RegisteredExtendedMahaRERA status: Certificate Signed

P51800054935

Ruparel Celestia · Mulund, Mumbai Suburban · Aadarsh Developers

Promised for 31 Dec 2026, extended to 30 Apr 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2026 to 30 Apr 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate21 Feb 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800054935

Is Ruparel Celestia delayed?

Its completion moved from 31 Dec 2026 to 30 Apr 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800054935. The completion date moved from 31 Dec 2026 to 30 Apr 2027.

Who is the promoter?

MahaRERA records Aadarsh Developers as the promoter of P51800054935.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800054935.