RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100010952

Lalbag Prestige · Manchar (Ct), Pune · Reliable Construction

Promised for 31 Dec 2019, extended once to 30 Dec 2021 — and that date has passed without the project marked complete on MahaRERA.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 30 Dec 2021 (1 extension certificate on record).
  • Caution: The latest completion date on record, 30 Dec 2021, has passed.

Documents 2

Registration certificate31 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100010952

Is Lalbag Prestige delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100010952. The completion date moved from 31 Dec 2019 to 30 Dec 2021.

Who is the promoter?

MahaRERA records Reliable Construction as the promoter of P52100010952.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100010952.

Answers are generated from the record.

Data through24 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology