Skip to content

Meghna Seven

Certificate Signed

Rohinjan, Raigarh 410206 |Promoter: Meghna Builders

26 Aug 2022Registered with MahaRERA
31 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
1Building
62Units registered38 booked (61%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Shop62 units in all
Address
13/1, 14/4, 14/5a, 13/1, 14/4, 1 4/5a, RohinjanPIN 410206
Designated bank account
220
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
26 Aug 2022
Promised
31 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200004666126 Aug 202231 Dec 202630 Apr 2027Meghna BuildersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Meghna Seven1562

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

38 of 62 units booked (61%), as the promoter reported to MahaRERA

1BHK · 26 units2BHK · 32 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1BHK38.05 sq m · 410 sq ft1810
1BHK38.33 sq m · 413 sq ft87
2BHK48.92 sq m · 527 sq ft10
2BHK49.46 sq m · 532 sq ft21
2BHK49.56 sq m · 533 sq ft76
2BHK50.32 sq m · 542 sq ft66
2BHK51.25 sq m · 552 sq ft72
2BHK53.56 sq m · 577 sq ft65
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK53.71 sq m · 578 sq ft11
2BHK54.53 sq m · 587 sq ft10
2BHK62.4 sq m · 672 sq ft10
Shop50.69 sq m · 546 sq ft10
Shop62.29 sq m · 670 sq ft10
Shop64.18 sq m · 691 sq ft10
Shop81.75 sq m · 880 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 53 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 19 Jul 2022Source

Legal

  • Legal Title reportLEGAL TITTLE AND SEARCH REPORT 1 TO 11.pdf · uploaded 19 Jul 2022Source
  • Legal Title reportLEGAL TITTLE AND SEARCH REPORT 12 TO 20.pdf · uploaded 19 Jul 2022Source
  • Legal Title reportLEGAL TITTLE AND SEARCH REPORT 21TO 30.pdf · uploaded 19 Jul 2022Source
  • Legal Title reportLEGAL TITTLE AND SEARCH REPORT 31TO 33.pdf · uploaded 19 Jul 2022Source
  • Declaration Form BFORM B DEVELOPERS.pdf · uploaded 19 Jul 2022Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 19 Jul 2022Source
Show all 54 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportLEGAL TITTLE AND SEARCH REPORT 1 TO 11.pdf · uploaded 19 Jul 2022Source
  • 2 Copy of the legal title reportLEGAL TITTLE AND SEARCH REPORT 12 TO 20.pdf · uploaded 19 Jul 2022Source
  • 3 Copy of the legal title reportLEGAL TITTLE AND SEARCH REPORT 21TO 30.pdf · uploaded 19 Jul 2022Source
  • 4 Copy of the legal title reportLEGAL TITTLE AND SEARCH REPORT 31TO 33.pdf · uploaded 19 Jul 2022Source
  • 1 a Details of encumbrances concerned to FinanceDETAILS OF ENCUMBRANCE.pdf · uploaded 19 Jul 2022Source
  • 1 Copy of Layout Approval (in case of layout)CC PLAN 1.pdf · uploaded 19 Jul 2022Source
  • 2 Copy of Layout Approval (in case of layout)CC PLAN 2.pdf · uploaded 19 Jul 2022Source
  • 3 Copy of Layout Approval (in case of layout)CC PLAN 3.pdf · uploaded 19 Jul 2022Source
  • 4 Copy of Layout Approval (in case of layout)CC PLAN 4.pdf · uploaded 19 Jul 2022Source
  • 5 Copy of Layout Approval (in case of layout)CC PLAN 5.pdf · uploaded 19 Jul 2022Source
  • 6 Copy of Layout Approval (in case of layout)CC PLAN 6.pdf · uploaded 19 Jul 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentCC PLAN 1.pdf · uploaded 19 Jul 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentCC PLAN 2.pdf · uploaded 19 Jul 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentCC PLAN 3.pdf · uploaded 19 Jul 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentCC PLAN 4.pdf · uploaded 19 Jul 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentCC PLAN 5.pdf · uploaded 19 Jul 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentCC PLAN 6.pdf · uploaded 19 Jul 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Order 1 TO 4.pdf · uploaded 19 Jul 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Order 5 TO 7.pdf · uploaded 19 Jul 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC Order 8 TO 10.pdf · uploaded 19 Jul 2022Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 19 Jul 2022Source
  • 1 Declaration in FORM BFORM B DEVELOPERS.pdf · uploaded 19 Jul 2022Source
  • 1 CERSAI detailsCRESAI DETAILS.pdf · uploaded 19 Jul 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM 3.pdf · uploaded 19 Jul 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPERATE BANK ACCOUNT DETAILS.pdf · uploaded 19 Jul 2022Source
  • 1 Deviation Report with respect to Allotment letterDEVITATION REPORTS WITH ALLOTMENT LETTER.pdf · uploaded 3 Aug 2022Source
  • 1 b Details of encumbrances concerned to LegalNO ENCUMBRANCES LETTER.pdf · uploaded 13 Aug 2022Source
  • 1 Proforma of Allotment letterDRAFT AGREEMENT TO SALE.pdf · uploaded 13 Aug 2022Source
  • 2 Proforma of Allotment letterDRAFT ALLOTMENT LETTER.pdf · uploaded 13 Aug 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDEVITATION REPORTS WITH AGREEMENT FOR SALE (1).pdf · uploaded 13 Aug 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEGHNA SEVEN.pdf · uploaded 30 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3 with sign_compressed.pdf · uploaded 20 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 20 Apr 2025Source

Technical

  • DocumentCC PLAN 1.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 2.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 3.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 4.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 5.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 6.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 1.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 2.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 3.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 4.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 5.pdf · uploaded 19 Jul 2022Source
  • DocumentCC PLAN 6.pdf · uploaded 19 Jul 2022Source

Technical (Architect)

  • DocumentFORM 1 MEGHNA SEVEN.pdf · uploaded 30 Nov 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Rohinjan, Panvel taluka

Survey, CTS, gat or plot numbers

13/114/414/5A

Boundaries

North
Survey No 13 1
South
Survey No 14 5
East
Survey No 14 5
West
Survey No 14 2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNeha Jain—
Chartered accountantagrawal vikas and co—
EngineerMehul Munnabhai Dhudhat—
Registered real estate agentK R Jairam—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology