51700028430 · Form -2A Engineer Certificate M Building March-2024.pdf · uploaded 14 Nov 2025Source
  • Form 2A (FY 2024-2025)P51700028430 · FORM 2 BUILDING M-PHASE -II MAR 2025.pdf · uploaded 14 Nov 2025Source
  • Withdrawal Update Form 1P51700027862 · SEP-25 ARCH-CERT - N.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 2P51700027862 · JUN-25 ENGG-CERT - N.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 3P51700027862 · SEP-25 CA-CERT - N.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 1P51700028441 · SEP-25 ARCH-CERT - L.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 2P51700028441 · SEP-25 ENGG-CERT - L.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 3P51700028441 · SEP-25 CA-CERT - L.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 1P51700028430 · SEP-25 ARCH-CERT - M.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 2P51700028430 · SEP-25 ENGG-CERT - M.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 3P51700028430 · SEP-25 CA-CERT - M.pdf · uploaded 13 Dec 2025Source
  • Withdrawal Update Form 1P51700028441 · DEC-25 ARCH CERT - L.pdf · uploaded 28 Jan 2026Source
  • Withdrawal Update Form 2P51700028441 · DEC-25 ENGG CERT - L.pdf · uploaded 28 Jan 2026Source
  • Withdrawal Update Form 3P51700028441 · DEC-25 CA CERT - L.pdf · uploaded 28 Jan 2026Source
  • Withdrawal Update Form 1P51700028430 · DEC-25 ARCH CERT - M.pdf · uploaded 28 Jan 2026Source
  • Withdrawal Update Form 2P51700028430 · DEC-25 ENGG CERT - M.pdf · uploaded 28 Jan 2026Source
  • Withdrawal Update Form 3P51700028430 · DEC-25 CA CERT - M.pdf · uploaded 28 Jan 2026Source
  • Withdrawal Update Form 1P51700027862 · DEC-25 ARCH CERT - N.pdf · uploaded 5 Mar 2026Source
  • Withdrawal Update Form 2P51700027862 · DEC-25 ENGG CERT - N.pdf · uploaded 5 Mar 2026Source
  • Withdrawal Update Form 3P51700027862 · DEC-25 CA-CERT - N.pdf · uploaded 5 Mar 2026Source
  • Withdrawal Update Form 1P51700028441 · MAR-26 ARCH-CERT - L.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1P51700028441 · MAR-26 ARCH-CERT - L.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2P51700028441 · MAR-26 ENGG-CERT - L.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2P51700028441 · MAR-26 ENGG-CERT - L.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3P51700028441 · MAR-26 CA-CERT - L.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3P51700028441 · MAR-26 CA-CERT - L.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1P51700028430 · MAR-26 ARCH-CERT - M.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1P51700028430 · MAR-26 ARCH-CERT - M.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2P51700028430 · MAR-26 ENGG-CERT - M.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2P51700028430 · MAR-26 ENGG-CERT - M.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3P51700028430 · MAR-26 CA-CERT - M.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3P51700028430 · MAR-26 CA-CERT - M.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1P51700027862 · MAR-26 ARCH-CERT - N.pdf · uploaded 10 Jun 2026Source
  • Withdrawal Update Form 1P51700027862 · MAR-26 ARCH-CERT - N.pdf · uploaded 10 Jun 2026Source
  • Withdrawal Update Form 2P51700027862 · MAR-26 ENGG-CERT - N.pdf · uploaded 10 Jun 2026Source
  • Withdrawal Update Form 2P51700027862 · MAR-26 ENGG-CERT - N.pdf · uploaded 10 Jun 2026Source
  • Withdrawal Update Form 3P51700027862 · MAR-25 CA-CERT - N.pdf · uploaded 10 Jun 2026Source
  • Withdrawal Update Form 3P51700027862 · MAR-25 CA-CERT - N.pdf · uploaded 10 Jun 2026Source
  • Form 2A (FY 2025-2026)P51700027862 · FORM 2A 2025-2026 - N.pdf · uploaded 29 Jul 2026Source
  • Form 2A (FY 2025-2026)P51700028441 · FORM 2A 2025-2026 - L.pdf · uploaded 29 Jul 2026Source
  • Form 2A (FY 2025-2026)P51700028430 · FORM 2A 2025-2026 - M.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 1P51700027862 · ARCH CERT JUN-2026 - N.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 2P51700027862 · JUN 2026 ENGG CERT - N.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 3P51700027862 · JUN - 2026 CA CERT - N.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 1P51700028441 · ARCH CERT JUN-2026 - L.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 2P51700028441 · JUN 2026 ENGG CERT - L.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 3P51700028441 · JUN - 2026 CA CERT - L.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 1P51700028430 · ARCH CERT JUN-2026 - M.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 2P51700028430 · JUN 2026 ENGG CERT - M.pdf · uploaded 25 Sep 2026Source
  • Withdrawal Update Form 3P51700028430 · JUN - 2026 CA CERT - M.pdf · uploaded 25 Sep 2026Source

Technical

  • DocumentP51700027862 · PHASE-II NEW SANCTION PLAN.pdf · uploaded 9 Dec 2020Source
  • DocumentP51700027862 · N BLDG BUILDING SANCTIONED PLAN (1).pdf · uploaded 9 Dec 2020Source
  • DocumentP51700028441 · PHASE-II NEW SANCTION PLAN.pdf · uploaded 16 Feb 2021Source
  • DocumentP51700028441 · L BLDG SANCTIONED PLAN.pdf · uploaded 16 Feb 2021Source
  • DocumentP51700028430 · PHASE-II NEW SANCTION PLAN.pdf · uploaded 16 Feb 2021Source
  • DocumentP51700028430 · M BLDG SANCTIONED PLAN.pdf · uploaded 16 Feb 2021Source

Technical (Architect)

  • DocumentP51700027862 · SEP-24 ARCH-CERT - N.pdf · uploaded 18 Oct 2024Source
  • DocumentP51700028441 · SEP-24 ARCH-CERT - L.pdf · uploaded 18 Oct 2024Source
  • DocumentP51700028430 · SEP-24 ARCH-CERT - M.pdf · uploaded 18 Oct 2024Source
  • DocumentP51700027862 · DEC-24 ARCH-CERT - N.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028441 · DEC-24 ARCH-CERT - L.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028430 · DEC-24 ARCH-CERT - M.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700027862 · CA Rera Certificate N Building June -2023.pdf · uploaded 23 Jan 2025Source
  • DocumentP51700028441 · CA Rera Certificate L Building June -2023.pdf · uploaded 23 Jan 2025Source
  • DocumentP51700028430 · CA Rera Certificate M Building June -2023.pdf · uploaded 23 Jan 2025Source
  • DocumentP51700027862 · SEP-26 ARCH-CERT - N.pdf · uploaded 7 Oct 2026Source
  • DocumentP51700028441 · SEP-26 ARCH-CERT - L.pdf · uploaded 7 Oct 2026Source
  • DocumentP51700028430 · SEP-26 ARCH-CERT - M.pdf · uploaded 7 Oct 2026Source

Technical (Engineer)

  • DocumentP51700027862 · June 23 - N Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700027862 · Sept 23 - N Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700027862 · Dec 23 - N Bldg_241227_153647.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700028441 · June 23 - L Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700028441 · Sept 23 - L Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700028441 · Dec 23 - L Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700028430 · June 23 - M Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700028430 · Sept 23 - M Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700028430 · Dec 23 - M Bldg.pdf · uploaded 27 Dec 2024Source
  • DocumentP51700027862 · MAR-24 ENGG-CERT - N.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700027862 · JUN-24 ENGG-CERT- N.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700027862 · SEP-24 ENGG-CERT- N.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028441 · MAR-24 ENGG-CERT - L.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028441 · JUN-24 ENGG-CERT- L.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028441 · SEP-24 ENGG-CERT- L.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028430 · MAR-24 ENGG-CERT - M.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028430 · JUN-24 ENGG-CERT- M.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700028430 · SEP-24 ENGG-CERT- M.pdf · uploaded 14 Jan 2025Source
  • DocumentP51700027862 · Form 2 Engineer Certificate N Building Dec -24.pdf · uploaded 30 Jan 2025Source
  • DocumentP51700028441 · Form -2Engineer Certificate L Building Dec-24.pdf · uploaded 30 Jan 2025Source
  • DocumentP51700028430 · Form 2- Engineer Certificate M Building Dec-24.pdf · uploaded 30 Jan 2025Source
  • DocumentP51700027862 · JUN 2026 ENGG CERT - N.pdf · uploaded 4 Aug 2026Source
  • DocumentP51700028441 · JUN 2026 ENGG CERT - L.pdf · uploaded 4 Aug 2026Source
  • DocumentP51700028430 · JUN 2026 ENGG CERT - M.pdf · uploaded 4 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bhiwandi (M Corp.), Bhiwandi taluka

Survey, CTS, gat or plot numbers

49/1P49/249/349/3P50/1P52/1P53/1P53/2P55P56P57/3

Boundaries

North
Adj Temghar Shiv
South
Adj S No 59 And 47
East
Adj Gaothan Adj H No 2 Adj S No 48 Adj S No 57
West
Adj Temghar Shiv

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectAcruti Consultant—P51700028441
ArchitectAkruti Consultant—P51700028430
ArchitectAkruti Consultant—P51700028441
ArchitectAkruti Consultant—P51700027862
Chartered accountantMadrecha And Co.—P51700028441
Chartered accountantMadrecha And Co.—P51700028430
Chartered accountantMadrecha And Co.—P51700027862
EngineerBaiju Jhohn—P51700028430
Show all 19 professionalsShow fewer professionals
RoleNameRegistration no.RERA
EngineerBaiju Jhohn—P51700027862
EngineerBaiju Jhohn—P51700028441
EngineerSachin Chhaya—P51700028430
EngineerSachin Chhaya—P51700027862
EngineerSachin Chhaya—P51700028441
EngineerTechline—P51700028430
EngineerTechline—P51700027862
EngineerTechline—P51700028441
EngineerTech Line Consulting Engineers—P51700027862
EngineerTechline Consulting Engineers—P51700028441
EngineerTechline Consulting Engineers—P51700028430

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology