P51700005374

Metro Highland Phase I · Ambarnath(M Cl), Thane · Metro Developers

Promised for 24 Jan 2019, extended once to 30 Jun 2019 — and that date has passed without the project marked complete on MahaRERA.

7 years and 9 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 24 Jan 2019 to 30 Jun 2019 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2019, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate11 Aug 2017View
Extension certificate15 Feb 2019View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700005374

Is Metro Highland Phase I delayed?

Yes. MahaRERA records a promised completion of 24 Jan 2019, revised to 30 Jun 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700005374. The completion date moved from 24 Jan 2019 to 30 Jun 2019.

Who is the promoter?

MahaRERA records Metro Developers as the promoter of P51700005374.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700005374.

Answers are generated from the record.

Data through25 Oct 2026, 02:01SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology