IDBLD_0455984 floorsPromised date passed
4Sanctioned habitable floorsregistration certificate
30 Dec 2021Revised completionpromised 30 Dec 2021
25 of 32Units bookedMahaRERA project page

Floors

4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52900010548 · registered 31 Aug 2017
Promised completion
30 Dec 2021
Revised completion
30 Dec 2021
Sanctioned habitable floors
4
ProjectId
4,220
ProjectName
Shivaji Park
TotalUnitCount
0
ProjectBuildingId
1,185
BuildingNameNumber
A
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52900010548
ProjectBuildingWingsId
1,185
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
A
NoOfBuildingWingFloorProposed
4
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
4

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1 BHK42.8 m² (461 sq.ft)88
1BHK47.6 m² (512 sq.ft)86
1BHK51.3 m² (552 sq.ft)1611
Total3225