Skip to content
Deedo home
Menu

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700029253

Rhytham Co Op Housing Society Ltd · Ambarnath (R), Thane · Telange Builders & Developers Private Limited

Promised for 25 Feb 2023, extended once to 29 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.

3 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 25 Feb 2023 to 29 Dec 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Dec 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate10 May 2021View
Extension certificate6 Aug 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700029253

Is Rhytham Co Op Housing Society Ltd delayed?

Yes. MahaRERA records a promised completion of 25 Feb 2023, revised to 29 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700029253. The completion date moved from 25 Feb 2023 to 29 Dec 2023.

Who is the promoter?

MahaRERA records Telange Builders & Developers Private Limited as the promoter of P51700029253.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700029253.

Answers are generated from the record.

Data through25 Oct 2026, 02:53SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology