RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P99000001847

Indraprasth Complex · Palghar · Swastik Developers

Promised for 31 Jan 2019, extended once to 30 Apr 2022 — and that date has passed without the project marked complete on MahaRERA.

7 years and 9 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2019 to 30 Apr 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Apr 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate29 Jul 2017View
Extension certificate8 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000001847

Is Indraprasth Complex delayed?

Yes. MahaRERA records a promised completion of 31 Jan 2019, revised to 30 Apr 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000001847. The completion date moved from 31 Jan 2019 to 30 Apr 2022.

Who is the promoter?

MahaRERA records Swastik Developers as the promoter of P99000001847.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000001847.

Answers are generated from the record.

Data through25 Oct 2026, 01:52SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology