Registered1 extensionMahaRERA status: Certificate Signed

P52100024300

Silver Wisteria · Chikhali, Pune · Shiv Prapti Buildcon

Promised for 31 Dec 2027, extended once to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028 (1 extension certificate on record).

Documents 2

Extension certificate20 Aug 2026View
Registration certificate24 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100024300

Is Silver Wisteria delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100024300. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records Shiv Prapti Buildcon as the promoter of P52100024300.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100024300.

Answers are generated from the record.

Data through25 Oct 2026, 02:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology