03 · RutuGandh Mahabaleshwar

Gogave · RERA P52700023106

IDBLD_0802851 floorExtended 4 mo
1Sanctioned habitable floorsregistration certificate
30 Oct 2028Revised completionpromised 30 Jun 2028
0 of 2Units bookedMahaRERA project page

Floors

1 sanctioned habitable floor, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52700023106 · registered 2 Dec 2019
Promised completion
30 Jun 2028
Revised completion
30 Oct 2028
Sanctioned habitable floors
1
ProjectId
26,594
ProjectName
RutuGandh Mahabaleshwar-2
TotalUnitCount
1
ProjectBuildingId
1,45,058
BuildingNameNumber
03
FsiWithSanctionSqmts
2
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
1
ProjectRegistartionNo
P52700023106
ProjectBuildingWingsId
1,48,475
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
03
NoOfBuildingWingFloorProposed
2
NoOfBuildingWingFloorHabitable
1
NoOfBuildingWingFloorSanctioned
2

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
3BHK108.8 m² (1,171 sq.ft)10
3BHK126.3 m² (1,359 sq.ft)10
Total20