Lig-11 Floors-15 Phase-I · Sector 21 Taloja
Pendhar · RERA P52000017439
IDBLD_01412115 floorsExtended 18 mo
15Sanctioned habitable floorsregistration certificate
30 Sep 2022Revised completionpromised 31 Mar 2021
42 of 90Units bookedMahaRERA project page
Floors
15 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52000017439 · registered 13 Aug 2018
- Promised completion
- 31 Mar 2021
- Revised completion
- 30 Sep 2022
- Sanctioned habitable floors
- 15
- ProjectId
- 19,340
- ProjectName
- SECTOR 21 TALOJA
- TotalUnitCount
- 0
- ProjectBuildingId
- 19,607
- BuildingNameNumber
- LIG-11 FLOORS-15 PHASE-I
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52000017439
- ProjectBuildingWingsId
- 19,607
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- LIG-11 FLOORS-15 PHASE-I
- NoOfBuildingWingFloorProposed
- 15
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 15
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| LIG RESIDENTIAL | 29.8 m² (321 sq.ft) | 90 | 42 |
| Total | 90 | 42 |
Data through12 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology