Navrang Co Op Hsg Society

Certificate Signed

Ambarnath (R), Thane 421501 |Promoter: Yadav Bros Construction

Residential / Group HousingRERAP51700049618
22 Feb 2023Registered with MahaRERA
31 Dec 2024Promised completion
1Building
20Units registered20 booked (100%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK EXISTING, 1BHK SOLD, 2BHK EXISTING, 2BHK SOLD20 units in all
Address
Plot No. 3, Gut No 54, Morivali, MorivaliPIN 421501
Designated bank account
35
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2024

The latest completion date on record passed 1 year and 10 months ago.

Registered
22 Feb 2023
Promised
31 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004961822 Feb 202331 Dec 202431 Dec 2024Yadav Bros ConstructionProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Navrang Co Op Hsg Soc Ltd420

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

20 of 20 units booked (100%), as the promoter reported to MahaRERA

1BHK EXISTING · 3 units1BHK SOLD · 5 units2BHK EXISTING · 7 units2BHK SOLD · 5 units
TypeCarpet areaUnitsBooked
1BHK EXISTING37.33 sq m · 402 sq ft33
1BHK SOLD37.33 sq m · 402 sq ft11
1BHK SOLD39.4 sq m · 424 sq ft44
2BHK EXISTING45.36 sq m · 488 sq ft33
2BHK EXISTING53.06 sq m · 571 sq ft44
2BHK SOLD45.36 sq m · 488 sq ft11
2BHK SOLD54.25 sq m · 584 sq ft44

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 68 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardYBC PAN CARD-converted.pdf · uploaded 4 Oct 2022Source
  • Other – FinanceClarification of Inventory.pdf · uploaded 12 Dec 2024Source

Legal

  • Legal Title reportTITLE.pdf · uploaded 4 Oct 2022Source
  • Declaration Form BForm B Co Promotor.pdf · uploaded 4 Oct 2022Source
  • Other – LegalFORMATE-A.pdf · uploaded 8 Dec 2022Source
  • Legal Title reportFORMATE-A.pdf · uploaded 12 Dec 2022Source

Migrated

  • 1 PAN CardYBC PAN CARD-converted.pdf · uploaded 4 Oct 2022Source
Show all 69 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTITLE.pdf · uploaded 4 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 4 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 4 Oct 2022Source
  • 1 Declaration in FORM BForm B Co Promotor.pdf · uploaded 4 Oct 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Architech Certificate.pdf · uploaded 4 Oct 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Navrang Chs - FORM -2.pdf · uploaded 4 Oct 2022Source
  • 1 Declaration about Commencement CertificateFORMATE- D.pdf · uploaded 11 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 Dec 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report-NAVRANG.pdf · uploaded 6 Dec 2022Source
  • 1 Disclosure of sold/ booked inventoryINVENTORY.pdf · uploaded 6 Dec 2022Source
  • 1 Other – LegalFORMATE-A.pdf · uploaded 8 Dec 2022Source
  • 2 Copy of the legal title reportFORMATE-A.pdf · uploaded 12 Dec 2022Source
  • 1 a Details of encumbrances concerned to FinanceENSUMBARANCES.pdf · uploaded 14 Dec 2022Source
  • 1 b Details of encumbrances concerned to LegalENSUMBARANCES.pdf · uploaded 14 Dec 2022Source
  • 1 Proforma of Allotment letterAllottment Letter.pdf · uploaded 14 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation report for AL.pdf · uploaded 14 Dec 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation report for AFS.pdf · uploaded 14 Dec 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Navrang (ASWA)-signed_compressed.pdf · uploaded 18 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnx A CPY - Signed.pdf · uploaded 18 Jan 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnx A SPY - Signed.pdf · uploaded 18 Jan 2023Source
  • 1 Other – TechnicalPlan with highlighted FSI.pdf · uploaded 19 Jan 2023Source
  • 1 Proforma of Agreement for saleAgreement for Sale.pdf · uploaded 13 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration A for separate bank account.pdf · uploaded 15 Feb 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentNavrang Revise CC.pdf · uploaded 8 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentREVISE Navrang Blue Print 21-03-2024_11zon.pdf · uploaded 8 Oct 2024Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 8 Oct 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPERATE BANK ACCOUNT.pdf · uploaded 8 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect july to sep 23.pdf · uploaded 25 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT oct to dec 23.pdf · uploaded 25 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT april to june 24.pdf · uploaded 25 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG APRIL TO JUNE 24.pdf · uploaded 25 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 1 OCT 23 TO DEC 23.pdf · uploaded 25 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)JULY 23 TO SEP 23.pdf · uploaded 25 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QUALITY ASSURANCE 23-24.pdf · uploaded 25 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT.pdf · uploaded 8 Nov 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT.pdf · uploaded 8 Nov 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng.pdf · uploaded 8 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG.pdf · uploaded 8 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)DRAWING.pdf · uploaded 7 Dec 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold.pdf · uploaded 12 Dec 2024Source
  • 1 Other – FinanceClarification of Inventory.pdf · uploaded 12 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)navrang co op hsg (1).pdf · uploaded 7 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)navrang form-5 (1).pdf · uploaded 7 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)organized (2).pdf · uploaded 28 Jan 2025Source

Technical

  • DocumentPlan.pdf · uploaded 4 Oct 2022Source
  • DocumentPlan.pdf · uploaded 4 Oct 2022Source
  • Other – TechnicalPlan with highlighted FSI.pdf · uploaded 19 Jan 2023Source
  • DocumentREVISE Navrang Blue Print 21-03-2024_11zon.pdf · uploaded 8 Oct 2024Source
  • DocumentDRAWING.pdf · uploaded 7 Dec 2024Source

Technical (Architect)

  • DocumentFORM-1 Architech Certificate.pdf · uploaded 4 Oct 2022Source
  • Documentarchitect july to sep 23.pdf · uploaded 25 Oct 2024Source
  • DocumentARCHITECT oct to dec 23.pdf · uploaded 25 Oct 2024Source
  • DocumentARCHITECT april to june 24.pdf · uploaded 25 Oct 2024Source
  • DocumentARCHITECT.pdf · uploaded 8 Nov 2024Source
  • DocumentARCHITECT.pdf · uploaded 8 Nov 2024Source

Technical (Engineer)

  • DocumentEngineer Certificate - Navrang Chs - FORM -2.pdf · uploaded 4 Oct 2022Source
  • DocumentJULY 23 TO SEP 23.pdf · uploaded 25 Oct 2024Source
  • DocumentENG 1 OCT 23 TO DEC 23.pdf · uploaded 25 Oct 2024Source
  • DocumentENG APRIL TO JUNE 24.pdf · uploaded 25 Oct 2024Source
  • DocumentENG.pdf · uploaded 8 Nov 2024Source
  • Documenteng.pdf · uploaded 8 Nov 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ambarnath (R), Ambarnath taluka

Survey, CTS, gat or plot numbers

Gut No 54Plot No. 3

Boundaries

North
Existing Building
South
9 Mtrs Road
East
Existing Building
West
Shivaji CHS

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrasad K Garad—
Chartered accountantA S Wadiya & Associates—
EngineerAtul Kudtarkar & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology