Pushpajal Apt. · Satara · Jagtap Pawar & Associates
Promised for 28 Aug 2018, extended once to 30 Sep 2020 — and that date has passed without the project marked complete on MahaRERA.
8 years and 2 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 28 Aug 2018 to 30 Sep 2020 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Sep 2020, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52700005094
Is Pushpajal Apt. delayed?
Yes. MahaRERA records a promised completion of 28 Aug 2018, revised to 30 Sep 2020, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52700005094. The completion date moved from 28 Aug 2018 to 30 Sep 2020.
Who is the promoter?
MahaRERA records Jagtap Pawar & Associates as the promoter of P52700005094.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52700005094.