Govind Heights

Certificate Signed

Ashele, Thane 421004 |Promoter: Om Construction

22 Sep 2025Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
70Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—70 units in all
Address
Village AshelePIN 421004
Designated bank account
21
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.14439, 73.17124
Govind Heights is at latitude 19.14439, longitude 73.17124.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
22 Sep 2025
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR133000250086822 Sep 202531 Dec 202730 Apr 2028Om ConstructionProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Govind Heights7870

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

70 units registered

— · 70 units
TypeCarpet areaUnits
——70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 35 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card Om Construction.pdf · uploaded 19 Jul 2025Source
  • Others18Declaration CERSAI certificate_Govind Heights.pdf · uploaded 31 Jul 2025Source
  • Others19Self Declaration Regarding No Encumberances.pdf · uploaded 31 Jul 2025Source
  • OthersOther Financials Details.pdf · uploaded 22 Aug 2025Source

Legal

  • Declaration Form B4Legal Title Report_Govind Heights.pdf · uploaded 17 Jul 2025Source
  • Declaration Form B5Form B-Developer_Govind.pdf · uploaded 17 Jul 2025Source
  • Declaration Form B2Developement Agreement_Govind Heights.pdf · uploaded 19 Jul 2025Source
Show all 36 documentsShow fewer documents

Legal

  • Others16Declaration about commencement certificate.pdf · uploaded 31 Jul 2025Source
  • Others23Form B Land Owner.pdf · uploaded 31 Jul 2025Source
  • OthersPage.pdf · uploaded 9 Sep 2025Source
  • OthersPage.pdf · uploaded 9 Sep 2025Source
  • OthersPage.pdf · uploaded 9 Sep 2025Source
  • OthersPage.pdf · uploaded 9 Sep 2025Source
  • OthersPage.pdf · uploaded 9 Sep 2025Source

Migrated

  • Withdrawal Update Form 1Form 1 Om Construction Sep-25.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Om Construction Sep-25.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 3Form 3 Om Construction Sept 25_compressed.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Om Construction Sep-25.pdf · uploaded 28 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Om Construction Sep-25.pdf · uploaded 28 Nov 2025Source
  • Withdrawal Update Form 3Form 3 Om Construction Sept 25_compressed.pdf · uploaded 28 Nov 2025Source
  • Withdrawal Update Form 1Form-1 Om Construction Dec 25.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 2Form-2 Om Construction Dec 25.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 3Form 3 Om Construction Dec 25.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 1Arch Om Construction March 26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2Engineer Om Construction March 26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3Form 3 Om Construction March 26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1Arch Om Construction June 26.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 2Eng Om Construction June 26.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Om Construction June 26.pdf · uploaded 25 Jul 2026Source
  • Form 5 (FY 2025-2026)Form-5 Signed.pdf · uploaded 28 Sep 2026Source

Technical

  • Document6Building Plan_Govind.pdf · uploaded 17 Jul 2025Source
  • Document7Annexure A_Govind.pdf · uploaded 17 Jul 2025Source
  • Others15Architect Certificate_Govind Heights.pdf · uploaded 31 Jul 2025Source

Technical (Architect)

  • DocumentArch Om Construction June 26.pdf · uploaded 25 Jul 2026Source

Technical (Engineer)

  • DocumentEng Om Construction June 26.pdf · uploaded 25 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ashele, Ambarnath taluka

Survey, CTS, gat or plot numbers

Sector 27S.NO.8 H NO. 3/B

Boundaries

North
Survey No. 8/6
South
Survey No. 8/3 A
East
Survey No. 8/3 A And 8/5
West
Survey No. 8/2 B

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVarghese John—
Chartered accountantDaksha Jeetu Ramrakhiyani—
Chartered accountantJeetu Ramrakhiyani—
EngineerMangesh Gulhane—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology