IDBLD_07393214 floorsExtended 4 mo
14Sanctioned habitable floorsregistration certificate
20 Apr 2027Revised completionpromised 20 Dec 2026

Floors

14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700031081 · registered 5 Oct 2021
Promised completion
20 Dec 2026
Revised completion
20 Apr 2027
Sanctioned habitable floors
14
ProjectId
34,773
ProjectName
SHIV SAI AWAS
TotalUnitCount
150
ProjectBuildingId
1,55,898
BuildingNameNumber
SHIV SAI AWAS BUILDING B
FsiWithSanctionSqmts
15
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
150
ProjectRegistartionNo
P51700031081
ProjectBuildingWingsId
1,59,323
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
SHIV SAI AWAS BUILDING B
NoOfBuildingWingFloorProposed
15
NoOfBuildingWingFloorHabitable
14
NoOfBuildingWingFloorSanctioned
15

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——150not published
Total150
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology