Skip to content

Trinity Moksh

Certificate Signed

Ambarnath(M Cl), Thane 421501 |Promoter: Rattanraj Lifespaces

15 Oct 2021Registered with MahaRERA
31 Mar 2027Promised completion
31 Jul 2027Revised completionPushed back 4 months
2Buildings
149Units registered18 booked (12%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
2BHK, 3BHK, Office space, Shop, Restaurant, Shop with mezzanine149 units in all
Address
S No 64 1 And 64 2, Nxt To Shiv Mandir Road, PalegaonPIN 421501
Designated bank account
154
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.21833, 72.97809
Trinity Moksh is at latitude 19.21833, longitude 72.97809.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
15 Oct 2021
Promised
31 Mar 2027
Revised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170003126015 Oct 202131 Mar 202731 Jul 2027Rattanraj LifespacesProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Trinity Moksh-Wing A1475
Trinity Moksh-Wing B1474

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

18 of 149 units booked (12%), as the promoter reported to MahaRERA

2BHK · 53 units3BHK · 52 unitsOffice space · 20 unitsShop · 14 unitsRestaurant · 1 unitShop with mezzanine · 9 units
BuildingTypeCarpet areaUnitsBooked
Trinity Moksh-Wing A2BHK64.2 sq m · 691 sq ft276
Trinity Moksh-Wing A3BHK82.52 sq m · 888 sq ft20
Trinity Moksh-Wing A3BHK94.31 sq m · 1,015 sq ft241
Trinity Moksh-Wing AOffice space21.62 sq m · 233 sq ft20
Trinity Moksh-Wing AOffice space29.58 sq m · 318 sq ft10
Trinity Moksh-Wing AOffice space30.18 sq m · 325 sq ft30
Trinity Moksh-Wing AOffice space30.57 sq m · 329 sq ft10
Trinity Moksh-Wing AOffice space33.68 sq m · 363 sq ft20
Show all 40 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Trinity Moksh-Wing AOffice space48.52 sq m · 522 sq ft10
Trinity Moksh-Wing AOffice space54.83 sq m · 590 sq ft10
Trinity Moksh-Wing AShop17.62 sq m · 190 sq ft11
Trinity Moksh-Wing AShop26.96 sq m · 290 sq ft20
Trinity Moksh-Wing AShop29.95 sq m · 322 sq ft10
Trinity Moksh-Wing AShop36.8 sq m · 396 sq ft10
Trinity Moksh-Wing AShop37.5 sq m · 404 sq ft30
Trinity Moksh-Wing AShop43.5 sq m · 468 sq ft10
Trinity Moksh-Wing AShop43.83 sq m · 472 sq ft10
Trinity Moksh-Wing AShop49.64 sq m · 534 sq ft10
Trinity Moksh-Wing B2BHK64.2 sq m · 691 sq ft268
Trinity Moksh-Wing B3BHK82.52 sq m · 888 sq ft20
Trinity Moksh-Wing B3BHK94.31 sq m · 1,015 sq ft240
Trinity Moksh-Wing BOffice space21.62 sq m · 233 sq ft20
Trinity Moksh-Wing BOffice space26.59 sq m · 286 sq ft10
Trinity Moksh-Wing BOffice space28.44 sq m · 306 sq ft10
Trinity Moksh-Wing BOffice space31.18 sq m · 336 sq ft10
Trinity Moksh-Wing BOffice space33.68 sq m · 363 sq ft20
Trinity Moksh-Wing BOffice space49.11 sq m · 529 sq ft10
Trinity Moksh-Wing BOffice space86.67 sq m · 933 sq ft10
Trinity Moksh-Wing BRestaurant167.42 sq m · 1,802 sq ft10
Trinity Moksh-Wing BShop33.2 sq m · 357 sq ft10
Trinity Moksh-Wing BShop35.25 sq m · 379 sq ft10
Trinity Moksh-Wing BShop36.75 sq m · 396 sq ft10
Trinity Moksh-Wing BShop with mezzanine33.74 sq m · 363 sq ft11
Trinity Moksh-Wing BShop with mezzanine50.56 sq m · 544 sq ft20
Trinity Moksh-Wing BShop with mezzanine56.33 sq m · 606 sq ft11
Trinity Moksh-Wing BShop with mezzanine56.6 sq m · 609 sq ft10
Trinity Moksh-Wing BShop with mezzanine60.06 sq m · 646 sq ft10
Trinity Moksh-Wing BShop with mezzanine71.59 sq m · 771 sq ft10
Trinity Moksh-Wing BShop with mezzanine83.17 sq m · 895 sq ft10
Trinity Moksh-Wing BShop with mezzanine88.64 sq m · 954 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 118 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card of Rattanraj Lifespaces.pdf · uploaded 17 Sep 2021Source

Legal

  • Legal Title reportTitle as per format A_compressed.pdf · uploaded 17 Sep 2021Source
  • Legal Title reportSearch Report of Moksh_11zon.pdf · uploaded 17 Sep 2021Source
  • Declaration Form BForm B of Promoter Trinity Moksh_compressed.pdf · uploaded 23 Sep 2021Source
  • Declaration Form BForm-B Developers.pdf · uploaded 29 Mar 2025Source

Migrated

  • 1 PAN CardPAN Card of Rattanraj Lifespaces.pdf · uploaded 17 Sep 2021Source
  • 1 Copy of the legal title reportTitle as per format A_compressed.pdf · uploaded 17 Sep 2021Source
Show all 119 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportSearch Report of Moksh_11zon.pdf · uploaded 17 Sep 2021Source
  • 1 Details of encumbrancesNEC.pdf · uploaded 17 Sep 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentMoksh CC dt 26072021_compressed.pdf · uploaded 17 Sep 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Moksha Architect Certificate_compressed.pdf · uploaded 17 Sep 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Sep 2021Source
  • 1 Disclosure of sold/ booked inventoryDeclaration Sold Unsold_11zon (1).pdf · uploaded 17 Sep 2021Source
  • 1 Proforma of Allotment letterDRAT SALE AGREEMENT FOR MOKSH-converted.pdf · uploaded 17 Sep 2021Source
  • 2 Proforma of Allotment letterAllotment letter of Moksh.pdf · uploaded 17 Sep 2021Source
  • 1 Declaration in FORM BForm B of Promoter Trinity Moksh_compressed.pdf · uploaded 23 Sep 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1st Form 3 Moksh.pdf · uploaded 23 Sep 2021Source
  • 1 Declaration about Commencement CertificateDeclaration for Commencemenr Certificate.pdf · uploaded 4 Oct 2021Source
  • 2 Commencement Certificates / NA Order for plotted development3-5.pdf · uploaded 6 Oct 2021Source
  • 1 Copy of Layout Approval (in case of layout)1-5 MYSCAN_20211009_0005-converted.pdf · uploaded 11 Oct 2021Source
  • 1 Building Plan Approval / NA Order for plotted development2-5 MYSCAN_20211009_0004-converted_compressed.pdf · uploaded 11 Oct 2021Source
  • 2 Building Plan Approval / NA Order for plotted development3-5 MYSCAN_20211009_0003-converted.pdf · uploaded 11 Oct 2021Source
  • 3 Building Plan Approval / NA Order for plotted development4-5 MYSCAN_20211009_0002-converted.pdf · uploaded 11 Oct 2021Source
  • 4 Building Plan Approval / NA Order for plotted development5-5 MYSCAN_20211009_0001-converted.pdf · uploaded 11 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Rattan Raj Lifespaces Form 5 Moksh.pdf · uploaded 21 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2nd Form 1 of Moksh 15122022.pdf · uploaded 3 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3rd Form 1 of Moksh 31032023_11zon.pdf · uploaded 3 Oct 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)4th Form 1 of Moksh 30062023_11zon.pdf · uploaded 3 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2nd Form 2 of Moksh 22122022.pdf · uploaded 3 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)3rd Form 2 of Moksh 31032023_11zon.pdf · uploaded 3 Oct 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)4th Form 2 of Moksh 30062023_11zon.pdf · uploaded 3 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2nd Form 3 of Moksh 23012023_11zon.pdf · uploaded 3 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3rd Form 3 of Moksh 31032023_11zon.pdf · uploaded 3 Oct 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4th Form 3 of Moksh 30062023_11zon.pdf · uploaded 3 Oct 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)4th Form 3 of Moksh 30062023_11zon.pdf · uploaded 3 Oct 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)4th Form 3 of Moksh 30062023_11zon.pdf · uploaded 4 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)From 5 Trinity Mkosh FY 2022-23.pdf · uploaded 21 Nov 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)5th Form 1 of Moksh 30092023.pdf · uploaded 13 Dec 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)5th Form 2 of Moksh 30092023.pdf · uploaded 13 Dec 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)5th Form 3 of Moksh 30092023.pdf · uploaded 13 Dec 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)6th Form 1 of Moksh 31122023_11zon.pdf · uploaded 12 Mar 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)6th Form 2 of Moksh 31122023_11zon.pdf · uploaded 12 Mar 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)6th Form 3 of Moksh 31122023_11zon.pdf · uploaded 12 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)7th Form 1 of Moksh 31032024_11zon.pdf · uploaded 20 Jun 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)7th Form 2 of Moksh 31032024_11zon.pdf · uploaded 20 Jun 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)7th Form 3 of Moksh 31032024_11zon.pdf · uploaded 20 Jun 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)8th Form 1 of Moksh 306062024.pdf · uploaded 16 Aug 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)8th Form 2 of Moksh 306062024_11zon.pdf · uploaded 16 Aug 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)8th Form 3 of Moksh 306062024_11zon.pdf · uploaded 16 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)9th Form 1 of Moksh 306092024_11zon.pdf · uploaded 7 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)9th Form 3 of Moksh 306092024_11zon.pdf · uploaded 7 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)9th Form 2 of Moksh 306092024_11zon.pdf · uploaded 7 Nov 2024Source
