Daffodil · Kst Central Park

Malkapur (Np) · RERA P52700080301

IDBLD_0901657 floorsExtended 4 mo
7Sanctioned habitable floorsregistration certificate
7 Apr 2031Revised completionpromised 7 Dec 2030
0 of 28Units bookedMahaRERA project page

Floors

7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52700080301 · registered 19 May 2025
Promised completion
7 Dec 2030
Revised completion
7 Apr 2031
Sanctioned habitable floors
7
ProjectId
55,996
ProjectName
KST CENTRAL PARK
TotalUnitCount
28
ProjectBuildingId
1,78,585
BuildingNameNumber
DAFFODIL
FsiWithSanctionSqmts
STILT +7
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
28
ProjectRegistartionNo
P52700080301
ProjectBuildingWingsId
1,82,301
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
DAFFODIL
NoOfBuildingWingFloorProposed
8
NoOfBuildingWingFloorHabitable
7
NoOfBuildingWingFloorSanctioned
8

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK86.1 m² (927 sq.ft)90
3BHK111 m² (1,195 sq.ft)100
LANDOWNER 2 BHK86.1 m² (927 sq.ft)50
LANDOWNER 3 BHK111 m² (1,195 sq.ft)40
Total280
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology