IDBLD_0678877 floorsExtended 4 mo
7Sanctioned habitable floorsregistration certificate
31 Jul 2028Revised completionpromised 31 Mar 2028
11 of 20Units bookedMahaRERA project page

Floors

7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52600056113 · registered 11 May 2024
Promised completion
31 Mar 2028
Revised completion
31 Jul 2028
Sanctioned habitable floors
7
ProjectId
44,516
ProjectName
CENTRE COURT
TotalUnitCount
0
ProjectBuildingId
1,21,002
BuildingNameNumber
A Building
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52600056113
ProjectBuildingWingsId
1,24,419
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
A Building
NoOfBuildingWingFloorProposed
7
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
7

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
Hall No 402 1RK97 m² (1,044 sq.ft)11
Office No 101496.3 m² (5,342 sq.ft)10
Office No 201228.4 m² (2,459 sq.ft)10
Office No 202240.3 m² (2,587 sq.ft)10
Office No 30155.3 m² (596 sq.ft)10
Office No 30297.3 m² (1,048 sq.ft)10
Office No 30372.2 m² (777 sq.ft)10
Office No 304138.4 m² (1,490 sq.ft)11
Office No 30598.6 m² (1,061 sq.ft)11
Office No 40155.3 m² (596 sq.ft)11
Show all 20 unit typesShow fewer unit types
TypeCarpet areaUnitsBooked
Office No 40372.2 m² (777 sq.ft)11
Office No 40451.7 m² (557 sq.ft)11
Office No 40565.5 m² (705 sq.ft)11
Office No 40650.5 m² (544 sq.ft)11
Office No 40746.3 m² (498 sq.ft)11
Shop No 0135.2 m² (379 sq.ft)11
Shop No 0296.9 m² (1,043 sq.ft)11
Shop No 0369.1 m² (743 sq.ft)10
Shop No 0490.3 m² (971 sq.ft)10
Shop No 05116.9 m² (1,258 sq.ft)10
Total2011