Rajyog Royal · Pimpale Gurav, Pune · Rajyog Builders And Developers
Promised for 30 Jun 2021, extended once to 30 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.
5 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2021 to 30 Dec 2022 (1 extension certificate on record).
- !Caution: The latest completion date on record, 30 Dec 2022, has passed.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100013691
Is Rajyog Royal delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 30 Dec 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100013691. The completion date moved from 30 Jun 2021 to 30 Dec 2022.
Who is the promoter?
MahaRERA records Rajyog Builders And Developers as the promoter of P52100013691.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100013691.