Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52900051854

Suvidha Suryakant Complex · Kasai, Sindhudurg · Bahar Dasharath Bhosale

Promised for 30 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.

10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: The latest completion date on record, 30 Dec 2025, has passed.

Documents 1

Registration certificate7 Jul 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P52900051854

Is Suvidha Suryakant Complex delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52900051854.

Who is the promoter?

MahaRERA records Bahar Dasharath Bhosale as the promoter of P52900051854.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52900051854.

Answers are generated from the record.

Data through22 Oct 2026, 01:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology