Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100025160

45 Baner Street · Baner, Pune · Raichandani Constructions And Developers

Promised for 28 Nov 2023, extended once to 30 Jul 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 28 Nov 2023 to 30 Jul 2024 (1 extension certificate on record).
  • Caution: The latest completion date on record, 30 Jul 2024, has passed.

Documents 2

Registration certificate17 Jan 2024View
Extension certificate20 Aug 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100025160

Is 45 Baner Street delayed?

Yes. MahaRERA records a promised completion of 28 Nov 2023, revised to 30 Jul 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100025160. The completion date moved from 28 Nov 2023 to 30 Jul 2024.

Who is the promoter?

MahaRERA records Raichandani Constructions And Developers as the promoter of P52100025160.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100025160.

Answers are generated from the record.

Data through24 Oct 2026, 02:18SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology