Adityasagar Complex

Completion due Dec 2026

Vabhave, Sindhudurg 416810 |Promoter: Siddhesh Mahadeo Kanade

7 Sep 2017Registered with MahaRERAFirst of 2 registrations
30 Dec 2026Promised completionLatest across registrations
31 Dec 2019Revised completion1 of 2 registrations pushed back, by up to 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 16.49831, 73.74549
Adityasagar Complex is at latitude 16.49831, longitude 73.74549.

Also registered as

Adityasagar Complex Phase II
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P52900012910

The latest completion date on record passed 6 years and 10 months ago.

Registered
7 Sep 2017
Promised
31 Dec 2018
Revised
31 Dec 2019

Completion promised for 30 Dec 2026

P52900029896
Registered
12 Jul 2021
Promised
30 Dec 2026

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P529000129107 Sep 201731 Dec 201831 Dec 2019Siddhesh Mahadeo KanadeProject page
P5290002989612 Jul 202130 Dec 2026—Siddhesh Mahadeo KanadeProject page

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificateP52900012910 · 7 Sep 2017ViewSource
  • Registration certificateP52900029896 · 20 Aug 2026ViewSource

Extension certificate

  • Extension certificateP52900012910 · 4 Jan 2019ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Vabhave

Survey, CTS, gat or plot numbers

C S No 38A/3AR.S.No. 38A Hissa No. 3A

Source: registration certificates, as stated there.