  • 1 Disclosure of sold/ booked inventorySold Unsold_11zon.pdf · uploaded 28 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A 3rd 31032024_11zon.pdf · uploaded 28 Nov 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A 4th 30062024_11zon.pdf · uploaded 28 Nov 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A 5th 30092024_11zon.pdf · uploaded 28 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)From 5 Trinity Moksh FY 2022-23.pdf · uploaded 16 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form-5 of Trinity Moksh FY 2023-24_compressed.pdf · uploaded 16 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)10th Form 1 of Moksh 31122024_11zon.pdf · uploaded 14 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)10th Form 3 of Moksh 31122024_11zon.pdf · uploaded 14 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)10th Form 2 of Moksh 31122024_11zon.pdf · uploaded 14 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold 31122024_11zon.pdf · uploaded 11 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A 6th 31122024_11zon.pdf · uploaded 11 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)10th Form 3 Revised of Moksh 31122024_11zon.pdf · uploaded 27 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Dec-2022_4_11zon.pdf · uploaded 27 Mar 2025Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Jun-2022_7_11zon.pdf · uploaded 27 Mar 2025Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Sep-2022_12_11zon.pdf · uploaded 27 Mar 2025Source
  • 4 Disclosure of sold/ booked inventorySold Unsold Mar-2023_10_11zon.pdf · uploaded 27 Mar 2025Source
  • 5 Disclosure of sold/ booked inventorySold Unsold Jun-2023_8_11zon.pdf · uploaded 27 Mar 2025Source
  • 6 Disclosure of sold/ booked inventorySold Unsold Sep-2023_13_11zon.pdf · uploaded 27 Mar 2025Source
  • 7 Disclosure of sold/ booked inventorySold Unsold Dec-2023_5_11zon.pdf · uploaded 27 Mar 2025Source
  • 8 Disclosure of sold/ booked inventorySold Unsold Mar-2024_11_11zon.pdf · uploaded 27 Mar 2025Source
  • 9 Disclosure of sold/ booked inventorySold Unsold Jun-2024_9_11zon.pdf · uploaded 27 Mar 2025Source
  • 10 Disclosure of sold/ booked inventorySold Unsold Sep-2024_14_11zon.pdf · uploaded 27 Mar 2025Source
  • 11 Disclosure of sold/ booked inventorySold Unsold Dec-2024_6_11zon.pdf · uploaded 27 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A for FY 2021-22_11zon.pdf · uploaded 27 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A for FY 2022-23_11zon.pdf · uploaded 27 Mar 2025Source
  • 1 Declaration in FORM BForm-B Developers.pdf · uploaded 29 Mar 2025Source
  • 1 Other – TechnicalPERT Chart.pdf · uploaded 3 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Mar-2025_11zon.pdf · uploaded 8 Apr 2025Source
  • 1 Other – TechnicalP51700031260_FileName_2.pdf · uploaded 9 Apr 2025Source
  • Form 111th Form 1 of Moksh 31032025_11zon.pdf · uploaded 2 Jun 2025Source
  • Form 211th Form 2 of Moksh 31032025_11zon.pdf · uploaded 2 Jun 2025Source
  • Form 311th Form 3 of Moksh 31032025_11zon.pdf · uploaded 2 Jun 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Mar-2025_11zon.pdf · uploaded 2 Jun 2025Source
  • Others2A for FY 2024-25.pdf · uploaded 2 Jun 2025Source
  • Form 112th Form 1 of Moksh 30062025_11zon.pdf · uploaded 5 Aug 2025Source
  • Form 212th Form 2 of Moksh 30062025_11zon.pdf · uploaded 5 Aug 2025Source
  • Form 312th Form 3 of Moksh 30062025_11zon.pdf · uploaded 5 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Jun-2025_11zon.pdf · uploaded 5 Aug 2025Source
  • Form 5 (FY 2024-2025)FY 2024-25 Rattan raj lifespaces.pdf · uploaded 12 Nov 2025Source
  • Withdrawal Update Form 113th Form 1 of Moksh 30092025_compressed.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 213th Form 2 of Moksh 30092025.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 313th Form 3 of Moksh 30092025.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 114th Form 1 of Moksh 31122025_11zon.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 214th Form 2 of Moksh 31122025_11zon.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 314th Form 3 of Moksh 31122025.pdf · uploaded 20 Jan 2026Source
  • Form 2A (FY 2024-2025)Form 2A FY 2024-25_11zon.pdf · uploaded 14 Mar 2026Source
  • Withdrawal Update Form 115th Form 1 of Moksh 31032026_11zon.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 215th Form 2 of Moksh 31032026_11zon.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 316th Form 3 of Moksh 31032026_11zon.pdf · uploaded 25 Apr 2026Source
  • Form 2A (FY 2025-2026)2A For FY 2025-26_11zon (1).pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 117th Form 1 of Moksh 30062026_11zon.pdf · uploaded 3 Aug 2026Source
  • Withdrawal Update Form 217th Form 2 of Moksh 30062026_11zon.pdf · uploaded 3 Aug 2026Source
  • Withdrawal Update Form 317th Form 3 of Moksh 30062026.pdf · uploaded 3 Aug 2026Source

