Sandhyanand Homes
Certificate SignedKasal, Sindhudurg 416603 |Promoter: Anand Laxman Dicholkar
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, Office space, Shop22 units in all
- Address
- S No 36a / 18, Pawnai Ravalnath Mandir Road, Opp Maruti Mandir, Bazarpeth KasalPIN 416603
- Designated bank account
- 82
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2023
The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 17 Jan 2022
- Promised
- 31 Dec 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52900032618 | 17 Jan 2022 | 31 Dec 2023 | 31 Dec 2023 | Anand Laxman Dicholkar | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Sandhyanand Homes | 5 | 22 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 22 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.15 sq m · 368 sq ft | 6 | 0 |
| 1BHK | 34.87 sq m · 375 sq ft | 6 | 0 |
| Office space | 7.2 sq m · 78 sq ft | 2 | 0 |
| Office space | 8.41 sq m · 91 sq ft | 2 | 0 |
| Office space | 12.32 sq m · 133 sq ft | 1 | 0 |
| Office space | 15.06 sq m · 162 sq ft | 1 | 0 |
| Shop | 8.8 sq m · 95 sq ft | 2 | 0 |
| Shop | 12.36 sq m · 133 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 54 filings listed on MahaRERA's project page
Finance
- PAN CardPANCARD.pdf · uploaded 24 Dec 2021Source
Legal
Show all 55 documentsShow fewer documents
Migrated
- 2 Copy of the legal title reportSEARCH REPORT_11zon (1).pdf · uploaded 24 Dec 2021Source
- 1 Details of encumbrancesNIL ENCUMBRANCE CERTIFICATE_001.pdf · uploaded 24 Dec 2021Source
- 1 Copy of Layout Approval (in case of layout)PLAN COPY_11zon (1).pdf · uploaded 24 Dec 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentSANCTION OF PLAN_11zon LETTER.pdf · uploaded 24 Dec 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentSANCTION OF PLAN_11zon LETTER.pdf · uploaded 24 Dec 2021Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE_001.pdf · uploaded 24 Dec 2021Source
- 1 Declaration in FORM BAFFIDAVIT FORM - B_11zon.pdf · uploaded 24 Dec 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE - FORM 1_11zon.pdf · uploaded 24 Dec 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE - FORM 2_11zon.pdf · uploaded 24 Dec 2021Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD-BOOKED INVENTORY_001.pdf · uploaded 24 Dec 2021Source
- 1 CERSAI detailsCERSAI_Search_Report_200226545986_For_Asset_Based_Search_24_12_2021_13_32_33_678.pdf · uploaded 24 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3_11zon.pdf · uploaded 24 Dec 2021Source
- 1 Proforma of Allotment letterAGREEMENT FOR SALE RERA.pdf · uploaded 24 Dec 2021Source
- 1 OtherAADHARCARD.pdf · uploaded 24 Dec 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERT.pdf · uploaded 10 Apr 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGG CERT.pdf · uploaded 10 Apr 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA REPORT.pdf · uploaded 10 Apr 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)DECHOLKAR ARCH CERTI_UPL.pdf · uploaded 10 Jul 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)DECHOLKAR ENG CERTI_UPL.pdf · uploaded 10 Jul 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)DICHOLKAR CA CERTI_UPL.pdf · uploaded 10 Jul 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT FORM 1 SANDHYANAND.pdf · uploaded 19 Oct 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE S.pdf · uploaded 19 Oct 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sandhyanand Homes.pdf · uploaded 19 Oct 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM I.pdf · uploaded 28 Jan 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM II.pdf · uploaded 28 Jan 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM III.pdf · uploaded 28 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FY 2021-22 Form 5.pdf · uploaded 24 Feb 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 21 Apr 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 21 Apr 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 11 May 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH CERT FORM 1.pdf · uploaded 24 Jul 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG CERT FORM 2.pdf · uploaded 24 Jul 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG CERT FORM 2.pdf · uploaded 24 Jul 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)SCAN with Sign.pdf · uploaded 26 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form5.pdf · uploaded 12 Oct 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Sept-23.pdf · uploaded 18 Oct 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 Sept-23.pdf · uploaded 18 Oct 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM- 3 Sept-23.pdf · uploaded 18 Oct 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentRera OC Certificate.pdf · uploaded 23 Jan 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDakhla.PDF · uploaded 30 Jan 2024Source
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate- Revised.PDF · uploaded 2 Feb 2024Source
- 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate- Revised.PDF · uploaded 2 Feb 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM- 4.PDF · uploaded 23 Feb 2024Source
Technical
Technical (Architect)
- DocumentForm-1 Sept-23.pdf · uploaded 18 Oct 2023Source
Technical (Engineer)
- DocumentFORM -2 Sept-23.pdf · uploaded 18 Oct 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Kasal, Kudal taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- H No 9 And 14
- South
- 9 M Wide Road
- East
- H No 13
- West
- H No 7 And 22
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar V N Kamat | — |
| Chartered accountant | Mangilal M Jain | — |
| Engineer | Ar V N Kamat | — |
Source: MahaRERA project page. Contact details are not shown.