Technical

  • Document1-5 MYSCAN_20211009_0005-converted.pdf · uploaded 11 Oct 2021Source
  • Document2-5 MYSCAN_20211009_0004-converted_compressed.pdf · uploaded 11 Oct 2021Source
  • Document3-5 MYSCAN_20211009_0003-converted.pdf · uploaded 11 Oct 2021Source
  • Document4-5 MYSCAN_20211009_0002-converted.pdf · uploaded 11 Oct 2021Source
  • Document5-5 MYSCAN_20211009_0001-converted.pdf · uploaded 11 Oct 2021Source
  • Other – TechnicalPERT Chart.pdf · uploaded 3 Apr 2025Source
  • Other – TechnicalP51700031260_FileName_2.pdf · uploaded 9 Apr 2025Source

Technical (Architect)

  • Document9th Form 1 of Moksh 306092024_11zon.pdf · uploaded 7 Nov 2024Source
  • Document10th Form 1 of Moksh 31122024_11zon.pdf · uploaded 14 Feb 2025Source
  • Document17th Form 1 of Moksh 30062026_11zon.pdf · uploaded 3 Aug 2026Source

Technical (Engineer)

  • Document9th Form 2 of Moksh 306092024_11zon.pdf · uploaded 7 Nov 2024Source
  • Document10th Form 2 of Moksh 31122024_11zon.pdf · uploaded 14 Feb 2025Source
  • Document17th Form 2 of Moksh 30062026_11zon.pdf · uploaded 3 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ambarnath(M Cl), Ambarnath taluka

Survey, CTS, gat or plot numbers

64 2S NO 64 1

Boundaries

North
24 Mtr Dp Road Plot No 1
South
60 Mtr Midc Pipeline Road Plot No 4
East
18 Mtr Dp Road S No 63 1 2
West
Adj S No 64 3 And S No 64 5

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPiyush N Bansal—
Chartered accountantMamta Watwani—
Chartered accountantVijay Kavrani—
EngineerAtul Kudtarkar—
EngineerMahesh Bhoir—
OtherDharmendra Mall—

Source: MahaRERA project page. Contact details are not shown.